Green Briar Drainage Dist. v. Clark

292 F. 828, 1923 U.S. App. LEXIS 3021
CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 17, 1923
DocketNo. 3227
StatusPublished
Cited by8 cases

This text of 292 F. 828 (Green Briar Drainage Dist. v. Clark) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green Briar Drainage Dist. v. Clark, 292 F. 828, 1923 U.S. App. LEXIS 3021 (7th Cir. 1923).

Opinion

.ALSCHULER, Circuit Judge.

Defendant in error Clark contracted-in writing to construct for plaintiff in error (a drainage district organized under the Illinois drainage statutes) certain ditches and levees in accordance with specifications and profiles, at the price of 13% cents per cubic yard of earth moved by Clark. The main controversy arises o-ver his right of recovery for something over 200,000 cubic yards of earth he claims to have moved in excess of the original estimate of somewhat under 600,000 yards; also over the question of damages-claimed by Clark to have accrued to him through failure to the district to make certain initial and subsequent payments to him as required by the contract.

Clark claims substantial performance of the contract, and that its-full completion was prevented by plaintiff in error’s engineer and com[829]*829missioners taking possession of his dredge boats and preventing his giving it the final touches. He contends that his removal of earth, far in excess of the estimate in the proceedings for organizing the district and assessment of benefited lands, and in the contract, was by order of the commissioners of the district and its engineer, under whose direction the contract required him to do his work, and that he did the work only in accordance with the stakes they set for his guidance, and that whatever increase there was in the yardage was occasioned by his following strictly the directions of the commissioners and engineer.

The action was i® assumpsit, and it was charged that there was about $25,000 due Clark for yardage, and another count charged loss and damage of $25,000 for failure of the district to advance funds, and cause estimates to be made, and to make partial payments, all as required by the contract; and a third count charges damage of $3,000 through being improperly required to move his dredge boat. A general verdict of $30,000 was rendered in favor of Clark, and judgment awarded therefor.

It is the contention for the district that, being a municipal corporation organized for a specific purpose, there was no authority in its officials to depart substantially from the specifications whereon the original estimates were made.

Upon the organization of the district the statute requires estimate to be made of the cost of the improvement and of the benefits to the lands proposed to be assessed therefor, and if the benefits are less than the cost the improvement may not be proceeded with. For this improvement it was estimated that about 600,000 yards of earth would have to be moved at an estimated cost of 12 cents per yard. It does not appear that the profiles and specifications made as the basis of the estimates were erroneous, but it does appear from the evidence that the amount of earth which Clark actually moved was upwards of 800,-000 yards — a rather startling excess over the estimate.

The law makes allowance for inaccuracies and contingencies, though it would not justify by way of excess or otherwise additional work which was not reasonably contemplated by the original proceedings. The very fact that the contract called for payment by the cubic yard rather than by fixing a definite sum would indicate that no hard and fast aggregate figure was intended, but that the reasonable necessities of the case should determine how much earth, would be moved to properly carry out the improvement. So also as to price, it cannot certainly be known that contracts within the estimated price can be let. Indeed, in this case the contract price per yard was 12% per cent, in excess of the estimated cost. While it would be difficult to lay down general rules applicable alike to all cases, it may here well be said that if the additional yardage was found to be reasonably within the contemplated improvement, and was authorized by those in charge of the work for the district, recovery therefor might be justified, notwithstanding the very considerable excess in yardage over the estimate.

Circumstances suggest themselves under which embarrassing questions might arise, not necessary now to be considered. For instance, if with the. materially larger cost than as estimated it should be found [830]*830that the total cost exceeds the benefit to the lands to be assessed for its payment, to what extent would a judgment be availing if for its payment resort can be had only to further assessment of the same lands; and, perhaps, the further question whether, if the funds of the district are exhausted, the judgment could be satisfied in any manner other than by further assessment of the same lands, and by proceedings similar to those under which the original assessment was made.

But assuming that recovery for the excess may be had where it appears that it was duly authorized by the district and was in furtherance of and reasonably within the contemplated improvement, it appears that upon these propositions of fact there was highly contradictory evidence. Clark maintained his work was all strictly within the direction of the district engineer and according to his stakes. This is denied, and it is asserted that much of the alleged excess, far from being authorized by the district, or for its benefit, was done by Clark wholly of his own motion and for his sole benefit — largely to enable him to move his unnecessarily wide dredge boat through the" ditch. In this state of the evidence the court charged the jury as follows:

“The plaintiff is only entitled.to have, if anything, the contract price for the dirt that was actually moved by him; and in determining what was the amount of earth removed by him from the ditch into the levee, or if he was to dig a ditch, the amount of dirt that was moved in digging the ditch— you have the evidence upon these two questions. You have the evidence of the witnesses who have testified in this ease, pro and con, and upon that evidence you are to determine how much dirt went into this levee. It is contended further that more dirt went into the levee than was contemplated or was required by the plans and specifications; this man was operating under the direction of the board of commissioners, through their supervisors or engineers, and if he, by placing stakes, required the plaintiff to build the levee bigger and higher, and to make it more substantial than the plans and specifications required, and he did that in a reasonably fair and workmanlike manner, and substantially complied with these requirements, then the additional height, if any, is not a violation of the rights of the defendant, and the plaintiff would- be entitled to that according to the contract price per unit of dirt removed.”

In charging that “the plaintiff was entitled, to have the contract price for the dirt that was actually moved by him,” the test imposed was only the quantity of earth moved, regardless of' whether the district authorized the excess. The latter part of the charge seems to take it for granted that whatever was done was done under the direction of the commissioners through their supervisors or engineers, thus taking this question from the jury, notwithstanding the sharp dispute in the evidence as to such authorization. But even if authorized by the engineer, unless the jury believed from the evidence that the excess was incidental to and in beneficial furtherance of the improvement, recovery therefor was not permissible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leister v. Dovetail, Inc.
546 F.3d 875 (Seventh Circuit, 2008)
Siegel v. Western Union Telegraph Co.
37 N.E.2d 868 (Appellate Court of Illinois, 1941)
Angleró v. Municipality of Fajardo
50 P.R. 41 (Supreme Court of Puerto Rico, 1936)
Angleró v. Municipio de Fajardo
50 P.R. Dec. 43 (Supreme Court of Puerto Rico, 1936)
O'Rourke Engineering Construction Co. & Duit, Inc. v. City of New York
229 A.D. 261 (Appellate Division of the Supreme Court of New York, 1930)
Alliance Ins. Co. v. Alper-Salvage Co.
19 F.2d 828 (Sixth Circuit, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
292 F. 828, 1923 U.S. App. LEXIS 3021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-briar-drainage-dist-v-clark-ca7-1923.