Goodwyn, Mills & Cawood, Inc. v. Markel Ins. Co.

911 So. 2d 1044, 2004 Ala. LEXIS 183, 2004 WL 1588101
CourtSupreme Court of Alabama
DecidedJuly 16, 2004
Docket1021820
StatusPublished
Cited by5 cases

This text of 911 So. 2d 1044 (Goodwyn, Mills & Cawood, Inc. v. Markel Ins. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodwyn, Mills & Cawood, Inc. v. Markel Ins. Co., 911 So. 2d 1044, 2004 Ala. LEXIS 183, 2004 WL 1588101 (Ala. 2004).

Opinion

Goodwyn, Mills Cawood, Inc. ("GM C"), an engineering firm, appeals from the trial court's order granting Markel Insurance Company's motion to enforce a settlement agreement and denying GM C's petition to reform the same agreement. We affirm in part, reverse in part, and remand.

I.
In October 1997, the Town of Vance solicited bids for a sewer-improvement project. The plans for the project were prepared by GM C. Bids were taken to determine the general contractor for the project, and Mountain Movers, LLC, was the low bidder. Vance awarded it the general contract. The contract required Mountain Movers to provide a payment bond and a performance bond for Vance. Markel Insurance Company issued those bonds. Under the terms of the bonds, Markel would be held responsible for the performance of the contract and for Mountain Movers' debts if Mountain Movers defaulted on its contract with Vance.

During construction of the project, a dispute arose between Mountain Movers and Vance. Mountain Movers claimed that it was entitled to additional compensation and to additional time to complete the project because of alleged deficiencies in the plans prepared by GM C and because of extra work on the project Vance was requiring. The parties were unable to resolve their differences, and, in July 1998, Mountain Movers abandoned the sewer-improvement project.1 Vance requested *Page 1046 that Markel perform its obligations under the payment and performance bonds it had issued, but Markel refused to do so.

In January 1999, Mountain Movers sued Markel, GM C, and Vance in the Tuscaloosa Circuit Court, asserting numerous claims including negligence, breach of contract, tortious interference with business and contractual relations, and fraud. Markel counterclaimed against Mountain Movers and cross-claimed against GM C and Vance. On November 8, 2000, after extensive discovery and settlement negotiations, Markel, Vance, and GM C entered into a settlement agreement; that agreement resolved all of the outstanding claims among the parties to the agreement. The only claims remaining were Mountain Movers' claims against Markel and Markel's counterclaims against Mountain Movers.2 The settlement agreement stated in relevant part that "[GM C] agrees to pay to Markel, as surety for Mountain Movers, LLC, the sum of [$275,000], said sum to be paid as settlement in full of all claims, actions, demands, and assertions of liability of any nature whatsoever by Mountain Movers . . . and Markel against [GM C]." Markel also agreed to pay Vance $250,000 in satisfaction of all claims under the performance bond issued by Markel. The agreement declared that all other claims between the parties to the settlement agreement were released and discharged. In a supplemental agreement, the parties agreed to defer their payment obligations under the settlement agreement until Mountain Movers' claims against Markel were resolved.

On October 3, 2001, before Mountain Movers' claims against Markel were resolved, and before any payments had been made pursuant to the settlement agreement, GM C's insurer, Reliance Insurance Company of Illinois, Inc., was determined to be insolvent and entered liquidation proceedings in Illinois. On November 6, 2001, although Mountain Movers' claims against Markel remained pending and the payments called for in the settlement agreement presumably were not yet due, Markel paid Vance the $250,000 it had agreed to pay under the settlement agreement.3 GM C refused to make the $275,000 payment to Markel called for under the settlement agreement, claiming that Reliance Insurance Company, not GM C, was obligated to fund that payment to Markel.

On February 12, 2002, Markel moved the trial court to enforce the settlement agreement against GM C. On February 26, 2002, the trial court entered a summary judgment for Markel on all of Mountain Movers' claims against it; on April 9, 2002, the trial court made its February 26, 2002, order final pursuant to Rule 54(b), Ala. R. Civ. P. On April 17, 2002, GM C petitioned the trial court to reform the settlement agreement to reflect the true intent of the parties, arguing that the parties' true intention had been for Reliance Insurance Company to fund the $275,000 payment to Markel and that the agreement did not accurately reflect that intent. On May 6, 2002, the trial court held an evidentiary hearing to consider Markel's motion and GM C's petition. On May *Page 1047 22, 2003, the trial court granted Markel's motion to enforce the settlement agreement and denied GM C's petition to reform the settlement agreement. The court also entered a judgment in favor of Markel and against GM C for $275,000 with interest calculated at 12% from November 6, 2001, the date Markel made the payment it was obligated to make to Vance under the settlement agreement. The trial court denied GM C's motion to alter, amend, or vacate its order. GM C appealed.

II.
The parties disagree as to the applicable standard of review. Markel argues that, because the trial court conducted an evidentiary hearing at which it heard oral testimony without a jury, the ore tenus rule should apply; therefore, the trial court's decision should not be overturned unless it is "manifestly unjust or plainly and palpably erroneous." Brewer v.Stanley, 534 So.2d 299, 300 (Ala. 1988). However, GM C argues that, because the trial court's decision was based almost exclusively on deposition testimony, affidavits, and exhibits, our review should be de novo. See Rogers Found. Repair, Inc. v.Powell, 748 So.2d 869, 871 (Ala. 1999) ("When a trial judge's ruling is not based substantially on testimony presented live to the trial judge, review of factual issues is de novo.").

In this case the appropriate standard of review is de novo review. The parties agree that the facts are not in dispute. As we stated in Philpot v. State, 843 So.2d 122, 125 (Ala. 2002), "[t]he ore tenus rule does not apply to cases involving undisputed facts." Moreover, while three witnesses did provide brief testimony at the May 6, 2002, evidentiary hearing, the trial court advised the parties that they should submit affidavits and that the trial court would treat the matter as one in which a motion for a summary judgment has been made. It is well-settled that we review a trial court's summary judgment de novo. Sessions v. Espy, 854 So.2d 515, 521 (Ala. 2002).

III.
GM C argues (1) that the trial court erred in denying its motion to reform the settlement agreement; (2) that the trial court erred in enforcing the settlement agreement against it when, GM C says, (a) the delay in funding the settlement until after Reliance Insurance Company entered liquidation was caused by Markel, and (b) Markel could have sought recovery from the Illinois Insurance Guaranty Fund; and (3) that the trial court erred in awarding interest on its judgment at a rate of 12% and measured from the date of Markel's payment to Vance.

For the reasons set forth below, we affirm the trial court's order denying GM C's motion to reform the settlement agreement. We also affirm the trial court's order enforcing the settlement agreement against GM C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Har-Mar Collisions, Inc. v. Scottsdale Insurance Co.
212 So. 3d 892 (Supreme Court of Alabama, 2016)
Mountain Lakes District v. Oak Grove Methodist Church ex rel. Green
126 So. 3d 172 (Court of Civil Appeals of Alabama, 2013)
AMERICAN HOMES AND LAND CORPORATION, INC. v. CA Murren & Sons Co.
990 So. 2d 871 (Supreme Court of Alabama, 2008)
Vest v. Vest
978 So. 2d 759 (Court of Civil Appeals of Alabama, 2006)
Alexander v. Burch
968 So. 2d 992 (Supreme Court of Alabama, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
911 So. 2d 1044, 2004 Ala. LEXIS 183, 2004 WL 1588101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodwyn-mills-cawood-inc-v-markel-ins-co-ala-2004.