Gottstein v. Seattle Lumber & Commercial Co.

35 P. 133, 7 Wash. 424, 1893 Wash. LEXIS 180
CourtWashington Supreme Court
DecidedDecember 22, 1893
DocketNo. 809
StatusPublished
Cited by3 cases

This text of 35 P. 133 (Gottstein v. Seattle Lumber & Commercial Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gottstein v. Seattle Lumber & Commercial Co., 35 P. 133, 7 Wash. 424, 1893 Wash. LEXIS 180 (Wash. 1893).

Opinion

The opinion of the court was delivered by

Stiles, J.

Appellant brought this action to recover sundry damages for failure to perform a contract to furnish materials for, and to build, certain houses. The answer of the respondent Seattle Lumber and Commercial Company set up, in the first place, that it was a surety only for its co-respondent Earp, and, secondly, that shortly after the execution of the contract, by the mutual agreement of all the parties to it, it ivas rescinded and given up, the fire of June 6,1889, at Seattle, having so changed the condition of appellant and the lumber company that they could not go on; and it was also claimed that if appellant had suffered damage in the construction of the houses by Earp, or in his failure to construct them, it was under some contract or employment of which the lumber company had no knowledge.

Upon the trial the respondent lumber company alone appeared (Earp having made default), and it was developed that the claim that a rescission had taken place was based upon two alleged conversations occurring on June 10th, in which appellant was alleged to have suggested and requested that, on account of their common losses in the fire, the whole matter of building the houses be dropped. Appellant denied ever having requested or agreed to any such proposition, and insisted that even if there had been such [426]*426an agreement, the effect of it was obviated, and the contract was revived by the conduct of all parties in subsequently proceeding with the erection of the buildings until they were nearly finished. He testified that so far from having been embarrassed by the fire, he had just previously obtained a loan of nearly enough money to pay for the buildings, and that the money was in bank, and under the terms of the loan could be used only for the purpose of building. Earp, according to respondent’s claim, was to be the builder, and the lumber company was to furnish the lumber and mill work and guarantee his performance of the contract. It is conceded that in July, Earp proceeded with the building, obtaining his materials where he could, the lumber company having lost its mill, and having gone entirely out of the business in which it -was formerly engaged. The testimony of the two sides does not materially differ as to how the work came to be resumed. Earp demanded pay from appellant for the value of the work done and materials furnished before the fire; but appellant refused, and said: “You go ahead with the building.” No money was due, under the contract, until the frames of all the houses were up, when a payment of §3,000 was to be made. The amount demanded by Earp was only a few hundreds. The contract was not surrendered or changed, nor was any name erased therefrom. The architect, in making certificates of work done, from time to time, in all cases certified Earp and the lumber company as entitled to payment; and in several instances the lumber company indorsed on the certificates a direction to pay the amount named to Earp. When the buildings were almost completed it was found that large bills for labor and materials were unpaid, and Earp abandoned his place as manager of the construction, whereupon the manager of the lumber company, the same person who had signed the contract, was called into a conference with appellant and the archi[427]*427tect, and ft was claimed that he there proposed, or gave his assent to a proposition, that appellant should proceed, under the terms of the contract, to finish the buildings at the expense of the contractors, if there should be a deficit. None of the testimony showing the amount of the damage was controverted.

The principal errors urged by appellant are as follows:

1. Appellant’s seventh request was:

“You are further instructed that the execution of the said contract having been admitted, before you are authorized to find that the same was abandoned and rescinded, you must find from the evidence that the minds of all the parties to the said contract met and consented to such rescission.”

This request exactly expressed the law of the case, and if the modifications made by the court by,striking out the word “all” and inserting “and alleged rescission” after the second occurrence of the word ‘ ‘ contract, ’ ’ made the charge mean anything different from what it did before, it was error to make the changes. We think both forms mean the same thing, and should not reverse the case for any such cause. But when counsel propose a proper charge it ought to be given to the jury in the form submitted, if given at all.

2. In so far as appellant’s eighth request was good, it was covered by the seventh, as above quoted. It was bad because it was open to the construction that under it, if the lumber company was a surety merely, it could not “escape the obligations ’ ’ of the contract unless there had been an agreement to abandon and rescind by all the parties. One of the close points in the case was that Earp was not present at the conversation where the lumber company claimed appellant to have asked that the contract be dropped; but if the lumber company was a surety merely, Earp’s absence would have made no difference. Appellant would have had no right to lead a mere surety to suppose the [428]*428contract was ended, and afterwards go on with the principal, without notice to the surety and his assent to his continuing bound.

3. The eighth charge given was:

‘ ‘ The court instructs you that the question of rescission, of whether that is a fact or not, must be proven by a preponderance of the evidence, and that the manner or the language of such rescission is immaterial; it is for you to determine, from all the facts in this case, whether that contract was rescinded or not. You have no right to pick out any particular part of the testimony and say that that does or does not prove a rescission. You should take the whole of the testimony and consider it; consider what the parties said; what the evidence shows that they said; you are to determine what they said, and what was said between them, and from that determine whether the contract was rescinded qr not. If it was rescinded, that was the end of it as far as the Seattle Lumber and Commercial Company is concerned.”

We think the court should have ended this charge with the words: “You should take the whole of the testimony and consider it.” That part of it which directed, the attention of the jury to what the parties said, and told them that from that they were to determine whether the contract was rescinded or not, was inaccurate and misleading, and could scarcely help producing the impression that what the court meant in the earlier portion of the charge by the “whole of the testimony,” or “facts,” was merely the conversations.

The last clause was not a correct statement. The contract might have been an explicit oral agreement to rescind, and yet the rescission might never have been acted upon, and the conduct of the parties may have shown a clear intention to disregard the oral agreement.

4. Another charge was:

“The court further instructs you, gentlemen, that if you find that, by agreement between the plaintiff and the Se[429]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jensen v. Sheard
96 P. 2 (Washington Supreme Court, 1908)
State v. Douette
71 P. 556 (Washington Supreme Court, 1903)
Sanford v. Royal Insurance
40 P. 609 (Washington Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
35 P. 133, 7 Wash. 424, 1893 Wash. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gottstein-v-seattle-lumber-commercial-co-wash-1893.