Grass v. Bangor

CourtSuperior Court of Maine
DecidedDecember 9, 2010
DocketPENre-08-14
StatusUnpublished

This text of Grass v. Bangor (Grass v. Bangor) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grass v. Bangor, (Me. Super. Ct. 2010).

Opinion

STATE OF MAINE SUPERIOR COURT PENOBSCOT, ss CIVIL ACTION DOCKET NO. RE-Or~4 WRf1~ f'~ tJ - Ic;Y~1 ,)010 JEFFREY B. GRASS, d/b/a J.B. GRASS EXCAVATING

Plaintiff,

v. ORDER ON DEFENDANT PM CONSTRUCTION'S RICHMOND BANGOR MOTION IN LIMINE DEVELOPMENT, LLC, PM CONSTRUCTION CO., INC., EASTERN BANK and KATAHDIN TRUST COMPANY

Defendants.

Before the Court is Defendant PM Construction Co., Inc. ("PM")'s motion in

limine requesting that Article 9 ("Article 9") of the contract ("Contract") between PM

and Plaintiff Jeffrey B. Grass, d/b/a J.B. Grass Excavating ("Grass") be found

unambiguous, therefore excluding any parol evidence relating to Article 9. Additionally,

PM asks that the Court "rule that Article 9 did not require PM Construction and Grass to

agree upon and execute change orders as a condition precedent to Grass being obligated

to perfonn changes to the scope of work as originally set forth in the Contract." (Def.' s

M. Limine 1.). In response, Grass has filed in opposition to PM's motion, requesting

that the Court rule that the Contract was unambiguous but required written change orders

between Grass and PM before any additional work was to be performed. In the

alternative, Grass requests that the Court find that the relevant Contract provisions are

ambiguous. Finally, Grass asks that if PM's interpretation of the Contract is adopted,

Article 9 be found unconscionable, invalid and unenforceable. (PI.' s Opp. M. Limine 1.).

1 1. FACTUAL BACKGROUND

Grass and PM agree about little in the factual record. Points of disagreement

between the parties regarding the facts will be noted. In or about September 2007, PM

and Grass entered into the Contract with PM serving as the contractor and Grass a

subcontractor on a project building a Walgreen's Pharmacy in Bangor. The Contract,

which both parties acknowledge as accurate, is attached as Exhibit 1 to Defendant's

Motion in Limine. The parties also both acknowledge that Exhibit 2 to Defendant's

Motion in Limine, entitled "AlA Document A 101™ - 1997" ("Owner's Contract") is the

controlling agreement between PM and the site's owner The Richmond Company, Inc.

("Richmond").

At some point during the project, a dispute arose between Grass and PM

regarding the scope of the excavation work Grass was obligated to perform under the

Contract. Grass contends that after beginning work on the project, it was discovered that

serious differences existed between the elevations identified in the site plans and

documents provided by PM and the actual elevations at the site. (PI.' s Opp. M. Limine

3.). Further, Grass alleges that PM instructed Grass to alter the proscribed method for

excavating trenches after Grass had began performing the work, creating a significant

increase in work. (PI.' s Opp. M. Limine 4.). Finally, Grass claims that the initial plans

and specifications indicated that the soils excavated on site would be used for fill and

backfill, but after commencing work PM directed him to remove the excavated soil and

obtain backfill from off site, which caused Grass added work and expenses. ld.

2 PM, while not addressing specific incidents, generally denies that Grass was

instructed to complete any work outside the scope of their agreement, but accepts the

contention solely for the purposes of this motion. (Def.' sM. Limine 2.).

At the time the dispute arose, Grass refused to continue work on the project until

Grass and PM agreed on written change orders delineating the scope of the new work as

well as Grass's compensation for performing. (Pl.'s Opp. M. Limine 4-5.). Grass claims

that PM's project manager issued assurances that change orders would be executed, but

that instead of providing change orders, PM hired another excavation company to

perform the additional work and the remaining work under the Contract. (Pl.' s Opp. M.

