Gradetech, Inc. v. City of San Jose

CourtDistrict Court, N.D. California
DecidedApril 3, 2020
Docket5:19-cv-06157
StatusUnknown

This text of Gradetech, Inc. v. City of San Jose (Gradetech, Inc. v. City of San Jose) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gradetech, Inc. v. City of San Jose, (N.D. Cal. 2020).

Opinion

1 2 3 4 5 6 UNITED STATES DISTRICT COURT 7 NORTHERN DISTRICT OF CALIFORNIA 8

9 GRADETECH, INC., and SAM Case No. 19-cv-06157-NC 10 RIVINIUS ORDER GRANTING IN PART AND 11 Plaintiffs, DENYING IN PART DEFENDANTS’ 12 v. MOTION TO DISMISS; GRANTING LEAVE TO AMEND 13 CITY OF SAN JOSE, et al., 14 Defendants. Re: Dkt. No. 17

15 16 This case arises out of an ongoing dispute between the City of San Jose and 17 contractor Gradetech, Inc. over a bike park construction project. Gradetech and its owner, 18 Sam Rivinius, bring claims under 42 U.S.C. § 1983 against the City of San Jose and its 19 employees for First Amendment retaliation and due process violations, and also seek a writ 20 of mandamus reversing their disqualification from a later contract. Defendants move to 21 dismiss all claims under Rule 12. The Court FINDS that Plaintiffs adequately alleged their 22 First Amendment retaliation claim, their due process claim for deprivation of property, and 23 their claim for a writ of mandamus and DENIES the motion to dismiss those claims. The 24 Court FINDS that Plaintiffs have not alleged sufficient facts to state a claim for deprivation 25 of their liberty based on either their right to bid on City contracts or their reputational 26 harm. The Court GRANTS the motion to dismiss that claim. Finding that the plaintiffs 27 could allege additional facts to cure, the Court GRANTS LEAVE TO AMEND. Finally, 1 I. Background 2 A. Facts Alleged in the First Amended Complaint 3 Plaintiffs allege the following facts in the First Amended Complaint at Dkt. No. 15. 4 These are factual allegations, not findings by the Court. For the purposes of this motion, the 5 Court assumes these facts are true. Cahill v. Liberty Mut. Ins. Co., 80 F.3d 336, 337–38 (9th 6 Cir. 1996). 7 The Lake Cunningham Bike Park Construction Project 8 Gradetech, Inc. is a licensed California contractor that has worked with the City of 9 San Jose and other government agencies in the Bay Area on many occasions since its 10 founding in 1991, including over 600 government contracts and 35 projects with San Jose. 11 FAC ¶¶ 5, 63, 69. In March 2016, Gradetech entered into a contract with the City of San 12 Jose for the Lake Cunningham Bike Park Construction Project. Id ¶ 16. The Project was 13 set to begin in May of that year. Id. ¶ 17. Throughout the Project, consultants and staff 14 from the City of San Jose caused cost increases and substantially delayed Project 15 completion by enlarging the Project’s features from what was shown on the plans. Id. ¶ 16 19. On September 1, 2016, Gradetech submitted a Notice of Potential Claim to defendant 17 Chris Mastrodicasa, the Associate Landscape Developer for the City, based on significant 18 changes in grading quantities. Id. ¶¶ 10, 19. Plaintiffs expressed concerns about both the 19 mismanagement of the Project and about safety issues, but the City ignored and rebuffed 20 their concerns. Id. ¶¶ 19, 20, 51. 21 The State Court Lawsuit 22 On November 15, 2017, Gradetech submitted a claim for $1.85 million in additional 23 amounts due under the Cunningham Project contract. Id. ¶ 21. This included a Daily 24 Extra Work Report. Id. On January 26, 2018, Gradetech filed a government claim against 25 the City, which was denied. Id. ¶ 23. In March 2018, Gradetech filed a lawsuit against the 26 City in Santa Clara County Superior Court for breach of contract based on the City’s 27 failure to compensate Gradetech for its work on the Project. Id. ¶ 24. In a March 2019 1 Gradetech) about payroll data discrepencies in the Daily Extra Work Report. Id. ¶ 30. 2 Other Projects 3 In January 2019, the City sought bids from contractors for Minor Street Projects. 