Gordon v. Tejunga Water & Power Co.

189 P. 288, 46 Cal. App. 347, 1920 Cal. App. LEXIS 797
CourtCalifornia Court of Appeal
DecidedFebruary 26, 1920
DocketCiv. No. 2069.
StatusPublished
Cited by1 cases

This text of 189 P. 288 (Gordon v. Tejunga Water & Power Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gordon v. Tejunga Water & Power Co., 189 P. 288, 46 Cal. App. 347, 1920 Cal. App. LEXIS 797 (Cal. Ct. App. 1920).

Opinion

ELLISON, P. J., pro tem

The complaint is in four counts. In the first count, after stating the corporate capacity of the defendant, it is alleged: “That the defendant employed the plaintiff to superintend and take charge of the management of the irrigation plant of the defendant at a salary of five dollars per day, and the plaintiff began under said employment on February 23, 1914, and continued to work for the defendant up to and including May 1, 1915.

“That for said labor so performed by the plaintiff for the defendant, the defendant has failed and neglected to pay any part thereof though requested often so to do.

“That there is now due, owing, and unpaid from the defendant to the plaintiff for the labor performed as aforesaid by the plaintiff for the defendant the sum of $1,980 less $70 credit thereon for fourteen days, absence from said work. ’ ’

In the second count it is alleged: “That for a period of ninety days between the dates of February 23, 1914, and May 1, 1915, the plaintiff furnished a team and wagon for hauling pipe materials and other supplies used in the care *349 and management of the defendant’s water system, and that the reasonable value of the services of said team is two dollars per day.

“That no part of said sum has been paid though the plaintiff has-repeatedly requested the defendant to pay the same, and that the sum of $180 is now due, owing, and unpaid from the defendant to the plaintiff for said services.”

In the third count it is alleged: “That between July 9, 1914, and May 1, 1915, the plaintiff furnished the defendant tires, oils, and grease for machines, amounting to $226.30, which said sum was the reasonable price for the tires, oils, and grease so furnished and that the same was furnished at the special instance and request of the defendant.

“That no part of said sum has been paid though the plaintiff has repeatedly requested the defendant to pay the same, and that the sum of $226.30 is now due, owing, and unpaid from the defendant to the plaintiff for said materials aforesaid.”

And, in the fourth count it is alleged: “That between February 23, 1914, and May 1, 1915, the plaintiff furnished other materials and supplies for the repair and improvement of the conduits of the water system, taps, and meters, to the extent of $187.48 at the special instance and request of the defendant, no part of which has been paid though the defendant has been often requested so to do.”

There was a general demurrer filed to the complaint, which was overruled, and the defendant answered, denying all the allegations of the complaint, except the incorporation of the defendant. And by amendment to the answer it was alleged that each, all and every of the claims sued upon in said action and set forth in plaintiff’s complaint, were fully paid, satisfied, and discharged by the defendant. It is also alleged in the said amendment that at the time of the commencement of the alleged services set forth in the plaintiff’s complaint the plaintiff was, and had been, indebted to the defendant in excess of the total amount sued for in the complaint for money loaned, water sold and delivered by the defendant to the plaintiff, money had and received by plaintiff belonging to defendant, goods, wares and merchandise sold and delivered by defendant to plaintiff, and notes and mortgage held by defendant against plaintiff. And that, at the time of the commencement of said services, it was understood and agreed *350 that, with the exception of small amounts to be paid in cash from time to time, the earnings of the plaintiff under said employment were to be applied by the defendant in payment and liquidation of the said indebtedness of plaintiff to defendant. It was then alleged that the defendant did, from time to time, credit said plaintiff on said. indebtedness with various sums of money as earned by, or that for any reason became due, the -plaintiff for services or any other reason, and that by reason of such application of payments and credits any and all claims of the plaintiff against the defendant had prior to the commencement of the action been liquidated, paid, satisfied and discharged.

As to the first cause of action stated in the complaint, the court found, as alleged in the complaint, that the defendant employed plaintiff to superintend and take charge of the management of its irrigation plant at a salary of five dollars per-day; that he began work February 23, 1914, and continued to May 1, 1915; that the defendant had failed and neglected to pay any part thereof; and that there is due and unpaid for said labor the sum of $1,910.

On the second cause of action the court found, as alleged in the complaint, that the plaintiff furnished a team and wagon that was used in the service of the defendant, and that the reasonable value thereof was two dollars per day, and that there was due and unpaid to the plaintiff for the use of said team the sum of $180.

The court failed to make any finding upon the third cause of action alleged in the plaintiff’s complaint.

Upon the fourth cause of action the court found that the plaintiff furnished supplies and materials for the repair and improvement of the conduits of the water system, taps, and meters to the extent of $187.48, and that no part of it had been paid, and that it was all now due and unpaid.

And the court ordered judgment entered in favor of the plaintiff for $2,277.48. From this judgment the defendant appeals.

The points raised upon the appeal are mainly technical and attack the sufficiency of the complaint to* state a cause of action and assign as error that the court failed to find upon some material allegations of the complaint and also of the answer.

*351 [1] The defendant claims that the first cause of action does not state a cause of action because there was no allegation of promise or agreement on the part of the defendant to pay the plaintiff five dollars per day for his work, and no allegation that such was the reasonable value thereof; that it does not allege when the salary was to become due and payable, nor that the same was done within the time agreed upon.

We think there is no merit in any of these contentions. The action is not upon a quantum meruit, but the complaint alleges the defendant employed the plaintiff to do certain work for it at a salary of five dollars per day, and that he began work under said employment on February 23, 1914, and continued to work up to the first day of May, 1915. This is a sufficient allegation of employment at an agreed compensation of five dollars per day.

[2] It is next claimed that there is no allegation that the. amount due for the work under said employment has not been paid, and in support of this position counsel cites the case of Potter v. Lowry, 25 Cal. App. 617, [144 Pac. 981].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larkin v. Barker
1928 OK 636 (Supreme Court of Oklahoma, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
189 P. 288, 46 Cal. App. 347, 1920 Cal. App. LEXIS 797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gordon-v-tejunga-water-power-co-calctapp-1920.