Goodwin v. Tony Pocahontas Coal Co.

106 S.E. 76, 88 W. Va. 49, 1921 W. Va. LEXIS 50
West Virginia Supreme Court·Decided February 22, 1921·Published·Cited by 8 cases

Opinion

KlTZ, PRESIDENT:

This writ of error seeks reversal of a judgment in favor of the plaintiffs for a balance claimed to be due them for certain work done under a contract, providing for the grading of a siding for the defendant. The contract sued on is not in controversy, and simply provided for the doing of the work at a certain stipulated price per yard. It provided no* method for ascertaining the quantity, and when the work was completed the parties were unable to agree upon the number of yard^ of excavation, and this suit resulted from that disagreement.

The plaintiffs contend that at the time they entered upon the work under the contract defendant, through its engineer in charge, agreed to furnish them cross sections of the work to be done; that he was called upon a number of times therefor, and failing to furnish the same they employed an engineer to make cross sections of so much of the work as had not been done, and also of that part of the work which had been done. After the work was done they had this engineer calculate the quantities from the measurements taken by him upon the ground, both as to the work which had been done when he took the measure-mentsp and as to that part of it which then remained to be done.

He ascertained that there had been removed 8236.8 cubic yards of material. The defendant’s engineer likewise calculated the quantity from his measurements made on the 'ground before the work was undertaken, and ascertained that there were only 5160.77 cubic yards. Payment was made before and at the trial for this quantity, and this controversy involves the excesp. The trial resulted in a verdict in favor of the plaintiffs for substantially what they claimed. The defendant insists that this verdict cannot be sustained, for the reason that the estimates submitted in evidence by the plaintiffs, upon which the verdict is based, áre not trustworthy, and should not be allowed to stand in opposition to the estimates made by its engineer, and second, because the court admitted in evidence proof of an agree[51] ment bad between the parties, after the controversy arose, to submit the same to the determination of another engineer.

As before stated, the contract provided for the payment to the plaintiffs of $1.15 for each yard of material excavated, and the sole question which the jury had to decide was the quantity of this material. The defendant’s engineer contends that he accurately measured the ground before the work was done, and accurately calculated the quantities from these measurements, while the plaintiff’s engineer claims that as to the work remaining to be done at the time he made his measurements the same were absolutely accurate, and that as to the work which had then been done they were as accurate as could be made under the conditions then existing; that in making his measurements he had to guide him some of the stakes yet remaining, ‘the slope of the ground above the cut, and information furnished him by the men who actually did the work, and that from this he was able to make a reasonably accurate calculation as to the number of yards actually removed. Not only is there a substantial difference between the measurements made by thesp engineers as to the quantity of work which had been done at 'the time the plaintiff’s engineer made his measurements, but there is likewise such a difference as to the work which then remained to be done. As to the work which remained to be done at that time, admittedly the engineer employed by the plaintiff was in just as good a positon to ascertain the quantities as the defendant’s engineer, and there is no' suggestion but that he was just as competent for this purpose. His calculation makes •this quantity 855 yards more than it is ascertained to be by the defendant’s engineer. It is admitted, both by the plaintiffs and by their engineer, that he was not in position to make as accurate measurements of the quantities removed before he went upon the ground as he would have been had he made his measurements before the removal of the material, and as to this work it may be said that the defendant’s engineer had superior information and better opportunity to make correct measurements than the plaintiffs’ engineer. But this is not conclusive of the question. There are many suggestions in the evidence of inaccuracies in the work done by the defendant’s engineer in other [52] particulars;, and particularly it is testified by tbe engineer employed by the plaintiffs that the defendants engineer furnished him a profile of the work as well as cross sections thereof, and that there was a very substantial difference between the quantity of the work shown by the profile made by the defendant’s engineer and the quantity as shown by his cross sections. The jury had this evidence before them and they were the judges and the sole judges as. to what weight should be given to the evidence of the witnesses. There was no other way of ascertaining the quantity of material removed by the plaintiffs except to measure it, and while it is admitted that this method might not be absolutely accurate because of the unevenness of the ground, still it was the only practicable method which could be adopted, and it is shown that the result reached, if the measurements were accurately taken, was in all probability within a very few yards of the actual amount of material removed. There is nothing in the nature of the defendant’s evidence to give to it the character of finality upon this question. It is quite as probable that the defendant’s engineer made mistakes in his measurements and calculations as that the plaintiffs’ engineer did. In fact, the jury may well have concluded, because of the discrepancies pointed out in the work of defendant’s engineer, that the same was not done with the same care and accuracy as characterized the work done, on behalf of the plaintiffs. We think upon the question as to the.quantity of material removed by the plaintiffs, the j-ury’s verdict is not in conflict with such a substantial preponderance of the evidence as would justify setting aside upon that ground.

Free access — add to your briefcase to read the full text and ask questions with AI

Goodwin v. Tony Pocahontas Coal Co., 106 S.E. 76, 88 W. Va. 49, 1921 W. Va. LEXIS 50 (W. Va. 1921).

106 S.E. 76 (Goodwin v. Tony Pocahontas Coal Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Edmiston v. Wilson
120 S.E.2d 491 (West Virginia Supreme Court, 1961)
Spriggs v. Cheyenne Newspapers, Inc.
182 P.2d 801 (Wyoming Supreme Court, 1947)
State v. Barker
38 S.E.2d 346 (West Virginia Supreme Court, 1946)
State v. Hayes
153 S.E. 496 (West Virginia Supreme Court, 1930)
State v. Atwell
153 S.E. 583 (West Virginia Supreme Court, 1930)
Osage Gas Co. v. Cleveland & Morgantown Coal Co.
133 S.E. 388 (West Virginia Supreme Court, 1926)
State v. Long
108 S.E. 279 (West Virginia Supreme Court, 1921)
State v. Driver
107 S.E. 189 (West Virginia Supreme Court, 1921)