Goodwin v. Kingsmen Plastering, Inc.

340 P.3d 169, 267 Or. App. 506
CourtCourt of Appeals of Oregon
DecidedDecember 10, 2014
Docket1110128; A151821
StatusPublished
Cited by8 cases

This text of 340 P.3d 169 (Goodwin v. Kingsmen Plastering, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodwin v. Kingsmen Plastering, Inc., 340 P.3d 169, 267 Or. App. 506 (Or. Ct. App. 2014).

Opinion

DEVORE, J.

Plaintiffs brought this action against defendants for damages arising out of alleged defects in the construction of their home. The trial court granted defendants’ motion for summary judgment on the basis that, in the absence of a discovery rule, plaintiffs’ claims were barred by the six-year statute of limitations in ORS 12.080(3), which governs actions for “interference with or injury to any interest of another in real property[.]” Plaintiffs appeal the resulting judgment and argue that ORS 12.080(3) includes a discovery rule. Defendants disagree and, in the alternative, contend that plaintiffs’ claims are barred by the two-year statute of limitations in ORS 12.110(1). In two recent cases, discussed below, we have concluded that ORS 12.080(3) governs and contains a discovery rule. Accordingly, we reverse and remand.

In reviewing the trial court’s grant of defendants’ motion for summary judgment, we state the facts in the light most favorable to plaintiffs, the nonmoving party. Loosli v. City of Salem, 345 Or 303, 306 n 1, 193 P3d 623 (2008). Plaintiffs, Michael and Sheila Goodwin, purchased their home- in December 2004. Defendant Kingsmen Plastering, Inc. (KPI), was the subcontractor responsible for installing the synthetic stucco siding — or exterior insulated finish system (EIFS) — during the construction of the home in 2001. Plaintiffs alleged that in May 2010, they discovered numerous construction defects in the EIFS, which resulted in water intrusion and hidden property damage to the home. On March 10, 2011, plaintiffs filed suit against KPI, Kingsmen Contracting, Inc. (KCI), and T&M Pipeline, Inc., asserting claims of negligence and negligence per se in the construction of the home.

KPI filed a motion for summary judgment, in which KCI joined, arguing that plaintiffs’ claims were time-barred by the two-year statute of limitations for negligence claims in ORS 12.110. Defendants contended that plaintiffs were aware of potential claims more than two years before filing suit against defendants. Defendants’ reliance on ORS 12.110 was largely predicated on dicta in a footnote in Abraham v. T. Henry Construction, Inc., 350 Or 29, 249 P3d 534 (2011). [509]*509The Supreme Court described the facts in that case and the plaintiffs’ discovery of water damage in their home more than six years after it was constructed. The court commented:

“The statute of limitations for contract actions is six years. ORS 12.080(1). Tort claims arising out of the construction of a house must be brought within two years of the date that the cause of action accrues, but, in any event, within 10 years of the house being substantially complete. ORS 12.110; ORS 12.135. Tort claims ordinarily accrue when the plaintiff discovers or should have discovered the injury. Berry v. Branner, 245 Or 307, 311-12, 421 P2d 996 (1966).”

350 Or at 34 n 3 (emphasis added). Based on that footnote, defendants here urged the trial court to apply ORS 12.110.

In the alternative, defendants contended that, if the six-year statute of limitations in ORS 12.080(3) applied to plaintiffs’ claims, then the claims were still time-barred because that subsection does not incorporate a “discovery rule.” Without a discovery rule, defendants reasoned, the time limitation for commencement of a suit began running when the injury occurred, which could be no later than the date plaintiffs purchased their home in December 2004. In defendants’ view, the March 2011 complaint was not timely, either way.

Plaintiffs responded that ORS 12.080(3) provides a six-year statute of limitation for their claims and includes a discovery rule. With a discovery rule, the period of limitations would be deemed to commence upon either the date that plaintiff actually discovered the injury or the date that a person exercising reasonable care should have discovered the injury. Greene v. Legacy Emanuel Hospital, 335 Or 115, 123, 60 P3d 535 (2002). In plaintiffs’ view, summary judgment was not appropriate because genuine issues of material fact existed regarding when plaintiffs did discover or reasonably should have discovered the injury.

The trial court concluded that ORS 12.080(3) applied, but that it does not incorporate a discovery rule. Thus, an action governed by ORS 12.080(3) must be brought within six years of the date that the injury actually occurs. Because plaintiffs filed their claim on March 10, 2011, and [510]*510the construction was completed no later than 2001, the trial court determined that plaintiffs’ claims were not timely. The court entered a limited judgment dismissing plaintiffs’ claims against KPI and T&M Pipeline, Inc.1

On appeal, plaintiffs and defendant KPI — the only defendant that is a party to this appeal — reassert their arguments and present the same two questions. We addressed both questions in recent opinions. In Riverview Condo. Assn. v. Cypress Ventures (A150586), 266 Or App 574, 593, 339 P3d 447 (2014) (Riverview), we were required to determine which statute of limitations applied to the plaintiffs “construction-defect claims — i.e., claims based on [the] defendants’ negligence during construction.” As in this case, the defendants in Riverview asserted that ORS 12.110(1) governed, pointing to the same footnote in Abraham. Id. at 599. We disagreed and, based on another line of cases,2 determined that construction-defect claims alleging injury to an interest in real property are governed by the six-year statute of limitations in ORS 12.080(3). Id. at 600. We rejected the argument that the Supreme Court’s statement in Abraham was binding precedent. We found that the statement was dictum without any precedential value. Id. at 599-600.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Romero v. Amburn
523 P.3d 1135 (Court of Appeals of Oregon, 2022)
Willms v. AmeriTitle, Inc.
499 P.3d 79 (Court of Appeals of Oregon, 2021)
State v. Ritchie
475 P.3d 903 (Court of Appeals of Oregon, 2020)
Hammond v. Hammond
438 P.3d 408 (Court of Appeals of Oregon, 2019)
Goodwin v. Kingsmen Plastering, Inc.
375 P.3d 463 (Oregon Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
340 P.3d 169, 267 Or. App. 506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodwin-v-kingsmen-plastering-inc-orctapp-2014.