Goudy & Stevens, Inc. v. Cable Marine, Inc.

924 F.2d 16, 1991 A.M.C. 1672, 1991 U.S. App. LEXIS 928, 1991 WL 4590
CourtCourt of Appeals for the First Circuit
DecidedJanuary 23, 1991
Docket89-2037
StatusPublished
Cited by33 cases

This text of 924 F.2d 16 (Goudy & Stevens, Inc. v. Cable Marine, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goudy & Stevens, Inc. v. Cable Marine, Inc., 924 F.2d 16, 1991 A.M.C. 1672, 1991 U.S. App. LEXIS 928, 1991 WL 4590 (1st Cir. 1991).

Opinion

TORRUELLA, Circuit Judge.

Appellee Goudy & Stevens, Inc. instituted this action in admiralty to enforce a lien for materials and labor furnished for the construction of the vessel WARRIOR. Appellants Cable Marine, Inc., 16th Street Properties, and the WARRIOR counterclaimed to recover damages suffered as a result of the sinking of the vessel while tied up to appellee’s dock. A judgment entered into by the parties prior to trial disposed of the original claims. A six-day bench trial on the remaining counterclaims led to the district court’s conclusion that appellee was in fact a bailee of the vessel within the legal meaning of the term, but that the shipyard was not liable for the damages suffered as a result of the vessel’s sinking. It is from this latter determination that appellants now seek recourse before us. We affirm.

I

On June 16, 1985, co-appellant 16th Street Properties purchased the sports fishing yacht WARRIOR from Warrior Yachts, Inc. The WARRIOR was of custom design and had been built for Warrior Yachts by appellee Goudy & Stevens. Goudy & Stevens is a corporation which operates a boatyard in East Boothbay, Maine. 1 Construction of the WARRIOR had begun in 1981 and ceased in 1983 when a dispute arose between Goudy & Stevens and the yacht’s prior owner over construction costs and delays related thereto.

Upon purchasing the WARRIOR, 16th Street Properties issued a work order to Cable Marine, Inc., a corporation which owns several shipyards in Fort Lauderdale, Florida. The terms of the agreement called for Cable Marine to arrange for the outfitting of the WARRIOR at Goudy & Stevens on behalf of 16th Street Properties. It was agreed that Goudy & Stevens personnel, together with Cable Marine’s mechanic, Mr. Robert Douglas, were to prepare the vessel to navigate under its own power to Fort Lauderdale where permanent construction would be completed.

During the time the repairs were being made, Mr. Douglas worked at the shipyard virtually every day. Once permission was obtained from Goudy & Stevens for him to remain on board and work on the yacht, he had unrestricted access to the vessel at all times. Although employed as a mechanic by Cable Marine, his work on board the WARRIOR was not strictly in that capacity but extended to all aspects of the ship. Work consumed an average of ten hours a day, seven days a week. Goudy & Stevens personnel, on the other hand, were not encouraged to work overtime and were not allowed to work on weekends. Although Douglas worked independently from Goudy & Stevens personnel, they cooperated with one another in many respects.

We digress momentarily to note that the district court found that in the years leading up to the events of this case there had never been a twenty-four hour watchman on duty at the Goudy & Stevens yard. 2 Ordinarily, however, a guard had been on duty from 6:00 a.m. to 11:00 p.m. Even when a watchman was on duty his responsibilities were circumscribed to starting up the machinery during the morning and keeping a watch for fires that might flare up due to the activities of the day. Guards would spend most of their time on the construction side of the yard, walking over to the yacht side about once an hour to *18 check the vessels’ water lines. The gates to the yard were customarily left open twenty-four hours a day since many of the yachts’ owners stayed aboard their ships at the marina during the night. Goudy & Stevens personnel testified that the shipyard had never experienced any serious problems with vandalism.

