Graves v. Hallmark

232 S.W.2d 130, 1950 Tex. App. LEXIS 2283
CourtCourt of Appeals of Texas
DecidedJune 12, 1950
Docket6065
StatusPublished
Cited by3 cases

This text of 232 S.W.2d 130 (Graves v. Hallmark) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graves v. Hallmark, 232 S.W.2d 130, 1950 Tex. App. LEXIS 2283 (Tex. Ct. App. 1950).

Opinion

PITTS, Chief Justice.

Appellee, Sam Hallmark, sued appellants, R. E. Graves and wife Helen A. Graves, for a debt alleged to be evidenced in part by a note and all of it secured by a mechanic’s and materialman’s lien. ' The suit arose out of a contract between the parties in which appellee agreed to furnish all labor and the material and construct improvements as a homestead for appellants on a tract of land owned by appellants and situated in Lubbock, Lubbock County, Texas. Before the construction began appellants executed a mechanic’s lien note of date July 15, 1948, for $11,000 payable1 in 120 days to appellee for the construction of certain improvements to be made on the land in question. The note provides for the usual interest and attorney fees if placed in the hands of an attorney for collection. On the same date the parties executed and acknowledged a mechanic’s and materialman’s lien contract with appellants signing as parties of the first part and appellee signing as party of the second part. The same was filed for record in Lubbock County. The lien contract sets out in part that the parties of the first part executed a promissory note in the sum of $11,000, payable to the party of the second part, and that the parties of the first part gave, granted and' conveyed to the party of the second part, his heirs and assigns, an express mechanic’s and materi-alman’s lien, as provided by the Constitution and laws of the State of Texas,-upon the land in question and all improvements thereon, or that may thereafter be placed thereon, to secure the payment in full of the above mentioned indebtedness, principal, interest, and attorneys’, fees, and further to secure the performance of -each and every covenant and obligation therein set out. The said contract also contains *131 a paragraph hereinafter set out concerning 'changes made during construction and extra costs for such, which' would ’he secured by the lien.'' During the construction appellants made two payments to ap-pellee of $2,000 each, aggregating $4,000, and they admit appellee ‘is entitled to a balance due of $5,122.15 which sum they are willing to pay but they deny liability for any sums incurred by reason of extra costs added as a result of any changes made during the construction of the improvements.

Written specifications were never provided and the improvements were made on the premises upon agreed oral specifications. The construction had been completed and appellants had taken possession of the premises before the trial of the case. Both parties pleaded the execution of the note and the mechanic’s and materialman’s lien contract and both parties rely on the said lien contract for recovery, appellants seeking to have their title quieted. Appel-lee pleaded certain changes made in the improvements during construction at the request of appellants, by reason of which changes extra costs were incurred for all of which he sues and seeks a foreclosure of the lien upon the same.

The case was tried to a jury and judgment was rendered upon the verdict for appellee on the note and mechanic’s and materialman’s lien, including interest and the costs for extras, for a total sum of $12,075.58, after allowing for certain credits and making certain deductions for offsets, and for a foreclosure of the said lien to cover it all and an additional personal judgment only was rendered for the sum of $1207.56 as attorney fees, which latter sum was not secured by the said lien. Appellants perfected their appeal and predicate the same upon two points of error.

In point one they charge that the trial court erred in overruling their exceptions to appellee’s alleged cause of action because the same sought to change or vary the terms of a written, signed, acknowledged and recorded mechanic’s and materi-alman’s lien contract for improvements made on appellants’ homestead. In reply to appellants’ first point appellee urges that he has not sought to change or vary the terms of the lien contract in question. On the contrary, he asserts that he pleaded the said lien contract and the note in question and relied on them and especially the terms of the lien contract for recovery.

The jury found, in effect, that the parties entered into a contract on or about July 15, 1948, to construct the improvements in question and executed the lien contract in question; that appellant, Helen A. Graves, was present when the said lien contract and note were executed and delivered by appellant, R. E. Graves, to appellee and that she signed and gave her consent to the lien contract; that the parties entered into an oral agreement relative to. the specifications for the construction of the improvements; that the improvements were constructed by appellee under the direction of appellant,- R. E. Graves, and that appellant, Helen A. Graves, also assisted in directing the construction of the improvements; that during the progress of construction both appellants directed appellee to make alterations and add certain extras to the improvements which increased the . cost over and. above the original cost contemplated; that one of the said changes made was to increase the floor space of the five room house from 900 square feet to 1140 square feet at an increase in cost of $2,000; and that other alterations and extras were authorized by. appellants which increased the cost of construction to the sum of $3,806 over and above the original cost price agreed upon. The jury also found, in effect, that appellants were entitled to an offset of $150 because of a defect in the foundation of the house and appellants were allowed a credit on the judgment for such a sum. The costs of the said extras and alterations added to the original cost price of $11,000 agreed upon aggregates the sum of $14,806, which sum, less deductions made for previous payments made by appellants in the sum of $4,000 and the offset allowed them in the sum of $150, - together with .interest on the final aggregate sum of $10,656, justifies the amount of the judgment for $12,075.58 rendered by the trial court as the balance of the debt due, except for the attorney *132 fees which is a personal judgment only for the sum of $1207.56, or ten per-cent- of the debt.

Nowhere do appellants challenge the findings of’ the jury of question the sufficiency of the evidence to support such findings; It therefore appears that a proper construction .of the lien contract in question and particularly of one paragraph therein contained will determine the controlling issue in this case. That particular paragraph in question of the lien contract makes the following provision:

“It is further expressly contracted and agreed that the plans and specifications above referred to, authorize the making of changes in same by which extra costs may be incurred and any such extra costs, not to exceed the sum of $ [blank], incurred in accordance with the right reserved to parties- of the first part to make such changes shall be secured by the liens herein given and granted as fully as if such amount were included in the original contract price.”

Appellants contend that because of the uncertainty of the amount of costs for extras reflected by the language used in the foregoing paragraph and because the space left for the maximum sum to be spent for extra costs authorized was left blank the lien cannot be legally foreclosed and enforced as against any extra costs for alterations on the construction of the improvements as a homestead.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Security Life & Casualty Co. of Dallas v. Gooch
289 S.W.2d 336 (Court of Appeals of Texas, 1956)
Robertson v. Smith
282 S.W.2d 99 (Court of Appeals of Texas, 1955)
Atkinson v. Dailey
238 S.W.2d 584 (Court of Appeals of Texas, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
232 S.W.2d 130, 1950 Tex. App. LEXIS 2283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graves-v-hallmark-texapp-1950.