Graubard v. Balcor Co.

2000 NMCA 032, 999 P.2d 434, 128 N.M. 790
CourtNew Mexico Court of Appeals
DecidedMarch 14, 2000
Docket20,846
StatusPublished
Cited by11 cases

This text of 2000 NMCA 032 (Graubard v. Balcor Co.) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graubard v. Balcor Co., 2000 NMCA 032, 999 P.2d 434, 128 N.M. 790 (N.M. Ct. App. 2000).

Opinion

OPINION

ALARID, Judge.

{1} Defendant, The Balcor Company (Balcor), filed an application for interlocutory appeal from an order denying its motion to dismiss Plaintiffs personal injury complaint against it for improper service of process. This Court granted the appeal and proposed summary reversal and remand to the district court for reconsideration of the motion. Both parties have responded to the proposed disposition and, having considered their arguments, we reverse the order denying the motion to dismiss and remand to the district court for reconsideration in light of the standards enunciated below.

BACKGROUND

{2} The order denying Balcor’s motion determined that there were three relevant dates: (1) March 28, 1997, the date the complaint was filed in district court-naming Balcor’s predecessor in interest as a defendant; (2) March 31, 1997, the date the statute of limitations ran on Plaintiffs claim; and (3) June 6, 1998, the date that the summons and complaint were served on Balcor’s predecessor in interest. The parties do not contest these dates or their relevance.

{3} In its letter decision, the district court stated its opinion that the fourteen month delay was too long to wait to serve a party, particularly when there was no evidence that the party had prior notice of the suit. The district court continued:

However, the Court of Appeals in Prieto v. Home Ed. Livelihood Program, 94 N.M. 738, 616 P.2d 1123 (Ct.App.1980) establishes that a complaint may be properly dismissed for lack of reasonable diligence upon a showing of intentional delay by the Plaintiff. There is no evidence of intentional delay in this case. The Motion to Dismiss is denied without prejudice. Should the Defendant obtain evidence of intentional delay, I will rehear the motion.

The order denying the motion and certifying the. question for interlocutory appeal did not reiterate the findings or reasoning reflected in the letter decision but denied the motion as not well taken.

ANALYSIS

{4} Balcor filed a motion to dismiss on December 4, 1998. This motion asserted as grounds for dismissal that Balcor received service of the complaint on October 26, 1998, and the complaint did not name or in any way identify it. Balcor asserted that service was improper since it was not a named party to the action and asked that the complaint be dismissed “for improper service of process and the fact that Balcor is simply not a named party to this action.” In late December, Plaintiff filed a response noting that the district court had entered an order on October 2, 1998, allowing Plaintiff to amend the complaint by interlineation to substitute Balcor for its predecessor in interest. In February 1999, Balcor filed a reply to the response that explicitly asserted the statute of limitations, which had run prior to the time that Balcor was named a party to the action, and that Balcor was unaware of any claim against it when the statute ran on March 31, 1997. It argued that it was not given notice of the claim until 17 months after the statute of limitations had run.

{5} We determine that Balcor timely asserted the defense of improper service of process including the lack of due diligence in effecting service. Cf. Rupp v. Hurley, 1999— NMCA-057, ¶ 20, 127 N.M. 222, 979 P.2d 733 (NMSA 1978 Rule 1-012(B)(5) defense of insufficiency of service of process is waived if not raised at the first opportunity, i.e., with the answer or as part of the first motion to dismiss).

{6} Plaintiff argues that the district court correctly interpreted Prieto as requiring a showing of intentional delay before an appeal could be dismissed for delayed service of process. We disagree with Plaintiffs interpretation of Prieto and reverse and remand this matter to give the district court an opportunity to reconsider the motion.

{7} In Prieto, this Court considered the effect of a three month delay in the service of process where the trial court did not find a lack of diligence in obtaining service and the trial court’s remarks were understood to find no fault on the plaintiffs part for the delay in service. See Prieto, 94 N.M. at 742, 616 P.2d at 1127. The record in that case also failed to establish laches or willful delay. See id. This Court held

that the statute [of limitations] is tolled by the timely filing of the complaint but that the trial court, in the exercise of its inherent power and in its discretion, independent of statute, may dismiss a case for failure to prosecute when it is satisfied that plaintiff has not applied due diligence in the prosecution of his suit.

See id. (Emphasis added.)

{8} Plaintiff argues that this Court should understand a lack of due diligence as being synonymous with intentional delay. Defendant, on the other hand, correctly points to case law stating that “a dismissal for failure to prosecute [with reasonable diligence] is functionally the same as a dismissal for negligence in prosecution.” See, e.g., Gathman-Matotan Architects & Planners, Inc. v. State. Dep’t of Fin. & Admin., 109 N.M. 492, 493, 787 P.2d 411, 412 (1990) (rejecting the plaintiffs attempt to distinguish between failure to prosecute and negligence in prosecution while interpreting NMSA 1978, § 37-1-14 (1880)).

{9} In support of its argument, Plaintiff recites how this Court distinguished Murphy v. Citizens Bank of Clovis, 244 F.2d 511, 512 (10th Cir.1957), by noting that the plaintiff in Murphy “deliberately waited thirteen months to turn the summons and complaint over to the United States Marshall for service.” Prieto, 94 N.M. at 741, 616 P.2d at 1126. While in Murphy intentional delay in the service of process showed a lack of due diligence, we are not persuaded that in the present case a significant unintentionally-caused delay cannot also demonstrate a lack of due diligence.

{10} It is also worth noting that in Murphy, the federal court was interpreting a 1953 New Mexico statute later codified as NMSA 1978, § 37-1-13 (1880), which provided that an intent to issue process immediately would be presumed upon the filing of the petition, declaration, bill, or affidavit in the proper clerk’s office. Cf. Prieto, 94 N.M. at 741, 616 P.2d at 1126 (determining that Section 37-1-13 was an anachronism in light of the adoption of what are now Rules 1-003 and 1-004 NMRA 2000). Even with the statutory presumption in effect in Murphy of an intent to issue process immediately, the Tenth Circuit determined that

[the plaintiffs] failure to issue process for a period of over thirteen months indicates a continued lack of reasonable diligence, an essential to the effective suspension of the statute of limitations.... The trial court found lack of diligence to exist as a fact. The finding is not erroneous and is fatal to plaintiffs complaint.

Murphy, 244 F.2d at 512 (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franklin v. Access Corrections
New Mexico Court of Appeals, 2025
Rivera v. Xerox Corporation
D. New Mexico, 2023
Gatlin v. CoreCivic, Inc
D. New Mexico, 2022
Padilla v. Reed
New Mexico Court of Appeals, 2017
Musick v. Sierra Nevada Prop. Mgmt.
New Mexico Court of Appeals, 2016
Baumeister v. New Mexico Commission for the Blind
409 F. Supp. 2d 1351 (D. New Mexico, 2006)
Martinez v. Segovia
2003 NMCA 023 (New Mexico Court of Appeals, 2002)
Romero v. Bachicha
2001 NMCA 048 (New Mexico Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
2000 NMCA 032, 999 P.2d 434, 128 N.M. 790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graubard-v-balcor-co-nmctapp-2000.