Great American Homes, Inc. v. Farley

692 S.W.2d 23, 1984 Tenn. App. LEXIS 3284
CourtCourt of Appeals of Tennessee
DecidedNovember 9, 1984
StatusPublished

This text of 692 S.W.2d 23 (Great American Homes, Inc. v. Farley) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great American Homes, Inc. v. Farley, 692 S.W.2d 23, 1984 Tenn. App. LEXIS 3284 (Tenn. Ct. App. 1984).

Opinions

BROOKS McLEMORE, Special Judge.

This case is before us to review the construction of a contract and the amount of credits due under that contract, as well as the method of allowing such credits.

The parties, defendants-sellers and plaintiff-buyer, entered into a contract for the sale of 292 + acres of land, at $4,500.00 per acre, representing a sale price of $1,314,000.00. At the closing, the plaintiff-buyer signed a deferred purchase money promissory note payable to the defendants-sellers in the sum of $1,088,775.00. The real estate sale contract and the applicable provisions of the note, among other things, provide that the plaintiff-buyer is to be credited in that the sale price will be reduced for all costs that may be experienced to raise the land to satisfactory elevations which may be required above the one hundred year flood area. Only a portion of the land was in the flood area, the buyer’s estimate being 90 acres.

The applicable provisions of the real estate sale contract are:

It appears that the land is penalized by the published 100 year flood elevation requirement in the Fletcher Creek basin, this offer is subject to the cost that may be experienced to raise any of the land area to satisfactory elevations which may be required above the 100 year flood area meaning that this cost due to raising the land to the satisfactory elevations will reduce the sales price offered accordingly. All land that has to be used for constructing a ditch to come into compliance with the 100 year flood plain, will be deeded to the purchaser without cost, which is believed to be approximately 10 acres.

The applicable provisions of the promissory note are:

Payment of this note is subject to the applicable conditions of the real estate contract (including its addendum) dated April 16, 1979 between the maker and the beneficiaries of this note. Payment of this note shall be reduced by amount of the costs experienced to raise the land as described in the aforementioned con[25]*25tract to the satisfactory elevations as may be required by the 100 year flood elevation requirement in the Fletcher Creek basin. Payment of this note shall also be reduced when it is determined how much land is in the ditch that must be constructed on the aforementioned land, the amount of acreage in said ditch — will be multiplied by $4,500 per acre and then subtracted from the amount of this note.

It is uncontroverted that the “one hundred year flood plain” is that as designated by the Corps of Engineers’ maps.

It is uncontroverted that some sort of ditch plan was to be used to raise the land above the one hundred year flood area.

Plaintiff-buyer and defendants-sellers entered into the sales contract on April 16, 1979, and closed the transaction on August 21, 1979. On June 9,1980, the buyer made a demand on the sellers for total credits in excess of $800,000.00 against the principal balance of the promissory note in the original sum of $1,088,775.00. This amount being in controversy, on March 17, 1981, a complaint for declaratory judgment was filed by plaintiff-buyer.

It was understood at the hearing that the method to be used by the plaintiff-buyer in raising the land out of the flood plain would be one of a system of lakes rather than by the construction of a ditch. It was also understood at the hearing that this system of lakes would be more expensive than a ditch method. The theory of both parties was that the amount of credits would depend upon the cost of raising the land out of the flood plain by a ditch method, and both parties offered their proof by expert testimony as to this cost. The expert testimony as to the proper method of preparing the ditches was sharply conflicting. There was a wide difference in the cost estimates.

The Chancellor, after evidentiary hearing, approved the method designed by the plaintiff-buyer’s experts, and after considering reports of the Master rendered judgment for credits as follows:

1. 132,560 cubic yards of dirt must be excavated at a cost of $1.25 per cubic yard $165,700.00
2. Invert and slope protection cost is as follows:
(a) Fletcher Creek Slope Protection 35,262 sq. ft. at $3.00 sq. ft. 105,786.00
Gabion Weirs 145 CY at $100 CY 14,500.00
(b) Lateral “A” Slope Protection 29,289 sq. ft. at $3.00 sq. ft. 87,867.00
Gabion Weirs 145 CY at $100 CY 14,500.00
(c) 50% of Lateral “B” Slope Protection 15,062.5 sq. ft. at $3.00 sq. ft. 45,187.50
Gabion Weirs 42.5 CY at $100 CY 4,250.00
3. Clearing and grubbing 21.27 Acres at $1509 per acre 32,096.43
4. Seeding and mulching 21.27 acres 17,836.35
5. A contingency fund of 10% 48,772.32
(a) Sub-total 536,495.60
6. Engineering fees at 6% 32,189.74
7. Sub-total 568,685.34
8. A permanent credit for 21.27 acres to be used in constructing the ditch. This credit to be allowed August 4, 1982 95,715.00
9. A permanent credit for engineering fees paid by plaintiff-buyer exclusive of fees spent in connection with litigation. This credit to be allowed August 4, 1982 12,397,52
10.Grand Total $676,797.86

The Chancellor found after construction of the provisions of the promissory note that the plaintiff-buyer was entitled to credits up to the maximum limit of $568,-685.34 when those costs were actually incurred or experienced. He further found that the anticipated amount to be spent by plaintiff-buyer for the raising of the property out of the flood plain, pursuant to a concept of a series of lakes, dams, and spillways, amounted to $820,189.50. Relating this sum to the maximum sum allowable ($568,685.34), the Chancellor determined that the mathematical percentage the plaintiff-buyer would be entitled to is a credit of sixty-nine per cent for every dollar spent by plaintiff-buyer to bring the property out of the flood plain up to the maximum allowable sum.

[26]*26Defendant-seller states five issues. The first complains that the method approved by the Chancellor in raising the land from the flood plain was erroneous and resulted in excessive credits in that it included the use of Gabion Weirs and Gabion Pads for erosion control.

The contract and the promissory note make no provision for the method by which the ditch is to be constructed to raise the land above the flood plain. In such case, the law of Tennessee implies that the method must be a reasonable one.

Two plans were presented to the Chancellor for removing the land from the flood plain, both plans presented by experts, and the Chancellor found the plan proposed by the plaintiff-buyer to be the reasonable plan.

Specifically the Chancellor found:

... This property lies in an area which the Court can take judicial knowledge of, as well as the proof addressing itself to it, and one of the more prosperous areas of this county ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stovall v. Dattel
619 S.W.2d 125 (Court of Appeals of Tennessee, 1981)
Ohio Casualty Insurance Co. v. Travelers Indemnity Co.
493 S.W.2d 465 (Tennessee Supreme Court, 1973)
Dearing v. Brush Creek Coal Co.
186 S.W.2d 329 (Tennessee Supreme Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
692 S.W.2d 23, 1984 Tenn. App. LEXIS 3284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-american-homes-inc-v-farley-tennctapp-1984.