Gordon v. CRS Consulting Engineers, Inc.

820 P.2d 492, 173 Utah Adv. Rep. 12, 1991 Utah App. LEXIS 162, 1991 WL 223055
CourtCourt of Appeals of Utah
DecidedNovember 1, 1991
Docket900336-CA
StatusPublished
Cited by1 cases

This text of 820 P.2d 492 (Gordon v. CRS Consulting Engineers, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gordon v. CRS Consulting Engineers, Inc., 820 P.2d 492, 173 Utah Adv. Rep. 12, 1991 Utah App. LEXIS 162, 1991 WL 223055 (Utah Ct. App. 1991).

Opinion

OPINION

GREENWOOD, Judge:

CRS Consulting Engineers, Inc. (“CRS”) appeals from an order dismissing its cross-claim for indemnification against Skyline Construction Co. (“Skyline”). We affirm.

BACKGROUND

This case arises from a personal injury suit. Plaintiff David K. Gordon was injured when he stepped into a sinkhole at the Utah State Training School, where he was employed. The sinkhole resulted from the construction of a storm drain system at the school. CRS did the engineering and design work for the system and Skyline was the contractor. Both CRS and Skyline performed pursuant to separate contracts with the State of Utah. Gordon alleged that CRS and Skyline had been negligent, respectively, in the design and construction of the storm drain system.

Before trial, CRS settled with Gordon for $100,000. The jury, in special verdicts, found that Skyline was negligent and that its negligence was the proximate cause of Gordon’s injuries. The jury also found that CRS was negligent but that its negligence was not a proximate cause of Gordon's injuries. The trial resulted in a judgment of one million dollars for Gordon against Skyline. Offsetting this by the CRS settlement, Skyline paid $900,000 to Gordon.

CRS and Skyline had crossclaimed against each other, each contending that it was contractually indemnified by the other. These crossclaims were dismissed. CRS appeals, contending that the trial court erred in holding that CRS was not indemnified by Skyline for its settlement with Gordon.

ISSUE

CRS argues that the contract between Skyline and the State provides indemnification for CRS as an employee and/or agent of the State.

ANALYSIS

Interpretation of a contract usually presents a question of law. Village Inn Apartments v. State Farm Fire and Casualty Co., 790 P.2d 581, 582 (Utah App.1990). The question of whether a contract is ambiguous is also one of law, which we review for correctness. Jarman v. Reagan Outdoor Advertising, 794 P.2d 492, 494 (Utah App.1990). Extrinsic evidence may be considered only if the agreement is ambiguous or appears to incompletely reflect the parties’ agreement. Ron Case Roofing & Asphalt v. Blomquist, 773 P.2d 1382, 1385 (Utah 1989). If the contract is not ambiguous, and therefore no extraneous evidence is considered, we review for *494 correctness. Terry v. Price Mun. Corp., 784 P.2d 146, 149 (Utah 1989).

In interpreting a contract, we look at the contract as a whole to determine the parties’ intent. Ron Case Roofing, 773 P.2d at 1385. We will accord commonly accepted meanings to the words and phrases of a contract whenever possible. Bear River Mut. Ins. Co. v. Wright, 770 P.2d 1019, 1020 (Utah App.1989).

“Utah courts apply the rule of strict construction when confronted with an indemnity agreement.” Pickover v. Smith’s Management Corp., 771 P.2d 664, 666 (Utah App.1989). Under this rule, there is a presumption against an intent to indemnify unless “ ‘that intention is clearly and unequivocally expressed.’ ” Id. at 667 (quoting Union Pac. R.R. v. El Paso Nat’l Gas Co., 17 Utah 2d 255, 408 P.2d 910, 913 (1965)). When construing indemnification clauses, no intention to confer third-party beneficiary rights will be inferred from the indemnity language alone. Ron Case Roofing, 773 P.2d at 1387.

The contractual provisions in question are found in three documents. First, Article XVII of the contract between CRS and the State (“Engineers Contract”) is entitled “Independent Contractor.” It states, in part, that CRS is “to be considered an independent contractor, and, as such, shall have no authority to bind the State of Utah ... nor to perform any acts as agent for the State of Utah except as herein expressly set forth.” In addition to providing plans and specifications for the project, the Engineers Contract also requires CRS to perform certain monitoring and oversight duties during the construction phase of the project. These include, for example, interpreting contract documents, assuring progress in accordance with contract documents, and preparing and recommending change orders.

Second, the contract between Skyline and the State (“Construction Contract”), incorporates by reference certain General Conditions and Specifications governing the project (“Specifications”). Paragraph 28 of the Specifications states, in part, as follows:

Indemnification. “Indemnities” shall be defined for the purpose of this section: The State of Utah and all institutions, agencies, departments, authorities, and instrumentalities of the State of Utah, and any member of their governing bodies, or their boards or commissions, or any of their elected or appointed officers, or any of their employees or authorized volunteers.
The contractor will protect, indemnify and hold harmless indemnities from every kind and character of damages, losses, expenses, demands, claims and causes of action arising against indemnities and their subcontractors, their officers, agents, employees or other person, firm or corporation whatsoever from, against, or on account of any and all claims, damages, losses, demands causes of action and expenses (including attorneys fees) arising out of or resulting from any violation or alleged violation by contractor, his officers, agents and employees, or his subcontractors or their officers, agents and employees of any federal, state or local law, statute or ordinance, relating to the work to be performed by the contractor on the project growing out of or incident to the work to be performed and operations to be conducted by the contractor, or his subcontractors under this agreement, whether such claims, death or damages, result from or are claimed to have resulted from the negligence of contractor, his officers, agents or employees, or his subcontractors ... or whether resulting from or alleged to have resulted from the concurrent negligence of indemnities and/or contractors, their officers, agents or employees.

(Emphasis added).

Third, the Construction Contract provides as follows in Article 11:

The Contractor agrees that it/he shall at all times protect and indemnify and save harmless, the State of Utah and all institutions, agencies, departments, authorities and instrumentalities of the State of Utah and any member of their governing bodies or of their boards or commissions or any of their employees

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adams v. General Accident
Tenth Circuit, 1997

Cite This Page — Counsel Stack

Bluebook (online)
820 P.2d 492, 173 Utah Adv. Rep. 12, 1991 Utah App. LEXIS 162, 1991 WL 223055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gordon-v-crs-consulting-engineers-inc-utahctapp-1991.