Gravis v. Gardner-Denver Co.

141 So. 2d 508, 1962 La. App. LEXIS 1978
CourtLouisiana Court of Appeal
DecidedMay 7, 1962
DocketNo. 457
StatusPublished

This text of 141 So. 2d 508 (Gravis v. Gardner-Denver Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gravis v. Gardner-Denver Co., 141 So. 2d 508, 1962 La. App. LEXIS 1978 (La. Ct. App. 1962).

Opinion

REGAN, Judge.

Plaintiff, Frank J. Gravis, assignee of all of the stock of Sanlou Production Company, instituted this suit against the defendant, Gardner-Denver Company, endeavoring to recover the sum of $56,032.78, representing the cost of renting, shipping and installing two compressor units, which were leased from the defendant and which failed to perform satisfactorily, together with damages incurred as a result thereof. Plaintiff then asserted that gas emanating from his field in Iberville Parish, Louisiana was both lost and wasted because the machinery did not operate in conformity with [510]*510the defendant’s representations, and he requested that the lease between the parties be ordered cancelled.

The defendant answered and denied that the compressors were defective and insisted that the malfunctioning' thereof was caused by plaintiff’s imperfect installation of the units and his failure to properly maintain them. Then, assuming the position of plaintiff in reconvention, defendant asserted that the plaintiff was indebted unto it in the amount of $46,142, representing unpaid rentals and service charges and the cost of ultimately transporting the units back to its Dallas, Texas plant and restoring them to working condition.

From a judgment in favor of the plaintiff for $39,992.78,1 the defendant has prosecuted this appeal.

The facts which provoked this litigation, chronologically related, are these:

In January 1958, the parties entered into a contract, whereby the defendant agreed to lease two Gardner-Denver compressor units to the plaintiff for a monthly rental of $1,033.75 per unit. This sum represented 2Yz percent of each unit’s value and the agreement afforded the lessee an option to purchase the machinery at various periods in the lease with the understanding that all rents paid would be applied to the purchase price. The lease provided that the machinery to be furnished would possess a compressing capacity of 1,762,500 cubic feet per day per unit.

The manufacturer then delivered the machinery to plaintiff’s St. Gabriel Field and supplied him with a sketch of the concrete slab that plaintiff was required to install so as to provide an adequate foundation for the equipment. The first unit, which was installed by plaintiff’s workmen, was ready to operate in February 1958. However, before it was initially operated, the manufacturer ordered one of its field engineers, Herschel Nickel, to inspect the installation thereof. Thereafter, the unit was started and it then developed that there was sand in one of the pipes which required removal before it would function normally. This was done within a period of several days, and the unit was then placed in operation.

Plaintiff’s workmen completed the installation of the second unit the following month. It was located adjacent to the first and before it was started, Charles Offer-man, another field engineer employed by the defendant, checked it in detail. Again the presence of sand was encountered and remedied. But in all other respects, Of-ferman emphasized the unit was properly installed, otherwise he would not have permitted its operation.

Approximately two weeks after the second unit was in service, a shed was constructed over all of the machinery to protect it from the elements. The roof thereof was designed to resemble an inverted “V”, and in the peak thereof three ventilators were installed, each measuring two feet in diameter. There were curtain sides attached to the shed which extended from the edge of the roof to a point between four and six feet from the ground.

From the time the units were placed in operation, plaintiff continuously experienced an overheating problem with the machinery, which resulted in its being frequently inoperative. When the machines became overheated, a thermostat would automatically turn them off so that they would not be damaged as a result thereof.

This problem was called to the attention of the Gardner-Denver representatives on innumerable occasions and the defendant dispatched several engineers who tediously endeavored to remedy the condition. The representatives offered various suggestions [511]*511to correct the overheating, which included removing the sides of the shed and a part of the roof so as to permit the engines to operate in a cooler atmosphere. Plaintiff complied with both suggestions; however, the condition persisted. Although he did not replace the sides thereof, he did replace that section of the roof which had been removed in order to protect the equipment from damage by the elements.

In May and June of 1958, plaintiff installed baffles on the radiators of each unit, which were intended to permit the entry of cooler air therein and also erected a water cooler as an additional precaution intended to militate against overheating. None of these measures appreciably increased .the compressing capacity thereof, but they did slightly alleviate the intensity of the problem.

On July 9, 1958, J. H. Howard, a field representative who had conducted the pre-contract negotiations on defendant’s behalf, addressed a letter to Sanlou Production Company, to the attention of Frank J. Gra-vis, wherein he recommended the installation of new fans on the units in another effort to remedy the condition. He then very pertinently wrote:

“I can understand your feelings about this unit and can assure you we are doing everything possible to straighten the matter out at the earliest possible date.”

The aluminum fans were installed in July 1958 and plaintiff continued using the units until February 1959; however, he then, out of sheer frustration, decided to replace them with another manufacturer’s equipment since the units persistently overheated and as a result thereof were thermostatically stopped, and as a consequence they never did perform in conformity with Howard’s representations to the plaintiff. The correspondence which passed between plaintiff and defendant, and which appears in the record, establishes that the defendant represented the rated capacity of the unit to be 1,762,500 million cubic feet per day, but plaintiff discovered that the actual capacity was only 567,067 cubic feet per day. This difference was obviously due to the malfunctioning and frequent shut down of the engines caused by overheating. The actual capacity was established by the testimony of William G. Blackwell, a consultant geologist and petroleum engineer who was field superintendent at the St. Gabriel Field development. Blackwell stated that this figure was computed by averaging the daily performance of eách unit over the period of time that the machines were in actual operation.

The litigants herein do not dispute the fact that the gas compressor units did not function properly nor that the- malfunction thereof resulted from overheating. However, the cause of the overheating has been the subject of much dispute. The rather voluminous record is embellished with it as were the briefs which contained a total of 139 pages. The oral argument was also largely devoted to this subject.

In order to prove that the overheating was caused by a defect in the design of the equipment, plaintiff introduced the expert testimony of John Russell Wait, Jr., a consulting pipeline engineer who has had extensive experience with Gardner-Denver compressors over a period of approximately twenty years. One of his professional functions was to supervise the installation of gas compressor units. Wait examined the compressors in the St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee Const. Co. v. L. M. Ray Const. Corp.
52 So. 2d 841 (Supreme Court of Louisiana, 1951)
Barber Asphalt Paving Co. v. St. Louis Cypress Co.
46 So. 193 (Supreme Court of Louisiana, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
141 So. 2d 508, 1962 La. App. LEXIS 1978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gravis-v-gardner-denver-co-lactapp-1962.