Gotion, Inc. v. Green Charter Twp.

CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 25, 2026
Docket24-1783
StatusUnpublished

This text of Gotion, Inc. v. Green Charter Twp. (Gotion, Inc. v. Green Charter Twp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gotion, Inc. v. Green Charter Twp., (6th Cir. 2026).

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 26a0096n.06

No. 24-1783

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT FILED Feb 25, 2026 ) KELLY L. STEPHENS, Clerk GOTION, INC., ) Plaintiff-Appellee, ) ) ON APPEAL FROM THE v. ) UNITED STATES DISTRICT ) COURT FOR THE WESTERN GREEN CHARTER TOWNSHIP, ) DISTRICT OF MICHIGAN Defendant-Appellant. ) ) OPINION ) )

Before: BOGGS, LARSEN, and DAVIS, Circuit Judges.

PER CURIAM. Green Charter Township entered into a Development Agreement with

Gotion, Inc., in which it committed to assist Gotion in constructing a battery component

manufacturing plant within township boundaries. Voters in the Township responded to the plans

by recalling the Township Board. The newly elected Board immediately began to undermine the

Development Agreement by rescinding resolutions supporting the project. Gotion sued for breach

of contract and sought injunctive relief. The district court granted Gotion a preliminary injunction,

and Green Charter Township appealed. After the filing of the appeal, however, the State of

Michigan informed Gotion that it was in default on obligations necessary to obtain funding central

to the project’s viability. Given the default, Gotion admits that the battery plant is no longer viable.

Accordingly, Gotion’s claim for injunctive relief is now moot, so we DISMISS the appeal and

REMAND to the district court for further proceedings. No. 24-1783, Gotion, Inc. v. Green Charter Township

I.

In 2022, Congress passed the Inflation Reduction Act. The Act’s tax incentives prompted

over $110 billion of capital investment in clean energy manufacturing. The Michigan Legislature

then passed a series of laws ambitiously aimed at achieving 100% carbon neutrality by 2050.

Gotion, Inc.—the American subsidiary of one of the largest electric vehicle battery manufacturers

in the world—capitalized on these measures, working with state and local governments to plan a

battery component manufacturing plant (the “Project”) within Green Charter Township in Mecosta

County, Michigan.

In September 2022, Gotion secured several grants from Michigan “to facilitate land

acquisition, public infrastructure improvements, engineering, permitting, wetland mitigation, and

other associated costs in support of the Project.” Gotion, Inc. v. Green Charter Township, No.

1:24-CV-275, 2024 WL 3179212, at *1 (W.D. Mich. May 17, 2024). Soon thereafter, the

Township’s seven-member Board unanimously adopted Resolution No. 01-122022 (“Support

Resolution”). Id. at 2. The Support Resolution “strongly support[ed] efforts to bring Gotion” to

the Township and pledged to “make every effort to work in the interests of our constituents and

community by assisting Gotion, Inc. in their efforts to join our community.” R. 1-2, Support Res.,

PageID 38. To attract Gotion to the area, the Township, Mecosta County, and the City of Big

Rapids offered a tax incentive package totaling $540 million. Gotion, 2024 WL 3179212, at *1.

The Support Resolution and tax incentives proved successful. In July 2023, Gotion selected a site

within the Township from among 56 competing locations. Gotion chose this site to reap the

combined $715 million in tax incentives and public grants offered by the state and local

governments. Gotion intended to invest over $2.36 billion into the Project and employ about 2,350

individuals, paying them, on average, 150% of Mecosta County’s average hourly rate.

-2- No. 24-1783, Gotion, Inc. v. Green Charter Township

To secure grants from the State, Gotion had to enter into agreements ensuring that it would

complete all the Project’s public infrastructure improvements and site development plans within a

certain time frame. Failure to make timely progress on the Project would constitute an “[e]vent of

[d]efault” on the agreements, which would permit Michigan to suspend or terminate the grants,

require repayment, or place a freeze on project funds. R. 1-3, Grant Agmt., PageID 51, 56.

To secure support from the Township, Gotion negotiated the Development Agreement,

which the Township Board adopted during a Board meeting in August 2023. The Development

Agreement requires the Township to, among other things, help Gotion obtain permits for the

Project. It states that the Township shall:

assist Gotion, to the extent legally permissible, in obtaining or causing to obtain any licenses, permits, or other governmental authorizations necessary to advance the Project and conduct business to support the Project, for which the failure to obtain such licenses, permits, or other governmental authorizations is reasonably likely to materially and adversely affect the Project (financially or otherwise), or impair Gotion’s ability to perform its obligations under this Agreement.

R. 1-1, Dev. Agmt., PageID 26. The Agreement further provides that any “material failure” to

comply with the Agreement by either party constitutes an “[e]vent of [d]efault,” which permits

“the non-breaching Party” to, “after expiration of any applicable Cure Period without a

cure, . . . exercise an[y] other available remedy at law or equity.” Id. at 28. The same month that

the parties entered into the Development Agreement, Gotion bought nearly 270 acres in the

Township for the Project site at a cost of $24,000,000. Gotion, 2024 WL 3179212, at *4.

But many members of the community were unhappy. In late 2022 or early 2023,

community members began to organize a campaign to recall the Township’s Board because of its

support for the Project. Two Board members resigned and were replaced in the summer of 2023,

before the recall election. The remaining members were ousted by a recall election in November

2023. All five replacement Board members campaigned on blocking the Project. Upon taking

-3- No. 24-1783, Gotion, Inc. v. Green Charter Township

office in November 2023, the new Board immediately commenced its efforts to halt the Project.

After the new Board rescinded two resolutions that were necessary to move the Project forward,

Gotion notified the Township that it had breached the Development Agreement and asked it to

cure the breach by reinstating the two rescinded resolutions. The Township refused and denied

that it had breached the Development Agreement.

After receiving the Township’s refusal letter, Gotion publicly announced its intent to

submit the Project site plan to the Mecosta County Planning Commission for approval; and it

submitted the application soon after. Green Charter responded by holding a special Board meeting

at which it stripped Mecosta County of its zoning authority over the Township. The Township

then sent Mecosta County a letter threatening to sue if it processed Gotion’s outstanding site-plan

application; the County then cancelled its scheduled review of the application.

Gotion responded in mid-March 2024 by suing the Township for breach of the

Development Agreement and seeking declaratory and injunctive relief. In May 2024, the district

court granted Gotion’s request for a preliminary injunction. Gotion, 2024 WL 3179212, at *12.

The court held that Gotion would likely succeed on the merits of its breach-of-contract claim. Id.

at *8–10. And the court determined that the “current record more than amply supports a showing

of irreparable harm to Gotion absent injunctive relief.” Id. at *11. It reasoned that Gotion would

suffer “significant monetary and contractual harms” if the Project, “an extensive undertaking with

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DeFunis v. Odegaard
416 U.S. 312 (Supreme Court, 1974)
Weiss v. Secretary of the U.S. Department of the Interior
459 F. App'x 497 (Sixth Circuit, 2012)
Speech First, Inc. v. Mark Schlissel
939 F.3d 756 (Sixth Circuit, 2019)
TransUnion LLC v. Ramirez
594 U.S. 413 (Supreme Court, 2021)
Resurrection Sch. v. Elizabeth Hertel
35 F.4th 524 (Sixth Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
Gotion, Inc. v. Green Charter Twp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gotion-inc-v-green-charter-twp-ca6-2026.