4 Id. ¶ 25. Gradetech submitted a bid. Id. ¶ 28. Its application exceeded minimum passing 5 scores and passed all pass/fail requirements. Id. ¶ 29. In May 2019, Gradetech received a 6 letter from the City’s Department of Public Works entitled “Notice of Disqualification,” 7 stating that Gradetech had been disqualified from the Minor Street Projects contractor 8 pool. Id. ¶ 31. The letter said that Gradetech’s “submittal was timely, responsive, and 9 scored above the minimum needed points,” but that “Gradetech [was] not qualified 10 because it submitted materially incorrect documentation of compensation in the . . . Lake 11 Cunningham Bike Park contract.” Id. A footnote of the letter stated: “Gradetech has filed 12 a lawsuit against the City seeking more than $1,853,000 in additional compensation. The 13 lawsuit is currently pending.” Id. ¶ 32. The letter invited Gradetech to request in writing a 14 hearing on the disqualification within 10 business days, and Gradetech did so. Id. ¶ 31. 15 Also in May 2019, defendant Matthew Cano, the City’s Public Works Director, 16 abruptly terminated the City’s 2018 General Engineering Construction for Transportation 17 Projects contract with Gradetech without warning or explanation. Id. ¶ 33. In June 2019, 18 Gradetech submitted the lowest bit and satisfied all bidding requirements for the City’s 19 Coyote Creek Trail Project. Id. ¶ 38. The only other bidders submitted higher bids and 20 failed to satisfy all requirements. Id. Instead of awarding the contract to Gradetech, the 21 City extended the other bidders’ deadline by 90 days—but did not extend Gradetech’s— 22 and withheld awarding the contract. Id. 23 The Hearing on the Minor Street Projects Disqualification 24 The hearing that Gradetech requested on its disqualification from the Minor Street 25 Projects contract took place on June 21, 2019. Id. ¶ 34. Defendant Jim Ortbal, San Jose’s 26 Deputy City Manager, served as the Hearing Officer. Id. Defendant Matt Loesch, San 27 Jose’s Assistant Direct of Public Works, served as the Hearing Administrator. Id. ¶¶ 10, 1 Public Works Department appeared for the City. Id. ¶ 34. At the hearing, Mr. Rivinius 2 “took responsibility for the problem” with the discrepancies in the Daily Work Report 3 from the Lake Cunningham Bike Park Construction Project and said “that he would correct 4 it.” Id. Rivinius “admitted he was mistaken in certifying incorrect employee payroll hours 5 as part of his government claim” and has since “withdrawn and corrected those mistakes.” 6 Id. ¶ 65. 7 On July 1, 2019, Jim Ortbal issued a letter affirming Gradetech’s disqualification 8 from the Minor Street Projects. Id. ¶ 36. The letter acknowledged that Gradetech had 9 scored above the required number of points and had successfully completed 35 jobs for the 10 City in the past. Id. ¶ 37. It stated that the reason for the disqualification was the 11 “contradictory, certified payroll records submitted by Gradetech in relation to the Lake 12 Cunningham project.” Id. It also included a footnote identical to that of the May 13 disqualification letter referring to the state court breach of contract lawsuit seeking more 14 than $1,853,000 in additional compensation. Id. ¶ 36. 15 Debarment 16 “At some point after Gradetech submitted its Notice of Potential Claim” in 17 September 2016, defendant Chris Mastrodicasa “began ‘trying to work on’ getting 18 Gradetech debarred from all City projects.” Id. ¶ 49. Other “senior staff at the City,” 19 including the other defendants in this case, “also began to scheme about Gradetech’s 20 debarment.” Id. 21 In August 2019, Gradetech received a letter from the City entitled “Notice of 22 Debarment.” Id. ¶ 39. The letter included an investigative report dated August 12, 2019, 23 authored by Public Works Director Matthew Cano. Id. The report recited the events 24 leading up to the Minor Street Projects contractor pool disqualification and “appeared to 25 rely on these events, among other things, in support of its recommendation for debarment.” 26 Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Buckley v. Valeo
424 U.S. 1 (Supreme Court, 1976)
Paul v. Davis
424 U.S. 693 (Supreme Court, 1976)
Harlow v. Fitzgerald
457 U.S. 800 (Supreme Court, 1982)
Connick Ex Rel. Parish of Orleans v. Myers
461 U.S. 138 (Supreme Court, 1983)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Washington v. Glucksberg
521 U.S. 702 (Supreme Court, 1997)
Conn v. Gabbert
526 U.S. 286 (Supreme Court, 1999)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Gradetech, Inc. v. City of San Jose, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gradetech-inc-v-city-of-san-jose-cand-2020.