On June 26, 1985, the WARRIOR was launched. The decision to launch the yacht was made even though work remained to be done, specifically with respect to certain hoses and clamps which were not yet installed. The operation was directed by Gene Huskins, Goudy & Stevens’ yacht supervisor, with Douglas and several other Goudy & Stevens employees assisting in the process. After the launching was completed, the vessel was secured to a floating dock by four lines on the yacht side of the yard, and remained so moored for the following two days. No problems were observed and the vessel did not appear to be taking on any water. Additional work was performed on the yacht on June 27 by both Douglas and Goudy & Stevens personnel, with Douglas being the last one to leave the vessel that day.

That night, Douglas was to pick up a principal of Cable Marine, by the name of George Cable, and the yacht’s intended captain, at the airport in Portland, Maine. They returned at approximately 1:30 a.m. on June 28, proceeded directly to Goudy & Stevens, and carried out a thorough inspection of the work that had been completed up to that point. They then left the vessel shortly after 2:15 a.m.

Around 5:00 a.m. that same morning, the WARRIOR was discovered sunk at the dock. Goudy & Stevens personnel contacted Mr. Cable immediately, and he then went to the boatyard to begin planning the salvage effort. At some point it was decided that Goudy & Stevens would undertake to raise the vessel. Salvage was begun on June 29, 1985 and the vessel cleared the water toward the end of that day. After the WARRIOR was raised, a number of marine surveyors examined her in an effort to determine the cause of the sinking. Although they concluded the obvious, that the sinking was caused by ingestion of water into the hull, they were unable to determine the point of entry, and the WARRIOR never leaked at the Goudy & Stevens yard after being raised.

II

The district court characterized the relationship between the parties as a bailment. A bailment, of course, is the delivery of goods by their owner to another for a specific purpose, and the acceptance of those goods by the other, with the express or implied promise that the goods will be returned after the purpose of the delivery has been fulfilled. 9 Williston on Contracts, § 1030, pp. 875-76. It has long been established that the law of bailment is applicable to suits for damages to or loss of a vessel that has been left with another for purposes of repair. See, e.g., Buntin v. Fletchas, 257 F.2d 512, 513 (5th Cir.1958). Thus, neither party could have reasonably taken issue with this finding of the district court, and neither has.

Appellants object to the trial court’s refusal to infer appellee’s negligence in carrying out its responsibilities as a bailee under the facts of this case. Generally, in order for a bailee to be held liable for damage to the bailed object, the bailor must establish that the bailee acted negligently in the performance of its duties and that its negligence was the proximate cause of the damage. Cf. Commercial Molasses Corp. v. N.Y. Barge Corp., 314 U.S. 104, 110, 62 S.Ct. 156, 160, 86 L.Ed. 89 (1941). However, “when the bailor shows delivery to a bailee and the bailee’s failure to return the thing bailed, he makes out a prima facie

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zahner v. Kijakazi
N.D. California, 2024
(PC) Allen v. Matteson
E.D. California, 2023
Santana v. County of Yuba
E.D. California, 2019
NUFI v. Garpo
Second Circuit, 2019
In Re: Parry
D. Massachusetts, 2018
Kam-Almez v. United States
682 F.3d 1364 (Federal Circuit, 2012)
Ward v. MB Properties, Inc.
Maine Superior, 2011
Northern Ins. Co. of NY v. Point Judith Marina
579 F.3d 61 (First Circuit, 2009)
In Re the Complaint of Martin
596 F. Supp. 2d 142 (D. Massachusetts, 2009)
Muller Boat Works, Inc. v. Unnamed 52' House Barge
464 F. Supp. 2d 127 (E.D. New York, 2006)
Jewelers Mutual Insurance v. N. Barquet, Inc.
410 F.3d 2 (First Circuit, 2005)
Standard Fire Insurance v. Thompson
245 F. Supp. 2d 242 (D. Maine, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
924 F.2d 16, 1991 A.M.C. 1672, 1991 U.S. App. LEXIS 928, 1991 WL 4590, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goudy-stevens-inc-v-cable-marine-inc-ca1-1991.