Graham Construction Services, Inc. and Travelers Casualty and Surety Company v. City of Corpus Christi

Court of Appeals of Texas·Decided December 30, 2024·No. 13-22-00536-CV·Published

Opinion

NUMBER 13-22-00536-CV

COURT OF APPEALS

THIRTEENTH DISTRICT OF TEXAS

CORPUS CHRISTI – EDINBURG

GRAHAM CONSTRUCTION SERVICES, INC. AND TRAVELERS CASUALTY AND SURETY COMPANY, Appellants,

v.

CITY OF CORPUS CHRISTI, Appellee.

ON APPEAL FROM THE COUNTY COURT AT LAW NO. 2 OF NUECES COUNTY, TEXAS

MEMORANDUM OPINION

Before Chief Justice Contreras and Justices Benavides and Silva Memorandum Opinion by Chief Justice Contreras

We issued our memorandum opinion and judgment in this matter on November 7,

2024. Both parties have filed motions for rehearing. See TEX. R. APP. P. 49. We deny the

motions for rehearing, but withdraw our November 7, 2024 memorandum opinion and judgment, and substitute the following memorandum opinion and accompanying

judgment in their place.

This case concerns the construction of a new wastewater treatment plant in

Corpus Christi. Appellee/cross-appellant, the City of Corpus Christi (the City), hired

appellant/cross-appellee Graham Construction Services, Inc. (Graham) to construct the

plant, but various disputes arose, and the parties sued each other. After a bench trial, the

trial court found in favor of the City on some claims and in favor of Graham on others.

Overall, with the opposing damages awards offset against each other, the final judgment

awarded the City nearly $1.3 million. Graham and fellow appellant/cross-appellee

Travelers Casualty and Surety Company (Travelers) challenge the trial court’s judgment

by two multifarious issues, and the City raises three issues on cross-appeal. We affirm in

part and reverse and render in part.

I. BACKGROUND

A. The Contract

In 2009, the City hired general contractor Graham to replace the Broadway

Wastewater Treatment Plant with a new facility. The parties executed a contract spanning

over four thousand pages which included detailed technical specifications. The contract

named Carollo Engineers, P.C. (Carollo) as the engineer of record and as the City’s

representative for purposes of administering the contract and observing the construction.

Travelers provided a performance bond in favor of the City, as required by the contract

and by statute.

According to the contract, the project was to be completed in two phases: Phase

1 included demolition of most of the old facility and construction of most of the new

2 facility’s infrastructure, while Phase 2 included the remaining work, such as the installation

of two clarifiers intended to increase the new facility’s capacity. The contract contained

the following Paragraph 4.02 delineating the expected timeframe for completion of the

phases:

Substantial Completion Completion

Phase 1 840 calendar days 900 calendar days

Phase 2 (to commence 200 calendar days 260 calendar days upon substantial completion of Phase 1)

Total Contract Time N/A 1,100 calendar days

In Paragraph 4.03, entitled “Liquidated Damages,” the contract stated:

A. [Graham] and [the City] recognize that time is of the essence of this Agreement, that Work under other contracts is dependent on the timely and satisfactory completion of the Work, and that [the City] will suffer financial loss if the Work is not completed within the times specified in paragraph 4.02, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize that it will be impracticable to determine actual damages which [the City] will sustain in the event of or by reason of the delay. Accordingly, instead of requiring any such proof, [the City] and [Graham] agree that as liquidated damages for delay (but not as a penalty) [Graham] shall pay [the City] the following amounts for each day that expires after the specified time in paragraph 4.02 for substantial completion until the Work is substantially complete. . . . It is further agreed that the amount stipulated for liquidated damages per day of delay is a reasonable estimate of the damages that would be sustained by [the City], and [Graham] agrees to pay such liquidated damages as herein provided. . . .

3 Item Liquidated Damages, per calendar day

Phase 1 Substantial Completion of the Work $2,600

Phase 2 Substantial Completion of the Work $2,600 Completion of all Work $1,600

The contract further stated as follows in a document entitled “General and Supplemental

Conditions”:

3.04 Amending and Supplementing Contract Documents

A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways: (i) a Written Amendment; (ii) a Change Order; or (iii) a Work Change Directive.

