Grassman v. Bonn

32 N.J. Eq. 43
CourtNew Jersey Court of Chancery
DecidedFebruary 15, 1880
StatusPublished

This text of 32 N.J. Eq. 43 (Grassman v. Bonn) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grassman v. Bonn, 32 N.J. Eq. 43 (N.J. Ct. App. 1880).

Opinion

The Chancellor.

Thomas H. Niven and John A. Middleton entered into a contract, dated November 7th, 1874, with the defendants, who are the Bull’s Ferry road commissioners, to do certain work (road and sewer construction) for them, finding the materials therefor; the price to be paid in monthly installments as the work progressed, and the installments to be based on monthly estimates made by the defendants’ engineer, of eighty-five per cent, of the work done at the time. The like percentage was to be paid at the completion and acceptance of the work on the price of the work on which the percentage had not been paid, and of the remaining fifteen per cent., two-thirds were to be paid in six months, and the rest in twelve months, after the date of the final certificate of the engineer. The contractors entered upon the performance of the work, but discontinued it, while it was still unfinished, on the 19th of March, 1875. On the 31st of that month, Middleton assigned his interest in the contract to Niven, who entered into an agreement [45]*45with the defendants, dated April 13th, 1875, by which he agreed to complete the contract, and they agreed to accept him as sole contractor accordingly. By that agreement they agreed to pay him for the work and materials in the manner and in the medium specified in the original contract, and he expressly agreed to prosecute the work to the satisfaction of the defendants, and that, in case the quality or prosecution thereof should not be fully to their satisfaction, or in case they were not satisfied that the workmen to be employed on the work were paid promptly, or in case no arrangement was made by him satisfactory to the defendants for the payment of materials furnished or to be furnished for the work, then, after five days’ written notice served on him, they might discharge him from their employment and declare the original contract and that agreement forfeited, and might declare all claims on his part, beyond the eighty-five per cent, of the final estimate, which was to be made immediately after the forfeiture, to be null and void, and might call on his sureties under the agreement to ■enter into a contract to do the work and furnish the materials which he had agreed to do and furnish, and if they should finish -the work they should have the same price which he would have been entitled to, but if they refused, the defendants were to be at liberty to employ another person or persons to complete the work, and he and his sureties were to pay to the defendants any excess over the price agreed to be paid to him wdiich they might be compelled to pay such other person or persons for completing the work.

Niven proceeded with the work under the agreement until December 29th, 1875, when he abandoned it, it being .still unfinished. A few days prior to that date he made an assignment to the complainant for the benefit of his creditors. His sureties, by an agreement dated January 22d, 1876, agreed with the defendants to finish the work for the .price payable by the original contract, and did so accordingly, to the satisfaction of the latter.

[46]*46When the agreement between Niven and the defendants for the completion of the work by him alone was made, they, at his request, advanced to him, on the security of the pledge of the materials lying along the line of the improvement, $4,000, to enable him to pay arrears of wages due laborers. Of this sum he repaid to them only $1,100. The work on the main sewer, which was part of the work which he contracted, to do, was suspended from about the middle of August, 1875, until the 5th of November following, in order to enable the defendants to ascertain whether a project for extensions of the sewer would be adopted. The project, if adopted, would have necessitated an enlargement of a considerable part of the sewer not then built. Eor his damages for this stoppage, he, at first, claimed nearly $10,000, but afterwards proposed to accept $5,000 in satisfaction. He subsequently reduced his claim from $5,000 to $3,000. The defendants were advised by their counsel that he was entitled to compensation, and the result was that in a few days afterwards Niven sent to the defendants a formal offer in writing to accept $3,000 in full settlement of his claims for damages arising from the stoppage of the sewer work, the extra cost of building a culvert, his claim for extra allowance on .certain receiving'basins and capping, claims for certain excavation in the sewer trench, and in full settlement of claims to date arising from delay or from extra work done in any and all cases not theretofore included in the engineer’s estimates. The defendants accepted the offer, provided it should be approved of in writing by all of his sureties, and that the $3,000 should be paid in the installments as they became due. When Niven finally discontinued the work, he left unpaid wages to laborers employed by him thereon. His assignment to the complainant, for the benefit of his creditors, is dated December 21st, 1875. On the day previous to that date he sent to the defendants his written request that they would pay to the laborers employed by him, and to Ms sub-contractors, the amounts due them out of the moneys in the hands of the [47]*47defendants, or to become due to him under the contract, and further requested that if any money should remain after such payments, they would pay it fro rata to those who had furnished block stone. On or about the 24th of December, and after that date, the defendants, in pursuance of that request, paid to the laborers their wages, taking from them an assignment (with power of attorney to collect) of their claims and all lien by virtue thereof. The greater part of those claims so paid have been presented by the defendants to the complainant, under the assignment to him.

After the work was finally discontinued by Niven, and before the sureties entered upon the work of completing the contract, the defendants were compelled to take measures at some cost to protect the work. When the sureties entered into the agreement to complete the work, they gave to the defendants their consent in writing, that the defendants might pay all laborers and materialmen whose claims remained unpaid, for work done and materials furnished subsequently to the contract of April 13th, 1875 (Niven’s), out of the unpaid fifteen per cent, then as yet unpaid and out of the eighty-five per cent, then as yet unpaid, for work and materials and other performance of the contract as far as it had then been performed by Niven and Middleton together or by the former alone, and that the materials furnished prior to the date of the contract of April, 1875, might also be paid for out of the fifteen per cent, or the balance thereof when earned by the completion of the contract, the eighty-five per cent, to be first exhausted in such payments. And, subject to such payments, the defendants then assigned to the sureties the fifteen per cent, of the remuneration for work theretofore done and materials furnished by Niven or by Niven and Middleton under the contracts which would have become due to Niven if he had completed the work.

The foregoing statement contains all the material facts of the case—quite all that it is necessary to take into consideration in deciding the questions submitted. Those questions which, under the conclusions I have reached, it is necessary [48]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phelan v. Albany & Susquehanna Railroad
1 Lans. 258 (New York Supreme Court, 1869)

Cite This Page — Counsel Stack

Bluebook (online)
32 N.J. Eq. 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grassman-v-bonn-njch-1880.