Graves v. Johnson

176 So. 256, 179 Miss. 465, 1937 Miss. LEXIS 49
CourtMississippi Supreme Court
DecidedOctober 4, 1937
DocketNo. 32818.
StatusPublished
Cited by38 cases

This text of 176 So. 256 (Graves v. Johnson) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graves v. Johnson, 176 So. 256, 179 Miss. 465, 1937 Miss. LEXIS 49 (Mich. 1937).

Opinion

Griffith, J.,

delivered the opinion of the court.

On August 22, 1936, appellants, under a contract with the state highway department, were engaged in the construction of a concrete highway from Belzoni to or beyond Silver City, and for a distance of approximately 6.770 miles. The work had been begun at Belzoni about three or four months previously, and proceeded thence southwardly towards Silver City. On the date aforesaid about one-half of the construction had been completed in so far as to admit local traffic thereon. It appears to have been the policy of the highway department to open the highway to local traffic as rapidly as the work progressed from the upper end of this link of -road, and as far along each day as the- concrete had had sufficient time after having been first laid to safely bear such traffic.

As to through traffic, it was provided in the contract that “during the construction of this project the road will be closed to through traffic, which will be detoured "around the work over the old road from Midnight to Belzoni.” When the work was first begun there was erected at a suitable and conspicuous place at the forks of this road with another, a large sign, 8 x 10 feet, which had painted thereon in large letters “Road Closed,” with 3, detour sign thereon directing traffic to take the *475 other fork, and this sign was maintained there until after the date first above named. The detour mentioned in the contract, and as above quoted, was reached about 100 yards below Belzoni. This detour is spoken of in this record as the Pluck road.

When the work reached the Pluck road detour, and the concrete had sufficiently hardened to admit through traffic to that point, a conspicuous detour sign with a pointer was there placed, reading “Detour,” and below the word “Detour,” “Local Traffic Only.” Since the road was to be open to local traffic beyond this point as the work progressed, the wooden barricade specified in the contract to be placed upon and across the road at detours could not be used at the Pluck detour, but it was moved from time to time down the highway as the progression of work would allow local traffic on the concrete road. There were no painted warning signs alongside the road south of the Pluck road detour.'

This wooden barricade, placed and replaced as 'the work progressed, was often removed or broken down at night by unknown parties, and the green concrete beyond was damaged by vehicles using the unusable portion of the work. This experience was so frequent, and of such serious consequences, that the highway engineer in immediate charge for the state highway department directed that, instead of the wooden barrier, a long steel trailer be put lengthwise across the road at the end of the usable portion; and this was done by the contractor, the trailer barricade being moved farther southward as the work progressed.

This trailer barricade had, as part of its construction, steel I-beams about 8 inches in height from top to bottom of the beam, supported by large steel wheels, so that the I-beams were about 30 to 35 inches above the road, and they were more than 20 feet in length. They were painted with aluminum paint, which, as the witnesses say, made a sort of silver-white appearance. The trailer *476 weighed about 6,000 pounds. The concrete part of the highway was 20 feet wide.

When the crew quit work at 5 oi’clock p. m. on the date first aforesaid, the trailer barricade was placed at right angles entirely across the road at the end of the usable portion and at the beginning of the unusable portion of the concrete highway, and flares were placed so as to light it at night. The roadway above the point was straight for a mile or more and was level throughout the entire of that distance. Some few minutes after six o ’clock p. m. on that date, while the sun was still shining brig’htly and on a cloudless day, with no nearby trees or other objects to cast any shadows, appellees’ decedent, driving an automobile at the rate of from 40 to 50 miles an hour, and without any slackening of speed at any time as he approached, crashed into this trailer barricade and was so seriously injured that death resulted in about 30 hours thereafter. His widow for herself and as next friend for his children brought suit and recovered a large judgment, from which this appeal is prosecuted.

In view of the aforementioned experiences with the wooden barricades, we would be disposed to hold that the contractor would have been justified in strengthening those barriers, so as to make them too heavy to be removed or struck down by trespassers at night; or that, so long as using the lighter wooden barricades, painted with black, white, and orange stripes prescribed by the highway department, the contractor could have attached such a barrier to the 3-ton trailer, with the trailer as a reinforcement, and that in such case the contractor would have a perfect defense against any person who' collided therewith, regardless of the consequences of such a collision. In this connection we note the contention of appellees that the contractor was required to maintain a sign 400 yards up the highway from the barrier, this sign reading “Detour 400 yards.”

