Gosselin v. City of Nashua

321 A.2d 593, 114 N.H. 447, 1974 N.H. LEXIS 298
CourtSupreme Court of New Hampshire
DecidedJune 28, 1974
Docket6887
StatusPublished
Cited by12 cases

This text of 321 A.2d 593 (Gosselin v. City of Nashua) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gosselin v. City of Nashua, 321 A.2d 593, 114 N.H. 447, 1974 N.H. LEXIS 298 (N.H. 1974).

Opinion

Griffith, J.

These cases arise from two actions brought by plaintiffs, Bentley Properties, Incorporated and cer *448 tain landowners from whom Bentley purchased land options, against the city of Nashua, its city clerk, and its planning board after the latter had rejected a site plan for a proposed shopping center, at that time a permitted use, on Amherst Street in Nashua. The two actions were tried together. While the trial court found against plaintiffs on their petition for certiorari on the merits of the planning board’s decision, it found in their f&vor on their petition for a writ of mandamus. Initially the trial court ordered approval of plaintiffs’ plan as amended, but after a rehearing it modified the decree issuing a writ of mandamus ordering approval of plan 7. Plaintiffs took no appeal from the trial court’s findings in the petition for certiorari, conceding during oral argument that determination of the petition for mandamus by this court would render the other case moot.

Subsequent to the hearing on the merits in the superior court, but before the court’s decision, the city of Nashua amended its zoning ordinance, effective January 1, 1974, and the property in question was rezoned. Under the new ordinance, a shopping center is no longer a permitted use on the greater portion of the proposed site. The parties have agreed that the issue of whether the zoning amendment bars construction of the shopping center despite the court’s decree mandating approval of plaintiffs’ site plan, may be decided by this court in the present case.

Defendants seasonably excepted to the findings and decree of the trial court, including specifically the rulings on both plaintiffs’ and defendants’ requests for findings of fact and rulings of law and the ruling of the court modifying the initial decree. All questions of law raised by defendants’ exceptions, the agreed statement of facts and the Nashua zoning amendment were reserved and transferred by the Trial Court, Johnson, J.

In early 1973, plaintiff Bentley acquired purchase options from the owners of the land in question. Bentley proceeded to prepare a preliminary site plan (plan 1) which was submitted for approval to the Nashua City Planning Board on May 31, 1973. While the planning board failed to place the plan on its agenda for its next scheduled meeting (see RSA 36:23 and Revised Ordinances of Nashua § 3842), it met with Ben *449 tley’s architects, explained why the plan was unacceptable and suggested revisions.

Plaintiffs revised their plan in accordance with the board’s suggestions, submitting a second plan (plan 2) for approval on July 1, 1973. Negotiations between plaintiffs and the planning board continued with the board requesting additional minor revisions on various submitted plans and with the plaintiffs attempting to make the revisions and providing additional information that the board requested. Between August 20 and October 4, plaintiffs submitted five (5) additional plans (plans 3-7) to the board for its approval. On October 4, 1973, plaintiffs submitted plan 7 which was voted on and rejected that same day by the planning board.

In November 1973, plaintiffs filed a petition for a writ of mandamus against Lionel Guilbert, clerk of the city of Nashua, and the Nashua City Planning Board, to compel them to issue a certificate of approval of their site plan pursuant to RSA 36:23 and Revised Ordinances of Nashua § 3842, due to the planning board’s failure to approve or disapprove the submitted plan within prescribed time limits. RSA 36:23 and Revised Ordinances of Nashua § 3842 are substantially the same except that the former provides for approval of a plan on demand if the planning board fails to approve or disapprove of the plan within ninety days while the latter imposes a thirty-day action requirement on the board. RSA 36:23 reads in pertinent part as follows: “The planning board shall place on its agenda for consideration any plat submitted to it within thirty days and shall act to approve or disapprove thereof within ninety days; provided, that the planning board may apply to the selectmen or city council for an extension not to exceed an additional ninety days before acting to approve or disapprove, otherwise such plat shall be deemed to have been approved, and the certificate of the municipality, as to the date of submission of the plat for approval and the failure to take action thereon within such time, shall be issued on demand and shall be sufficient in lieu of the written indorsement or other evidence of approval herein required; provided, however, that the applicant for the board’s approval may waive this requirement and consent to an extension of such period.”

*450 Defendants assert that the trial court erred in issuing the writ of mandamus, because plaintiffs waived their rights to the statutory time limit within which the board was required to act by submitting seven (7) separate plans for approval. The trial court found as a matter of law that plaintiffs did not waive their statutory rights to have the board act on their initial plan, and that all subsequent submissions to the board “constitute refinements of the concept embodied in the initial submission and do not constitute multiple submissions.” While defendants concede that if it is found plaintiffs did not waive the statutory time limit, they are entitled to a decree ordering approval of plan 1, they argue that each plan is a separate submission and mandamus cannot properly issue as to plan 7, because the board rejected that plan on the day it was submitted.

Plaintiffs argue that since they were entitled to a certificate of approval of their site plan by August 31, 1973, at the very latest, the amendment to title 14 of the Revised Ordinances of Nashua, effective January 1, 1974, should not be applied to prohibit construction of the proposed shopping center. They assert that since they have expended in excess of $100,000 in good faith reliance on the absence of any regulation prohibiting the proposed use, they have acquired a vested right to complete the shopping center despite the subsequent adoption of an ordinance prohibiting the same.

An existing classification of property confers no vested right on an owner in itself “as all property is held in subordination to the police power of the municipality.” R.A. Vachon & Son, Inc. v. Concord, 112 N.H. 107, 110, 289 A.2d 646, 648 (1972); Brady v. Keene, 90 N.H. 99, 4 A.2d 658 (1939); Village House, Inc. v. Loudon, 114 N.H. 76, 314 A.2d 635 (1974). The present case raises the question whether vested rights may accrue when a subdivision approval is applied for and not granted which is similar to the more common situation where a building permit has already issued and then is subsequently revoked. Winn v. Corporation, 100 N.H. 280, 124 A.2d 211 (1956). In both situations “the governing principles are substantially similar” (R.A. Vachon & Son, Inc. v. Concord, 112 N.H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PMC Realty Trust v. Town of Derry
480 A.2d 51 (Supreme Court of New Hampshire, 1984)
Board of County Commissioners v. CMC of Nevada, Inc.
670 P.2d 102 (Nevada Supreme Court, 1983)
Henry and Murphy, Inc. v. Town of Allenstown
424 A.2d 1132 (Supreme Court of New Hampshire, 1980)
Town of Freedom v. Gillespie
419 A.2d 1090 (Supreme Court of New Hampshire, 1980)
Beck v. Town of Raymond
394 A.2d 847 (Supreme Court of New Hampshire, 1978)
Town of Nottingham v. Lee Homes, Inc.
388 A.2d 940 (Supreme Court of New Hampshire, 1978)
Brennan v. Saco Construction, Inc.
381 A.2d 656 (Supreme Judicial Court of Maine, 1978)
Thomas v. Zoning Board of Appeals of the City of Bangor
381 A.2d 643 (Supreme Judicial Court of Maine, 1978)
Town of Paradise Valley v. Gulf Leisure Corp.
557 P.2d 532 (Court of Appeals of Arizona, 1976)
Golden Gate Corp. v. Town of Narragansett
359 A.2d 321 (Supreme Court of Rhode Island, 1976)
Allard v. Thalheimer
358 A.2d 395 (Supreme Court of New Hampshire, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
321 A.2d 593, 114 N.H. 447, 1974 N.H. LEXIS 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gosselin-v-city-of-nashua-nh-1974.