....

6.18 Continuing the Work

A. [Graham] shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with [the City]. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, excepts as permitted by paragraph 15.04 or as [the City] and [Graham] may otherwise agree in writing.

....

14.04 Substantial Completion

A. When [Graham] considers the entire Work ready for its intended use [Graham] shall notify [the City] and [Carollo] in writing that the entire Work is substantially complete (except for items specifically listed by [Graham] as incomplete) and request that [Carollo] issue a certificate of Substantial Completion. Promptly thereafter, [the City], [Graham], and [Carollo] shall make an inspection of the Work to determine the status of completion. If [Carollo] does not consider the Work substantially complete, [Carollo] will notify [Graham] in writing giving the reasons therefor. If [Carollo] considers the Work substantially complete, [Carollo] will prepare and deliver to [the City] a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion. There shall be attached to the certificate a

4 tentative list of items to be completed or corrected before final payment. [The City] shall have seven days after receipt of the tentative certificate during which to make written objection to [Carollo] as to any provisions of the certificate or attached list. If, after considering such objections, [Carollo] concludes that the Work is not substantially complete, [Carollo] will within 14 days after submission of the tentative certificate to [the City] notify [Graham] in writing, stating the reasons therefor. If, after consideration of [the City]’s objections, [Carollo] considers the Work substantially complete, [Carollo] will within said 14 days execute and deliver to [the City] and [Graham] a definitive certificate of Substantial Completion (with a revised list of items to be completed or corrected) reflecting such changes from the tentative certificate as [Carollo] believes justified after consideration of any objections from [the City].

....

15.02 [The City] May Terminate for Cause

A. If [Graham] refuses or fails to prosecute the Work . . . [the City] may without prejudice to any other right or remedy, serve written notice upon [Graham] and [Graham]’s surety of [the City]’s intention to terminate the Contract. Such notice will contain the reasons for [the City]’s intention to terminate the Contract and unless such violations shall cease and satisfactory arrangements for the corrections thereof have been accepted by [the City] in writing within 20 days after the service of such notice, the Contract shall upon the expiration of said 20 days cease and terminate.

Free access — add to your briefcase to read the full text and ask questions with AI

Graham Construction Services, Inc. and Travelers Casualty and Surety Company v. City of Corpus Christi, (Tex. Ct. App. 2024).

Graham Construction Services, Inc. and Travelers Casualty and Surety Company v. City of Corpus Christi (Graham Construction Services, Inc. and Travelers Casualty and Surety Company v. City of Corpus Christi) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
PAJ, Inc. v. Hanover Insurance Co.
243 S.W.3d 630 (Texas Supreme Court, 2008)
Ridgway v. TTnT Development Corp.
26 S.W.3d 428 (Missouri Court of Appeals, 2000)
Briscoe v. Goodmark Corp.
102 S.W.3d 714 (Texas Supreme Court, 2003)
Hudson v. Wakefield
711 S.W.2d 628 (Texas Supreme Court, 1986)
Stewart v. Basey
245 S.W.2d 484 (Texas Supreme Court, 1952)
Phillips v. Phillips
820 S.W.2d 785 (Texas Supreme Court, 1992)
Middle States Petroleum Corp. v. Messenger
368 S.W.2d 645 (Court of Appeals of Texas, 1963)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Tittizer v. Union Gas Corp.
171 S.W.3d 857 (Texas Supreme Court, 2005)
Perry v. Del Rio
66 S.W.3d 239 (Texas Supreme Court, 2001)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Criswell v. European Crossroads Shopping Center, Ltd.
792 S.W.2d 945 (Texas Supreme Court, 1990)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
McKnight v. Hill & Hill Exterminators, Inc.
689 S.W.2d 206 (Texas Supreme Court, 1985)
Ortiz v. Jones
917 S.W.2d 770 (Texas Supreme Court, 1996)
Texas Department of Transportation v. Needham
82 S.W.3d 314 (Texas Supreme Court, 2002)
Gulf States Utilities Co. v. Low
79 S.W.3d 561 (Texas Supreme Court, 2002)