Limine 5.). PM disagrees that change orders were necessary, and alleges that Grass left

the project. (Def.' s M. Limine 1-2.).

At issue is the interpretation of Article 9 of the Contract, reprinted here in full:

Contractor may unilaterally make changes in the work covered by this Subcontract. Upon receipt of Contractor's written authorization to proceed with changed work, Subcontractor shall perform the changed work without delay. Extra compensation for such changed work will only be allowed when the amount has been agreed to prior to the execution of the changed work or when Contractor has been paid extra compensation by the Owner for said changed work. No compensation for changes or any other claims whatsoever shall be allowed unless Contractor is entitled to payment for Owner and the claim is submitted to Contractor in a timely fashion allowing Contractor to process the claim under the terms of the Contract Documents. The failure to so submit claims in a timely manner shall be deemed a waiver of the claim by the Subcontractor. All changes must be authorized by Contractor's form before payment will be made. (Def. Exh. 1,2).

ll. APPLICABLE LAW

3 "The issue of whether contract language is ambiguous is a question of law for the

court." Portland Valve, Inc. v. Rockwood Systems Corp., 460 A.2d 1383, 1387 (Me.

1983). See also Beal v. Allstate Insurance Company, 2010 ME 20, ~ 26,989 A.2d 733,

741. If the contract language is unambiguous, its interpretation is also a question oflaw

for the Court. Portland Valve, 460 A.2d at 1387. "A contract provision is considered

ambiguous if it is reasonably possible to give that provision at least two different

meanings." Villas by the Sea Owners Ass 'n v. Garrity, 2000 ME 48, ~ 9, 748 A.2d 457,

461. "The parol evidence rule operates to exclude from judicial consideration extrinsic

evidence offered to alter, augment or contradict the unambiguous language of an

integrated written agreement." Handy Boat Servo v. Proffessional Servs., 1998 ME 134, ~

11, 711 A.2d 1306, 1308-09.

III DISCUSSION

a. Ambiguity and the Parol Evidence Rule

PM argues that Article 9 is an unambiguous statement that PM could unilaterally

make changes to Grass's scheduled work, which Grass was obligated to perform upon

receipt of written authorization. Regarding payment, PM points out that there are two

possible methods for payment in Article 9: upon an agreement for extra compensation in

advance of the work being done, or if the Owner compensated PM for the extra work.

PM classifies the payment provisions as a condition precedent to Grass obtaining extra

payment and not a pre-condition to the obligation to perform extra work.

Grass counters by arguing that Article 9 is ambiguous because "[i]t makes no

sense that within the same paragraph, one can first force someone to do work without

receiving compensation and then state that no extra compensation will be allowed for the

4 work if it is not agreed to prior to execution ofthe work." (PI.' s Opp. M. Limine 10.)

(emphasis added). The plain language of Article 9 speaks against this argument.

Article 9 states that "[e]xtra compensation for such changed work will only be

allowed when the amount has been agreed to prior to the execution of the changed work

or when Contractor has been paid extra compensation by the Owner for said changed

work." (Def. Exh. 1,2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beal v. Allstate Insurance Co.
2010 ME 20 (Supreme Judicial Court of Maine, 2010)
Barrett v. McDonald Investments, Inc.
2005 ME 43 (Supreme Judicial Court of Maine, 2005)
Handy Boat Service, Inc. v. Professional Services, Inc.
1998 ME 134 (Supreme Judicial Court of Maine, 1998)
Villas by the Sea Owners Ass'n v. Garrity
2000 ME 48 (Supreme Judicial Court of Maine, 2000)
Portland Valve, Inc. v. Rockwood Systems Corp.
460 A.2d 1383 (Supreme Judicial Court of Maine, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Grass v. Bangor, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grass-v-bangor-mesuperct-2010.