Grace Petroleum Corporation v. Federal Energy Regulatory Commission

815 F.2d 589, 96 Oil & Gas Rep. 429, 1987 U.S. App. LEXIS 4063
CourtCourt of Appeals for the Tenth Circuit
DecidedMarch 31, 1987
Docket85-2038
StatusPublished

This text of 815 F.2d 589 (Grace Petroleum Corporation v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grace Petroleum Corporation v. Federal Energy Regulatory Commission, 815 F.2d 589, 96 Oil & Gas Rep. 429, 1987 U.S. App. LEXIS 4063 (10th Cir. 1987).

Opinion

815 F.2d 589

GRACE PETROLEUM CORPORATION, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Plains Resources, Inc. and Arkla Energy Resources, a
division of Arkla, Inc., Intervenors.

No. 85-2038.

United States Court of Appeals,
Tenth Circuit.

March 31, 1987.

Patricia Fry Eldridge of Bracewell & Patterson, Houston, Tex. (Charles H. Shoneman and Randall S. Rich, Bracewell & Patterson, Washington, D.C., with her, on the briefs), for petitioner Grace Petroleum Corp.

Joseph R. Hartsoe, Attorney (William H. Satterfield, General Counsel, Jerome M. Feit, Solicitor, and Andrea Wolfman, Attorney, with him on the brief), F.E.R.C., Washington, D.C., for respondent F.E.R.C.

Stanley L. Cunningham (C. David Stinson, also of McAfee & Taft, Oklahoma City, Okl., with him, on the brief), for intervenor Plains Resources, Inc.

Before LOGAN, MOORE, and ANDERSON, Circuit Judges.

LOGAN, Circuit Judge.

This appeal concerns the price that small producers may receive for natural gas delivered after an existing contract has expired, but before a rollover contract has been executed. In 1973, petitioner Grace Petroleum Corporation (Grace), then a small producer,1 succeeded to another small producer's interest in a 1962 contract to sell natural gas to Arkansas Louisiana Gas Company (Arkla). This 1962 contract expired on December 13, 1982, before a rollover contract2 was executed. Because the gas in question was dedicated to interstate commerce, Grace was obligated, pursuant to 15 U.S.C. Sec. 717f(b), to continue deliveries after the contract expired.3

On May 2, 1984, Grace and Arkla executed a rollover contract. The parties explicitly agreed that "[t]he rollover gas purchase contract will be effective on December 13, 1982," the expiration date of the prior contract. R. I, 35. Under the rollover contract, Grace was to receive a higher price, the maximum allowed under Sec. 106(a) of the Natural Gas Policy Act (NGPA), 15 U.S.C. Sec. 3316(a).

Grace petitioned the Federal Energy Regulatory Commission for a declaratory order allowing Grace to receive the higher price for December 13, 1982, to May 2, 1984--the period after the original contract had expired but before the rollover contract had been executed. At issue in this appeal are the Commission's orders denying Grace's petition, Grace Petroleum Corp., Order Denying Petition for Declaratory Order, 30 Fed. Energy Reg. Comm'n Rep. (CCH) p 61,321 (March 25, 1985) (hereinafter March 25 Order), and Grace Petroleum Corp., Order Denying Rehearing, 31 Fed. Energy Reg. Comm'n Rep. (CCH) p 61,220 (May 23, 1985) (hereinafter May 23 Order).

Grace alleges that the Commission acted arbitrarily in failing to follow its own precedent and that the Commission exceeded its authority under the NGPA in denying Grace's petition. Plains Resources, Inc., a small producer negotiating similar retroactive rollover contracts, has intervened on appeal. Plains argues that the Commission's orders are contrary to the regulatory scheme under the National Gas Act (NGA), 15 U.S.C. Secs. 717-717w, and fail to recognize the existence of a contract implied in fact during the interim period. Because we hold that the Commission in denying Grace's petition has arbitrarily disregarded its own prior interpretations of Sec. 106(a) of the NGPA, 15 U.S.C. Sec. 3316(a), we do not reach the other arguments.

Section 106(a)(1)(A) of the NGPA allows small producers to charge the higher rollover price beginning with "the month in which the effective date of such rollover contract occurs." 15 U.S.C. Sec. 3316(a)(1)(A) (emphasis added). Two of the Commission's decisions allowed small producers to contract for an effective date before the actual execution of the rollover contract. Spradling Drill Co., 14 Fed. Energy Reg. Comm'n Rep. (CCH) p 61,145, at 61,265 (Feb. 19, 1981) (A small producer is "entitled to collect [the Sec. 106(a)(1)(A) rollover] rate as of the effective date authorized by the contract."); Riddell Petroleum Corp., 16 Fed. Energy Reg. Comm'n Rep. (CCH) p 61,047, at 61,083 (July 24, 1981) ("Riddell, as a small producer, is entitled to collect [the rollover rate] ... as of the date agreed upon by the parties as being the contract's effective date."). Under these decisions, Grace should be allowed to contract for a retroactive "effective" date that would allow it to receive the higher Sec. 106(a) rollover price during this interim period. The Commission does not oppose this reading of Spradling and Riddell, but argues instead that these decisions have been properly overruled.

While an agency has a well-settled right to modify or even overrule established precedent, "it is equally settled that an agency must provide a reasoned explanation for any failure to adhere to its own precedents." Hatch v. FERC, 654 F.2d 825, 834 (D.C.Cir.1981); accord Squaw Transit Co. v. United States, 574 F.2d 492, 496 (10th Cir.1978) ("[W]e surely must require the agency to adhere to its own pronouncements, or explain its departure from them."). "[A]n agency changing its course must supply a reasoned analysis indicating that prior policies and standards are being deliberately changed and not casually ignored, and if an agency glosses over or swerves from prior precedent without discussion it may cross the line from the tolerably terse to the intolerably mute." Greater Boston Television Corp. v. FCC, 444 F.2d 841, 852 (D.C.Cir.1970) (footnotes omitted), cert. denied, 403 U.S. 923, 91 S.Ct. 2229, 29 L.Ed.2d 701 (1971). See also 4 K. Davis, Administrative Law Treatise Sec. 20:11 (2d ed. 1983).4

To explain its failure to adhere to its own precedent, the Commission first contends that two intervening decisions, Transcontinental Gas Pipe Line Corp., 17 Fed. Energy Reg. Comm'n Rep. (CCH) p 61,232 (Dec. 11, 1981) (Transco ), and United Gas Pipe Line Co., 24 Fed. Energy Reg. Comm'n Rep. (CCH) p 61,083 (July 19, 1983), overturned the rule embraced by Spradling and Riddell. In these cases the Commission prohibited retroactive modification of existing contracts. See Transco, supra, at 61,453 ("[C]ontract modifications ... permit collection of NGPA rates only from the date of contract amendment."); United, supra, at 61,221 ("[T]hese contracts can only provide authority for [statutory] prices after the contract modification or amendment was executed."). Neither case involved the present issue, whether a rollover contract could be retroactively applied for the period after the original contract has expired; neither mentioned the Spradling and Riddell decisions.

Transco and United thus gave no notice that the rule enunciated in Spradling and Riddell had changed. In fact, the Riddell decision itself distinguished modifications of existing contracts from the execution of new rollover contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
815 F.2d 589, 96 Oil & Gas Rep. 429, 1987 U.S. App. LEXIS 4063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grace-petroleum-corporation-v-federal-energy-regulatory-commission-ca10-1987.