Gorham Co. v. United Engineering & Contracting Co.

95 N.E. 805, 202 N.Y. 342, 1911 N.Y. LEXIS 1023
CourtNew York Court of Appeals
DecidedJune 13, 1911
StatusPublished
Cited by7 cases

This text of 95 N.E. 805 (Gorham Co. v. United Engineering & Contracting Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gorham Co. v. United Engineering & Contracting Co., 95 N.E. 805, 202 N.Y. 342, 1911 N.Y. LEXIS 1023 (N.Y. 1911).

Opinions

Hiscock, J.

At the times herein involved the respondent was the lessee of a building situate at the southwest corner of Fifth avenue and Thirty-third street, in the city of New York, which had first been used for hotel purposes and later had been re-built for business uses. The appellant was a contractor which had undertaken the construction of the Manhattan crosstown tunnel of the Pennsylvania, New York & Long Island Railroad Company, the route of which lay through Thirty-third street. Originally it seems to have been expected that this tunnel as it ran by respondent’s premises would be constructed by excavation from the surface of the street, and it was anticipated that the operation might impair the condition and safety of respondent’s building. Accordingly, in January, 1907, a contract was made between the parties to this action whereby the appellant, among other things, agreed to build a foundation wall and curtain wall under the north wall of respondent’s building on Thirty-third street. No time was fixed for the commencement or *345 completion of the work and, therefore, it was ruled on the trial without objection that reasonable dispatch was required. The appellant so failed to perform or commence its work under said contract that in July, 1907, this action was brought for its alleged default, and in January, 1908, a new contract was made by respondent with another contractor for the performance of the work.

Respondent sought by the action amongst other things to recover for damage to its building because of appellant’s failure to fulfill its contract seasonably and also the reasonable cost of doing the work which the latter had contracted to do. On the trial three issues amongst others were sharply contested and submitted to the jury.' These were: First, whether certain injuries to respondent’s building resulted from appellant’s failure with reasonable diligence to perform its contract or were the result of other causes; second, whether all of the work done by respondent on account of appellant’s alleged default was necessary and, therefore, chargeable in any event to the latter; third, the reasonable cost and value of the work which respondent did in making up for appellant’s default.

Three lines of evidence were introduced by respondent and received to sustain its contention on one or more of these issues, all of which were objected to and are now seriously criticized by the appellant.

The respondent on the appellant’s alleged default did not make a general advertisement for bids to do the work which the latter had agreed to do, but requested two contractors to submit bids. One of these was a man named Brown, who subsequently did the work. One of respondent’s officers was allowed to testify in substance that after Brown had made his bid he was invited to respondent’s office and there the officer in question attempted to persuade him to reduce the amount of his bid; that Brown declined to do this except by a small sum on the ground that he could not afford to do the work for less, and that thereupon the bid was accepted. Appellant insists that *346 this was an objectionable method of showing that the work was worth the sum charged by the contractor, and for which recovery was subsequently had in this action. Personally, I do not think that this evidence' was of sufficient importance to call for a reversal even though it be assumed that it was objectionable. In the course of the trial Brown and others gave evidence tending to show that the work was worth the amount charged in the bid and for which the respondent had recovery, and in view of this evidence it is difficult to see how the conversation in question could have produced any serious result.

The other persons who submitted a bid were a firm named Fountain & Choate. Their bid was offered in response to a letter written by respondent’s attorneys and they proposed to do the work for $55,350, which was nearly $10,000 in excess of the Brown bid. This bid was received in evidence “ only for the purpose of going to the question of what was a reasonable price for the work that thereafter was alleged to have been done,” and it is insisted that it was improper for that purpose. I agree with this contention. The accuracy of the bid and the reasonableness of the amount for which these bidders proposed to do the work involved in this litigation was not verified by any other evidence on the trial, and the ruling, therefore, amounted to this, that an unverified bid was received as some proof of what it was reasonably worth to do the work with which the appellant was being charged. Not only was the accuracy of the bid not directly verified by the examination of any witnesses on the trial but there was an entire absence of evidence showing circumstances which might create an inference that it was a reliable test and measure of values. It was not the result of open and competitive bidding on very precise specifications but was given in response to a private invitation which was somewhat general in its description of the work to be done. Aside from the fact that the bidders’ letter head describes them as “Builders,” I do not find any evidence which *347 showed that- they were engaged in this kind of work. Certainly there is no evidence showing that they were customarily engaged in doing it or were advantageously equipped for completing at a reasonable price such a contract as this. There may have been many reasons which made them unwilling or unable to accept the work at a price which would be regarded as reasonable by those desiring and prepared to do such work. The very fact that on a contract of this size their bid was nearly 25 per cent higher than that of Brown, who conceded that he made a handsome profit, would seem to indicate that their judgment was not very reliable. In short there is nothing to bring this evidence within those rules which in exceptional cases do allow the price bid or paid for an article to stand as some evidence of its value, or to free it from those objections which ordinarily apply to hearsay testimony.

Respondent was allowed to introduce evidence of a certain proceeding instituted by the superintendent of buildings of the city of Hew York addressed to respondent as owner of the building and to one Astor as owner of the ground, requiring certain things to be done to make the building safe and to which appellant was in no manner a party. This proceeding was begun by a notice served after commencement of this action stating that the building was unsafe and that a survey would be made for the purpose of ascertaining this fact. This survey was made by an inspector and two architects, one of whom was selected by the respondent, and reported in substance amongst other things that the premises had been made “ unsafe and dangerous in the following respects, to wit: In that by reason of the excavation of the tunnel in 33rd St.” the walls were unsafe and that the premises “should be immediately made safe- by * * * underpinning the said westerly portion of the northerly wall and portions of the adjacent cross walls to solid bottom.” On subsequent application on notice to the Supreme Court for the issue of a precept, findings were made of the *348

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Van Iperen v. Hays
269 N.W. 448 (Supreme Court of Iowa, 1935)
State Ex Rel. Havner v. Associated Packing Co.
249 N.W. 761 (Supreme Court of Iowa, 1933)
Castles v. Rovenger
211 A.D. 356 (Appellate Division of the Supreme Court of New York, 1925)
Lazarowitz v. Kazan
122 Misc. 202 (City of New York Municipal Court, 1924)
Udell Savings Bank v. Hollingsworth
194 Iowa 440 (Supreme Court of Iowa, 1922)
Havholm v. Whale Creek Iron Works
162 A.D. 354 (Appellate Division of the Supreme Court of New York, 1914)
Bilkovic v. Loeb
156 A.D. 719 (Appellate Division of the Supreme Court of New York, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
95 N.E. 805, 202 N.Y. 342, 1911 N.Y. LEXIS 1023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gorham-co-v-united-engineering-contracting-co-ny-1911.