Gootee Const., Inc. v. Amwest Sur. Ins. Co.

781 So. 2d 792, 0 La.App. 5 Cir. 1639, 2001 La. App. LEXIS 366, 2001 WL 253905
CourtLouisiana Court of Appeal
DecidedFebruary 28, 2001
Docket00-CA-1639
StatusPublished
Cited by3 cases

This text of 781 So. 2d 792 (Gootee Const., Inc. v. Amwest Sur. Ins. Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gootee Const., Inc. v. Amwest Sur. Ins. Co., 781 So. 2d 792, 0 La.App. 5 Cir. 1639, 2001 La. App. LEXIS 366, 2001 WL 253905 (La. Ct. App. 2001).

Opinion

781 So.2d 792 (2001)

GOOTEE CONSTRUCTION, INC.
v.
AMWEST SURETY INSURANCE COMPANY and Premier Glass Plus, Inc.

No. 00-CA-1639.

Court of Appeal of Louisiana, Fifth Circuit.

February 28, 2001.
Writ Denied May 11, 2001.

*793 Lloyd N. Shields, Daniel Lund, III, Mark S. Senter, William J. Perry, Shields Mott Lund L.L.P., New Orleans, for Appellant Premier Glass Plus, Inc.

David J. Krebs, Maura Z. Pelleteri, Preaus, Roddy & Krebs, L.L.P., New Orleans, for Appellant Amwest Surety Insurance Company.

Thomas F. Gardner, Douglas A. Kewley, Mary Ann Darr Wegmann, Metairie, for Appellee Gootee Construction, Inc.

Panel composed of Judges EDWARD A. DUFRESNE, Jr., JAMES L. CANNELLA and PATRICK SCHOTT, Pro Tempore.

CANNELLA, Judge.

Defendants, Premier Glass Plus, Inc. (Premier) and its insurer, Amwest Surety Insurance Company (Amwest), appeal from the summary judgment granted in favor of Plaintiff, Gootee Construction, Inc. (Gootee). For the reasons which follow, we reverse and remand.

The New Orleans Aviation Board (NOAB), as owner, contracted with Gootee, as general contractor, for renovations to Concourse D at the New Orleans International Airport (the Project). One of the requirements of the Project was the installation of an exterior, insulated panel wall system (Panel System). On April 5, 1995, Gootee entered into a subcontract (the Subcontract) with Premier to provide the Panel System for the Project. The Subcontract sum to be paid to Premier upon completion was $639,000. The rights and responsibilities of the parties were set out in the Subcontract, with reference to certain specifications for the Panel System. Alply Inc. (Alply) was set out as an acceptable manufacturer of the panels within the designated specifications and the panels were to be installed according to the manufacturer's installation instructions. Premier secured the obligations of the Subcontract with a performance bond issued by Amwest. Premier in turn contracted with another company, Premier Glass, Inc. (Premier, Inc.), to do the actual installation work.

Sometime thereafter, Gootee became dissatisfied with Premier's work and, on May 12, 1997, sent a letter to Alply, with a copy to Premier, notifying them that the installation of their materials by Premier had been rejected by the Airport Management Consultants because several panels had been field cut, exposing the insulation, and had not been properly installed.

Gootee hired another subcontractor, De-George Glass Company, Inc.(DeGeorge), to rework the exterior wall system for the Project. After DeGeorge completed its work on the Project, Gootee made demand on Premier and Amwest for payment of $479,955, the amount allegedly charged by DeGeorge for the rework. Premier and Amwest refused to provide payment to Gootee for DeGeorge's work on the Project. On January 20, 1998, Gootee filed the instant suit seeking reimbursement for *794 the funds which it expended to correct the defective work performed by Premier.

In response to the suit, Premier filed an answer and a third-party demand against Alply. Premier filed a supplemental and amending third-party demand against Premier, Inc., the actual installer of the panels, and Lloyds of London, its insurer.

