Gray v. Cooper

274 S.W. 941, 217 Mo. App. 592, 1925 Mo. App. LEXIS 40
CourtMissouri Court of Appeals
DecidedJuly 1, 1925
StatusPublished
Cited by3 cases

This text of 274 S.W. 941 (Gray v. Cooper) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gray v. Cooper, 274 S.W. 941, 217 Mo. App. 592, 1925 Mo. App. LEXIS 40 (Mo. Ct. App. 1925).

Opinion

*604 COX, P. J.

-Action for damages for breach of contract. Plaintiff recovered and defendant appealed.

Defendant, Cooper, was the owner of a pit of clay described as dias pore clay and burley clay, the latter being of cheaper grade than the former. These parties entered into a written contract, the essential parts of which are as follows:

“That party of the first part for and in consideration of the price and sum hereinafter specified agrees to furnish F. O. B. cars, St. James, Mo., two cars of Dias Pore clay and one car of second or Burley clay, if the cars are furnished when the clay is ordered, and if the cars are not furnished when the clay is ordered then to furnish on the tract (on the ground) for the price and sum of $4 per ton of 2000 pounds for the Dias Pore clay and $1.70 per ton for the second, or Burley clay, R. E. weights to govern, and further, after returns of the aforesaid cars are received and the same proves satisfactory to party of the second part, to furnish F. O. B'. cars, St. James, Mo., twenty-five or more cars and to furnish in proportion of one car of Burley not to exceed two cars of Burley to four of Dias Pore.

Party of the second part agrees to take the above-named three cars of clay, and to ship same as soon as cars can be procured; party of the second part agrees. *605 after returns are received on the above mentioned three cars, and said returns prove satisfactory to give his order to party of the first part for not less than twenty-five cars and to' pay the price and sum above mentioned, and to ship same as fast as cars can be procured.

Party of the second part hereby agrees to pay the price for the clay above mentioned as follows: 50 per cent when clay is loaded, and balance when returns are received from each shipment.

Party of the second part further agrees to give to party of the first part a written guarantee for payment of the remainder of each shipment when he makes an order for the twenty-five or more cars.

Both parties agree that the twenty-five cars or more as stated herein shall be taken and construed to mean not less than twenty-five cars nor more than the capacity of the clay pit is now opened up.

Party of the second part further agrees to pay for the Burley or seconds, 50 per cent when same is put on the ground or cars and to pay the balance on each car put on the ground upon receipt of the returns from each car or cars shipped of the Dias Pore clay.”

Under the written contract, the three cars mentioned were delivered to plaintiff. He shipped them and got satisfactory returns. He then told defendant to continue to load as long as he had any clay. Also told defendant he would take all the clay in the pit. No written order was given defendant for any clay. Defendant spoke to plaintiff about the written guarantee for the 50 per cent not paid at time of delivery. Plaintiff did not give the written guarantee but the evidence in this case tends to show that with defendant’s consent and in lieu of said guarantee, plaintiff arranged orally with a bank for remittances for shipments to be made to the bank and the bank then to pay defendant. The business continued in that way for a period of about six months during which time defendant delivered to plaintiff forty-eight cars of dias pore clay and 1694 tons of burley clay. *606 Fifty percent of the purchase price was paid as the clay was delivered. The dias pore was then shipped by plaintiff and remittance therefor made to the bank and the bank paid defendant out of this remittance the balance due him on all clay delivered. After business had been conducted in this way for about six months, defendant made some complaint about the arrangements for delivery of burley clay and he and plaintiff had some difficulty about it and defendant then notified plaintiff he would deliver no more clay. Plaintiff then brought this suit for damages on account of the failure of defendant to mine and deliver the clay remaining in the pit.

The first question raised is that the contract was not binding because unilateral and a suit upon it for damages for its breach could not be maintained. It is also contended in the same connection that testimony to show that plaintiff told defendant he would take all the clay in the pit was incompetent because it was an offer to change by parol the terms of a written contract and for the further reason that if plaintiff wished to exercise his option to order more than was specifically provided for in the contract, the order must be in writing.

Defendant in his answer in the case and also in the brief in this court admits, impliedly at least, that the contract was binding as to the first three cars delivered and shipped and the twenty-five cars additional mentioned in the written contract. There can be no question that the contract was a valid and binding contract for the sale of some amount of clay. By its terms when executed, three cars were sold by defendant and bought by plaintiff. We are of the opinion that when the returns foi the shipment of the three cars were received and were admitted by plaintiff to be satisfactory, that the contract then became binding for twenty-five cars additional without any further order from plaintiff. This much is practically conceded by appellant. As more than twenty-five cars additional were delivered and paid for we need not discuss further that feature of the con *607 tract. We only mention the three cars and the twenty-five cars as showing that the contract was valid and binding when executed. The real question in this case is as to what extent it was binding and what force, if any, was given it by the subsequent action of the parties. Some suggestion was made in oral argument in this court that the clay in the pit was real estate and under the Statute of Frauds, a sale of it must be by written contract which should provide the quantity sold, the consideration and all other parts of the agreement in full and hence an order for any amount of clay must be in writing. We think the appellant is wrong in that position. It is true that while the clay remained in the pit it was part of the real estate but plaintiff did not buy it in the pit. Had he done so and had his contract provided that he should remove the clay from the pit, then appellant’s contention would be correct. By this .contract, however, plaintiff bought clay delivered at the railroad and he did not buy it in the pit. The defendant was to deliver the clay, hence he must sever it from the soil and convert it into personal property before he could deliver it. The sale was of personal property and that fact must be kept in mind in construing this contract.

In a sale of personal property, the amount sold must be certainly stated or means for accurately determining the amount provided. [Hudson v. Browning, 264 Mo. 58, 174 S. W. 393; Reigart v. Manufacturers Coal & Coke Co., 217 Mo. 142, 117 S. W. 61; Halloway v. Mountain Grove Creamery Co., 286 Mo. 489, 499, 228 S. W. 451; Saginaw Medicine Co. v. Dykes et al., 210 Mo. App. 399, 238 S. W. 556; Malloy v. Egyptian Tie & Timber Co., 212 Mo. App. 429, 247 S. W. 469.]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. State Highway Commission v. Warner
361 S.W.2d 159 (Missouri Court of Appeals, 1962)
Denney v. Spot Martin, Inc.
328 S.W.2d 399 (Missouri Court of Appeals, 1959)
Dugan v. Trout
271 S.W.2d 593 (Missouri Court of Appeals, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
274 S.W. 941, 217 Mo. App. 592, 1925 Mo. App. LEXIS 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gray-v-cooper-moctapp-1925.