Graycon Building Group, Inc. v. Med Ridge West

CourtCourt of Appeals of Kansas
DecidedDecember 2, 2022
Docket124361
StatusUnpublished

This text of Graycon Building Group, Inc. v. Med Ridge West (Graycon Building Group, Inc. v. Med Ridge West) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graycon Building Group, Inc. v. Med Ridge West, (kanctapp 2022).

Opinion

NOT DESIGNATED FOR PUBLICATION

No. 124,361

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

GRAYCON BUILDING GROUP, INC., Appellant,

v.

MED RIDGE WEST, LLC, Appellee.

MEMORANDUM OPINION

Appeal from Sedgwick District Court; FAITH A.J. MAUGHAN, judge. Opinion filed December 2, 2022. Reversed and remanded with directions.

Neil C. Gosch, of Triplett Woolf Garretson LLC, of Wichita, for appellant.

Todd E. Shadid and Michael L. Baumberger, of Klenda Austerman LLC, of Wichita, for appellee.

Before WARNER, P.J., HURST, J., and TIMOTHY G. LAHEY, S.J.

PER CURIAM: Graycon Building Group, Inc. (Graycon) appeals a finding by the district court that its mechanic's lien against property owned by Med Ridge West, LLC (MRW) was invalid under K.S.A. 58-4301(e)(2). Following our review of the record, we reverse the ruling of the district court. A district court considering a petition challenging a mechanic's lien under K.S.A. 58-4301 is limited to resolving the question of whether the purported lien is fraudulent, as that term is defined in K.S.A. 58-4301. We find Graycon's lien is not fraudulent under the statutory definition and that any other challenge to the validity of Graycon's mechanic's lien is governed by K.S.A. 60-1101 et seq.

1 FACTUAL AND PROCEDURAL BACKGROUND

On August 27, 2019, MRW contracted with Graycon to build a restaurant on property MRW owned in Wichita, Kansas. A dispute arose between MRW and Graycon regarding the timeliness and quality of Graycon's work and the amount due under the contract. Graycon claimed MRW owed it $284,818.24, while MRW claimed that Graycon owed it $74,051.83. In the parties' contract, the project architect was tasked with serving as an "Initial Decision Maker" when there was a contractual dispute between the parties. MRW asked the project architect to resolve the dispute. Graycon did not participate or submit any documents to the architect, although MRW submitted information it had received from Graycon concerning various aspects of the dispute. The architect determined that after issuance of the architect's final Certificate of Payment, MRW would owe $9,897.15 to Graycon.

Shortly after receiving the architect's determination, Graycon filed a General Contractor's Mechanic's Lien Statement contending that the value of its lien was $216,209.41. Having last provided materials and labor under the MRW contract on October 5, 2020, and having filed a notice of extension, Graycon was required to file a mechanic's lien statement on or before March 5, 2021—the date upon which the lien statement was filed—in order to perfect and preserve its lien rights. See K.S.A. 60-1102 (a) and (c). In response, MRW filed a motion for judicial review of Graycon's "purported mechanic's lien" as authorized by the fraudulent-lien statute, K.S.A. 58-4301. MRW alleged Graycon was "not entitled to payment from [MRW] and therefore [had] no basis to file a lien." MRW requested the court invalidate the lien, find it fraudulent, and direct the clerk to nullify the lien.

The district court reviewed the documents attached to MRW's motion and allowed argument by counsel for the parties. MRW clarified that it was alleging Graycon's lien was fraudulent under K.S.A. 58-4301(e)(2). The district court ruled that Graycon's lien

2 violated K.S.A. 2020 Supp. 58-4301(e)(2), but expressly declined to call it "fraudulent," stating, "I will find that the lien—I won't use the word fraudulent, but it is invalid based on the amount." The district court gave Graycon the option of having its entire lien invalidated or accepting a reduction to $9,897.15—the amount the architect determined Graycon was owed. Graycon chose to accept the reduction.

Graycon filed a motion to reconsider, again arguing that it was improper to use the expedited procedure in K.S.A. 58-4301 to address the merits of the lien, and further argued that the determination by the architect was not final because the contract provided for mediation and binding dispute resolution. Oddly, the form of binding dispute resolution chosen by the parties was also mediation. Nonetheless, the district court agreed, and MRW conceded, the amount due to Graycon could change because the contract provided for mediation following the architect's decision. The district court amended its ruling to find the architect's determination, while "final and binding," was subject to mediation. The district court's decision reducing Graycon's lien remained in effect.

In this timely appeal, Graycon contends the district court exceeded its statutory authority by adjudicating Graycon's lien instead of just determining whether the lien was fraudulent or not. Relying largely on our court's analysis in In re Lien Against the District at City Center, 57 Kan. App. 2d 884, 462 P.3d 181 (2020), Graycon asserts the district court may examine only the question of whether a lien is fraudulent under K.S.A. 58- 4301, and any other question about the validity of the lien must be addressed by applying the procedures in K.S.A. 60-1101 et seq. MRW contends another published opinion from our court, In re Mechanic's Lien Against City of Kansas City, 37 Kan. App. 2d 440, 154 P.3d 515, rev. denied 284 Kan. 946 (2007), permits the district court to address the issues raised by MRW using the expedited procedure in the fraudulent-lien statute.

3 ANALYSIS

Standard of Review

Interpretation of K.S.A. 58-4301 is a legal question reviewed de novo as is the district court's ruling because it was based on documents filed by the parties. City of Kansas City, 37 Kan. App. 2d at 443; see Montgomery v. Saleh, 311 Kan. 649, 654, 466 P.3d 902 (2020). The most fundamental rule of statutory interpretation is the Legislature's intent governs if that intent is ascertainable. Courts first try to determine intent through the statutory language, giving common words their ordinary meaning. 311 Kan. at 654. When a statute is plain and unambiguous, courts do not speculate about the legislative intent behind the clear language and refrain from "reading something into the statute that is not readily found in its words." 311 Kan. at 654-55; see In re M.M., 312 Kan. 872, 874, 482 P.3d 583

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re a Mechanic's Lien Against the City of Kansas City
154 P.3d 515 (Court of Appeals of Kansas, 2007)
Ambrosier v. Brownback
375 P.3d 1007 (Supreme Court of Kansas, 2016)
Glaze v. J.K. Williams, LLC
439 P.3d 920 (Supreme Court of Kansas, 2019)
In re M.M.
482 P.3d 583 (Supreme Court of Kansas, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Graycon Building Group, Inc. v. Med Ridge West, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graycon-building-group-inc-v-med-ridge-west-kanctapp-2022.