On February 9, 2000, Gootee filed a Motion for Summary Judgment, contending that Premier breached its contract with Gootee by not installing the panels in accordance with the manufacturer's specifications, as required by their contract. Gootee attached the contracts, its May 12, 1997 notice of defect letter addressed to Alply with copies to Premier and Amwest, the July 31, 1997 formal rejection notice by the NOAB because of improper installation, and the deposition of C. Reece Owen (Owen), the President and executive officer designated by Premier, acknowledging that the installation of certain panels was not in accordance with the manufacturer's specifications.

Premier opposed the summary judgment with affidavits by Owen and Dan Kinney (Kinney), President of Premier, Inc. Owen's affidavit stated that Premier had subcontracted with Premier, Inc. for installation of the panels and that Premier, Inc. was an authorized installer for Alply, the manufacturer of the wall system that met the specifications in the subcontract. Kinney's affidavit stated that Premier, Inc. was an authorized installer for Alply, that Premier completed two phases of the required work, that the work was inspected periodically by Alply and that the warranty was issued by Alply. He stated that the warranty would not have been issued by Alply if the work had not met with the manufacturer's recommendations. Thus, Premier argued that there were material issues of fact that precluded summary judgment.

The motion for summary judgment was considered by the trial court on April 11, 2000 and judgment was rendered on April 17, 2000, granting the summary judgment in favor of Gootee, awarding damages in the amount of $479,955, prejudgment interest from May, 17, 1977 of $107,733.84, and attorney's fees of $114,138.38. The judgment was specified as final between Gootee, Premier and Amwest, with only the third-party claims of Premier and Amwest against Alply, Premier, Inc ., and Lloyds of London remaining. It is from this judgment that Premier appeals.

On appeal Premier argues that the trial court erred in granting the summary judgment on two grounds: first, because Gootee did not prove it complied with the contractual putting in default requirements; and second, because Gootee did not prove Premier's alleged default or the relationship between the default and the amount of the damages.

Gootee counters that Premier cannot raise, for the first time on appeal, any issues concerning defects in the manner in which Gootee notified Premier that it was in default. Premier did not raise this defense in the trial court and, therefore, cannot raise it now.[1] Further, Gootee argues that Premier was put in default and the contractual default requirements were met by the May 12, 1997 letter to Alply which was copied to Premier. Also, Gootee points out that there are two separate *795 contractual provisions applicable to noncompliance with the contractual requirements, one addressing default and the other for breach, which does not require notice. Gootee also argues that it met its burden for summary judgment by the deposition testimony of Owen, who admitted that some of the work was not up to specifications.

La. C.C.P. art. 966 provides that a summary judgment shall be rendered forthwith if the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to material fact and that mover is entitled to judgment as a matter of law. Under the 1997 amendment to the article, summary judgment is favored, but the burden of proof remains with the mover. Chiasson v. New Orleans Pub. Group, Inc., 99-1338 (La.App. 5th Cir.4/25/00), 761 So.2d 89; Hussain v. Enterprise Leasing Co., Inc., 98-806 (La.App. 5th Cir.3/10/99), 735 So.2d 46, 47. Appellate courts review the granting of a summary judgment de novo under the same criteria governing the trial court's consideration of whether a summary judgment is appropriate. Guillory v. Interstate Gas Station, 94-1767 (La.3/30/95), 653 So.2d 1152; Felix v. Briggs of Oakwood, Inc., 99-721 (La.App. 5th Cir.12/15/99), 750 So.2d 1091.

After reviewing the record in this case, we conclude that the trial court erred in granting the summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manning v. Sampson
50 So. 3d 908 (Louisiana Court of Appeal, 2010)
Gootee Const., Inc. v. Amwest Sur. Ins. Co.
856 So. 2d 1203 (Supreme Court of Louisiana, 2003)
Prince v. K-Mart Corp.
815 So. 2d 245 (Louisiana Court of Appeal, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
781 So. 2d 792, 0 La.App. 5 Cir. 1639, 2001 La. App. LEXIS 366, 2001 WL 253905, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gootee-const-inc-v-amwest-sur-ins-co-lactapp-2001.