Grass v. Bangor
Opinion
STATE OF MAINE SUPERIOR COURT PENOBSCOT, ss CIVIL ACTION DOCKET NO. RE-Or~4
WRf1~ f'~ tJ - Ic;Y~1 ,)010 JEFFREY B. GRASS, d/b/a J.B. GRASS EXCAVATING
Plaintiff,
v. ORDER ON DEFENDANT PM CONSTRUCTION'S
RICHMOND BANGOR MOTION IN LIMINE DEVELOPMENT, LLC, PM CONSTRUCTION CO., INC., EASTERN BANK and KATAHDIN TRUST COMPANY
Defendants.
Before the Court is Defendant PM Construction Co., Inc. ("PM")'s motion in limine requesting that Article 9 ("Article 9") of the contract ("Contract") between PM and Plaintiff Jeffrey B. Grass, d/b/a J.B. Grass Excavating ("Grass") be found unambiguous, therefore excluding any parol evidence relating to Article 9. Additionally, PM asks that the Court "rule that Article 9 did not require PM Construction and Grass to agree upon and execute change orders as a condition precedent to Grass being obligated to perfonn changes to the scope of work as originally set forth in the Contract." (Def.' s M. Limine 1.). In response, Grass has filed in opposition to PM's motion, requesting that the Court rule that the Contract was unambiguous but required written change orders between Grass and PM before any additional work was to be performed. In the alternative, Grass requests that the Court find that the relevant Contract provisions are ambiguous. Finally, Grass asks that if PM's interpretation of the Contract is adopted, Article 9 be found unconscionable, invalid and unenforceable. (PI.' s Opp. M. Limine 1.).
1. FACTUAL BACKGROUND
Grass and PM agree about little in the factual record. Points of disagreement between the parties regarding the facts will be noted. In or about September 2007, PM and Grass entered into the Contract with PM serving as the contractor and Grass a subcontractor on a project building a Walgreen's Pharmacy in Bangor. The Contract, which both parties acknowledge as accurate, is attached as Exhibit 1 to Defendant's Motion in Limine. The parties also both acknowledge that Exhibit 2 to Defendant's Motion in Limine, entitled "AlA Document A 101™ - 1997" ("Owner's Contract") is the controlling agreement between PM and the site's owner The Richmond Company, Inc. ("Richmond").
At some point during the project, a dispute arose between Grass and PM regarding the scope of the excavation work Grass was obligated to perform under the Contract. Grass contends that after beginning work on the project, it was discovered that serious differences existed between the elevations identified in the site plans and documents provided by PM and the actual elevations at the site. (PI.' s Opp. M. Limine 3.). Further, Grass alleges that PM instructed Grass to alter the proscribed method for excavating trenches after Grass had began performing the work, creating a significant increase in work. (PI.' s Opp. M. Limine 4.). Finally, Grass claims that the initial plans and specifications indicated that the soils excavated on site would be used for fill and backfill, but after commencing work PM directed him to remove the excavated soil and obtain backfill from off site, which caused Grass added work and expenses. ld.
PM, while not addressing specific incidents, generally denies that Grass was instructed to complete any work outside the scope of their agreement, but accepts the contention solely for the purposes of this motion. (Def.' sM. Limine 2.).
At the time the dispute arose, Grass refused to continue work on the project until Grass and PM agreed on written change orders delineating the scope of the new work as well as Grass's compensation for performing. (Pl.'s Opp. M. Limine 4-5.). Grass claims that PM's project manager issued assurances that change orders would be executed, but that instead of providing change orders, PM hired another excavation company to perform the additional work and the remaining work under the Contract. (Pl.' s Opp. M. Limine 5.). PM disagrees that change orders were necessary, and alleges that Grass left the project. (Def.' s M. Limine 1-2.).
At issue is the interpretation of Article 9 of the Contract, reprinted here in full:
Contractor may unilaterally make changes in the work covered by this Subcontract. Upon receipt of Contractor's written authorization to proceed with changed work, Subcontractor shall perform the changed work without delay. Extra compensation for such changed work will only be allowed when the amount has been agreed to prior to the execution of the changed work or when Contractor has been paid extra compensation by the Owner for said changed work. No compensation for changes or any other claims whatsoever shall be allowed unless Contractor is entitled to payment for Owner and the claim is submitted to Contractor in a timely fashion allowing Contractor to process the claim under the terms of the Contract Documents. The failure to so submit claims in a timely manner shall be deemed a waiver of the claim by the Subcontractor. All changes must be authorized by Contractor's form before payment will be made. (Def. Exh.
1,2).
ll. APPLICABLE LAW
"The issue of whether contract language is ambiguous is a question of law for the court." Portland Valve, Inc. v. Rockwood Systems Corp., 460 A.2d 1383, 1387 (Me. 1983). See also Beal v. Allstate Insurance Company, 2010 ME 20, ~ 26,989 A.2d 733, 741. If the contract language is unambiguous, its interpretation is also a question oflaw for the Court. Portland Valve, 460 A.2d at 1387. "A contract provision is considered ambiguous if it is reasonably possible to give that provision at least two different meanings." Villas by the Sea Owners Ass 'n v. Garrity, 2000 ME 48, ~ 9, 748 A.2d 457, 461. "The parol evidence rule operates to exclude from judicial consideration extrinsic evidence offered to alter, augment or contradict the unambiguous language of an integrated written agreement." Handy Boat Servo v. Proffessional Servs., 1998 ME 134, ~ 11, 711 A.2d 1306, 1308-09.
III DISCUSSION
a. Ambiguity and the Parol Evidence Rule PM argues that Article 9 is an unambiguous statement that PM could unilaterally make changes to Grass's scheduled work, which Grass was obligated to perform upon receipt of written authorization. Regarding payment, PM points out that there are two possible methods for payment in Article 9: upon an agreement for extra compensation in advance of the work being done, or if the Owner compensated PM for the extra work. PM classifies the payment provisions as a condition precedent to Grass obtaining extra payment and not a pre-condition to the obligation to perform extra work.
Grass counters by arguing that Article 9 is ambiguous because "[i]t makes no sense that within the same paragraph, one can first force someone to do work without receiving compensation and then state that no extra compensation will be allowed for the
work if it is not agreed to prior to execution ofthe work." (PI.' s Opp. M. Limine 10.) (emphasis added). The plain language of Article 9 speaks against this argument.
Article 9 states that "[e]xtra compensation for such changed work will only be allowed when the amount has been agreed to prior to the execution of the changed work or when Contractor has been paid extra compensation by the Owner for said changed work." (Def. Exh. 1,2). This statement, while serving the interests of PM, is not ambiguous. It simply means that if there is not an agreement for payment prior to PM providing Grass with a work authorization, PM will pay Grass upon receiving compensation for the extra work from Richmond. There is no provision in Article 9 saying that a claim for compensation for extra work must be provided prior to the work being completed, as Grass argues. The Contract provision simply requires the claim to be made "in a timely fashion" (alternatively, it is also referred to as "in a timely manner"). (Def. Exh. 1, 2). Thus, a plain reading of Article 9 shows a single method for PM to direct Grass to complete extra work and two non-conflicting, unambiguous pathways for Grass to be compensated for performing.
Free access — add to your briefcase to read the full text and ask questions with AI
Grass v. Bangor (Grass v. Bangor) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.