The record is somewhat obscure as regards this contention, for the reason that there are no explanations *477 by any competent witness of the practical import of tbe very general language used in the contract on this point when applied to tbe changing situation here under review; but, so far as we can dependably see from what is now before us, and particularly when we look to the standard drawings, to which particular reference is made in the contract as regards the signs and barricades to be erected and maintained, the contract did not require the contractor, or certainly it is not clear that it did, to erect or maintain any such 400-yard sign south of the Pluck detour, for there was no other established detour. The testimony shows, without dispute, that the local traffic, in availing of the usable portion of the concrete below the Pluck detour, would turn off from that portion at any convenient place or places before reaching the unusable portion, and would thence use the borrow pits alongside the unusable portion of the main highway, it appearing that these borrow pits had been left in such condition as to be thus employed. And tbe other warning signs with the word “Slow” were required to be placed only when, and where, the state or project engineer in charge directed them to be placed; and there is no evidence in the record that any such warning signs were so directed.

All this can and ought to be cleared up on a new trial, but, as the record now stands before us, we think too much was made of this matter of warning signs in instruction No. 1 granted to appellees; for, in addition to the matter above stated, the rule is that, if all the existing physical facts were sufficient to give notice, the failure to give cumulative notice or notices does not aid plaintiffs’ case. Raymond v. Sauk County, 167 Wis. 125, 166 N. W. 29, L. R. A. 1918F, 425; and see, also Hubbard v. Concord, 35 N. H. 52, 69 Am. Dec. 520, 533, and compare Thompson v. Miss. Cent. R. Co., 175 Miss. 547, 166 So. 353. Instruction No. 1 charged the jury that, as a matter of law, the appellants were required to erect and maintain reasonably proper and suitable danger

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spoo Ex Rel. Spoo v. Tl Wallace Const. Co.
858 So. 2d 199 (Court of Appeals of Mississippi, 2003)
Mississippi Dept. of Transp. v. Trosclair
851 So. 2d 408 (Court of Appeals of Mississippi, 2003)
Bush Construction Co. v. Blakeney
350 So. 2d 1370 (Mississippi Supreme Court, 1977)
City of Jackson v. Sullivan
349 So. 2d 527 (Mississippi Supreme Court, 1977)
Austin v. Montgomery
336 So. 2d 745 (Mississippi Supreme Court, 1976)
Thompson v. Riverside Chemical Co.
416 F. Supp. 35 (N.D. Mississippi, 1976)
McLaurin v. OLD SO. LIFE INSURANCE COMPANY
334 So. 2d 361 (Mississippi Supreme Court, 1976)
Shideler v. Taylor
292 So. 2d 155 (Mississippi Supreme Court, 1974)
Shurley v. Hoskins
271 So. 2d 439 (Mississippi Supreme Court, 1973)
Elsworth v. Glindmeyer
234 So. 2d 312 (Mississippi Supreme Court, 1970)
Blain v. Sullivan
204 So. 2d 436 (Mississippi Supreme Court, 1967)
DeLaughter v. Womack
164 So. 2d 762 (Mississippi Supreme Court, 1964)
Kettle v. Musser's Potato Chips, Inc.
162 So. 2d 243 (Mississippi Supreme Court, 1964)
Walters v. Gilbert
158 So. 2d 43 (Mississippi Supreme Court, 1963)
Trantham v. Gillioz
348 S.W.2d 737 (Missouri Court of Appeals, 1961)
Gray v. Felts
131 So. 2d 454 (Mississippi Supreme Court, 1961)
Pullin v. Nabors
128 So. 2d 117 (Mississippi Supreme Court, 1961)
United Gas Pipe Line Co. v. Jones
111 So. 2d 240 (Mississippi Supreme Court, 1959)
Millers Mutual Fire Insurance v. King
98 So. 2d 662 (Mississippi Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
176 So. 256, 179 Miss. 465, 1937 Miss. LEXIS 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graves-v-johnson-miss-1937.