Graves v. Downey

CourtSuperior Court of Maine
DecidedDecember 16, 2004
DocketHANcv-03-38
StatusUnpublished

This text of Graves v. Downey (Graves v. Downey) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graves v. Downey, (Me. Super. Ct. 2004).

Opinion

STATE OF MAINE SUPERIOR COURT

HANCOCK, SS. CIVIL ACTION Docket No. CV- 03-38, JL oo HAL af! wy fe

Kathleen Graves et al., Plaintiffs

V. Decision and Judgment

Oe

S.E. Downey, Registered Land Surveyor, P.A. et al., Defendants

APR 26 OS

Hearing on the complaint was held on April 27, April 28, May 21 and June 5, 2004. On each hearing date, plaintiff Kathleen L. Graves, defendant Patrick J. Downey, and counsel for the parties were present. Plaintiff David C. Graves was not present for trial, and defendant Stephen E. Downey was present for portions of the proceedings.

The plaintiffs own a parcel of land located in the Town of Bar Harbor. They decided to subdivide the parcel into three smaller lots. One lot (the most northerly of the three) would be conveyed to one of their sons; the second would go to a family friend and contractor, Stephen Robbins; and they planned to hold the remaining land and transfer it to another son at some future date. In return for the transfer of land to him, Robbins agreed to act as a general contractor to improve the subdivided lots.

Defendant S.E. Downey, Registered Land Surveyor, P.A. is a professional service corporation and is engaged in the business of surveying. Defendant Stephen Downey is the president and sole shareholder of the business and, at times relevant to this case, defendant Patrick Downey (Stephen’s son) was employed by and worked for the business. Because Stephen Downey did surveying work for Robbins previously, in early 1999 Robbins secured the professional services of the Downey firm to conduct a survey of the entire Graves parcel and create the three new interior lots.

Patrick Downey was principally responsible for the surveying work. He was

finishing his term as surveyor in training, and Stephen Downey wanted Patrick to manage the project. Stephen’s essential role was to supervise Patrick’s work. Indeed, when Robbins first contacted Stephen Downey, Stephen referred Robbins to Patrick. In spring 1999, Patrick Downey produced a survey. See joint exhibit 1. On the basis of this surveying work, Robbins substantially constructed a house on the northerly eight acre lot that was to be conveyed to the plaintiff's son. The construction process included improving a road that constituted a boundary of the plaintiffs’ lot, providing power, installing a septic system and drilling a well. Robbins framed, sided and enclosed the exterior of the house, which was set on a slab foundation. He also had erected the chimney. The house and the associated improvements were all located within the area that Patrick had surveyed to be the new lot, which in turn was within the plaintiff’ s parcel, according to the Downey survey.

The easterly side of the Graves parcel is bounded by federally owned land, which is part of Acadia National Park. The land abutting the northern boundary of the plaintiffs’ parcel is subject to building restrictions imposed and controlled by the Park.’ While the construction process was ongoing, the Park was in the process of having its own survey work performed on its property. The surveyor, Richard Day, learned of the construction work on or near the Graves property, and, suspecting that the locus of the construction was actually on property that was subject to federal restriction, he alerted Park officials to the situation. One or two meetings were held at the Park’s headquarters. Park Superintendent Michael Blaney, Kathleen Graves, her attorney, Day and Patrick Downey were present for at least one of the meetings. At that meeting, Day expressed

his opinion that the new house had been constructed beyond the boundaries of the Graves

' The evidence does not appear to include any direct evidence that the Park had such control over that northerly parcel, which is owned by one Shepard Harris. However, the court finds that the Park in fact had the legal authority to prohibit the type of construction at issue here. This finding is based on, among other things, Kathleen Graves’ testimony about the position maintained by the Park during the Graves’ efforts to resolve the problem. For the reasons she described, the Park apparently was the party that rejected the possibility of some accommodation that would have allowed the house to remain at its original location. Indeed, there was such little question about the Park’s rights that the Graves ultimately arranged to move the house from its original location to one that was more clearly within the boundaries of their lot. Finally, the very fact that the Park involved itself in this matter is indirect evidence of its right to control development in the location of the new house. lot, and Day explained his reasons supporting that conclusion. Despite Patrick Downey’s testimony to the contrary, the court finds that Patrick was given full opportunity to explain why, in his view, the house was located on the Graves land. Despite direct inquiry posed to him, he did not attempt to justify his opinion in any meaningful way.

As a result of this problem, the Graves made vigorous attempts to resolve the apparent encroachment. The owner of the land where the house apparently was located in fact expressed some willingness to reach an accommodation. However, the Park refused to allow the house to remain at the site, which, it continued to assert, was not within the Graves parcel. The Graves also sought the intervention of members of Maine’s congressional representatives, but that effort was also unsuccessful. Ultimately, the Graves came to realize that they would be unable to let the house remain in its original location. They arranged to have the house moved to a site that indisputably was on their property. This process was more extensive than transporting the house itself, because the relocation required a new foundation, a new septic system, a new well and other work. The cost of this work amounted to $110,589.00. See plaintiffs’ exhibits 10- 23.

In this action, the Graves allege that the defendants breached their contract for surveying services and that the defendants were negligent.

In addition to opposing the plaintiffs’ substantive allegations, the defendants raise several formal arguments. They contend first that the court cannot reach the merits of the plaintiffs’ claims, because an analysis of their causes of action requires the court to determine where the boundaries of the plaintiffs’ parcel is located on the face of the earth. This, the defendants argue, cannot be accomplished unless all abutting property owners are joined as parties in this action. This argument fails for two reasons. First, it does not appear that the defendants have preserved this issue. Pursuant to M.R.Civ.P. 12(b), a rule 12(b)(7) motion to dismiss for failure to join an indispensable party under rule 19 is waived if not asserted in a responsive pleading.” Here, the defendant’s amended

responsive pleading did not raise the issue.

* The defendants have expressly framed this argument as a motion to dismiss the complaint for failure to join an indispensable party under rule 19. See “Defendant’s Second, even if the defendants have preserved this argument, then it fails on its merits. If this action constituted one for a declaratory judgment that would “resolve ownership rights” among persons who are not parties to the action, then joinder of those missing parties would be required. See Lamson v. Cote, 2001 ME 109, § 18, 775 A.2d 1134, 1139. It simply stands to reason that the court cannot adjudicate the rights of persons who are denied the opportunity to participate in that adjudicatory process. Here, however, the plaintiff’s claims are not intended to bind the federal government, Shepard Harris or any other nearby property owner. Rather, the plaintiffs seek an award of compensatory damages based on theories of contract and tort.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Slipp v. Stover
651 A.2d 824 (Supreme Judicial Court of Maine, 1994)
Snyder v. Haagen
679 A.2d 510 (Supreme Judicial Court of Maine, 1996)
Lamson v. Cote
2001 ME 109 (Supreme Judicial Court of Maine, 2001)
Hennessy v. Fairley
2002 ME 76 (Supreme Judicial Court of Maine, 2002)
Schneider v. Richardson
411 A.2d 656 (Supreme Judicial Court of Maine, 1979)
McLaughlin v. Sy
589 A.2d 448 (Supreme Judicial Court of Maine, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Graves v. Downey, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graves-v-downey-mesuperct-2004.