Goodwin & Goodwin, Inc. v. Neel, Harvell and Associates, PC

CourtDistrict Court, E.D. Oklahoma
DecidedJuly 31, 2023
Docket6:21-cv-00019
StatusUnknown

This text of Goodwin & Goodwin, Inc. v. Neel, Harvell and Associates, PC (Goodwin & Goodwin, Inc. v. Neel, Harvell and Associates, PC) is published on Counsel Stack Legal Research, covering District Court, E.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodwin & Goodwin, Inc. v. Neel, Harvell and Associates, PC, (E.D. Okla. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF OKLAHOMA

GOODWIN & GOODWIN, INC., ) an Arkansas Corporation, ) ) Plaintiff, ) ) Case No. CIV-21-19-TDD v. ) ) NEEL, HARVELL AND ASSOCIATES, P.C., ) an Oklahoma Corporation, and ) AERO-MOD, INC., a Kansas Corporation, ) ) Defendants. )

FINDINGS OF FACT AND CONCLUSIONS OF LAW

On April 25 and 26, 2023, the Court conducted a bench trial of the issues presented for decision in the Final Pretrial Report in this matter. See [Doc. No. 52]. Plaintiff and Counterclaim-Defendant Goodwin & Goodwin, Inc., appeared through attorney Matthew Horan and corporate representative Bryan Goodwin. Defendant Neel, Harvell and Associates, P.C., appeared through attorney J. Patrick Mensching and corporate representative Scott Neel. Defendant and Counter-Claimant Aero-Mod, Inc., appeared through attorney John D. Lackey and corporate representative Robert Mahan. Upon consideration of the evidence, the case record, and the parties’ arguments, the Court finds and rules as follows. Background This dispute arises out of the construction of a wastewater treatment plant (“Plant”) in Pocola, Oklahoma. In 2013, the City of Pocola engaged Neel, Harvell and Associates (“NHA”), an engineering firm specializing in wastewater treatment plant design, to design a new Plant. During the course of its design, NHA consulted with Aero-Mod, a wastewater equipment supplier, regarding equipment and electrical aspects of the Plant.

After NHA completed its initial design plans in 2018, the City of Pocola solicited bids for the new Plant’s construction. Ultimately, Goodwin & Goodwin (“G & G”) was selected to serve as the project’s general contractor. G & G executed a contract with Aero- Mod for the purchase of equipment to be installed at the Plant, and broke ground on the project in August of 2018. Between March and August of 2019, G & G poured and formed the Plant’s tank

walls to a height of twenty-two feet. After constructing the tank walls, G & G discovered that the equipment it purchased from Aero-Mod was only compatible with eighteen-foot, as opposed to twenty-two-foot, tank walls. As a result of this discrepancy, G & G reduced the height of certain tank walls from twenty-two to eighteen feet. G & G seeks to recover from Aero-Mod and NHA for the losses it allegedly incurred

while revising the tank walls. It asserts claims for negligence and breach of contract against Aero-Mod, as well as a negligence claim against NHA. Aero-Mod has alleged breach of contract and negligence counterclaims against G & G. The claims are within the Court’s jurisdiction pursuant to 28 U.S.C. § 1332. Findings of Fact

1. The City of Pocola solicited bids for the construction of its new Plant in the Spring of 2018. The bid advertisement was distributed on March 5, 2018, and all bids were due by April 19, 2018. Aero-Mod also distributed a draft purchase order to the general contractors interested in bidding on the project. By doing so, Aero-Mod proposed selling certain equipment for installation at the Plant.

2. The scope of services to be provided by the general contractor were based on the design plans created by NHA. The structural portion of NHA’s plans included a “hydraulic profile” which depicted, inter alia, the Plant’s top and bottom tank-wall elevations. The bottom elevation was 407 feet, and the top elevation was 429 feet, equating to a tank-wall height of twenty-two feet. See Pl.’s Ex. 2 at 4. 3. During the bidding period, NHA distributed a “notice to bidders,” which

altered certain design specifications. Specifically, the notice stated: The Drawings for the [Wastewater Treatment Plant Improvements] shall be and are hereby amended as follows: *** Sheets 30 & 32: Air piping supply and details (revisions from Aero-Mod). See attached drawing.

Pl.’s Ex. 5 at 1 (“Addendum No. 2”). The attached drawing reflects revised tank-wall heights of eighteen feet, as opposed to the twenty-two-foot walls depicted in the hydraulic profile. Addendum No. 2 is dated April 10, 2018, and is signed by NHA’s project manager, Scott Neel.1 Although Bryan Goodwin testified that an engineer typically approves project revisions, he also testified that Addendum No. 2 expressly altered the project’s specifications. 4. Upon reviewing the bid package and submitting its bid, G & G was selected to serve as the general contractor for the project. After it was selected, it signed two

1 Scott Neel is not a certified engineer. contracts: one with the Pocola Municipal Authority, and another with Aero-Mod for the purchase of equipment for installation at the Plant. See Pl.’s Ex. 6, 7.

5. The contract between G & G and the Pocola Municipal Authority is dated effective May 29, 2018. The contract specifies that Pocola Municipal Authority retained NHA to act as its representative in connection with the completion of the Plant. See Pl.’s Ex. 6 at 44. By signing the contract, G & G represented that it “examined and carefully studied the Bidding Documents,” including Addendum No. 2, which depicts eighteen-foot tank walls. Pl.’s Ex. 6 at 22.

6. The contract2 between G & G and Aero-Mod was executed by G & G’s president, Bryan Goodwin, on June 8, 2018. The contract states that “[t]he following scope of services is based upon the latest plans and specifications prepared by Neel, Harvell & Associates sealed February 23, 2018.” Pl.’s Ex. 7 at 2. It also provides: “As noted before, this scope of supply is based upon the referenced drawings. Should any changes be made

to the plans that will affect this scope of services, then Aero-Mod reserves the right to adjust this scope appropriately.” Pl.’s Ex. 7 at 11. 7. The contract required submittals3 to be sent by email to NHA’s project manager, Scott Neel. It also specifies that “[d]elivery [of equipment] may be within 20 weeks of receipt of approved submittal drawings. Allow six (6) weeks for drawing

2 The contract also included a choice of law provision, which states: “This offer and any related confirmation or contract of sale shall be governed by and construed in accordance with the laws of the State of Kansas.” Pl.’s Ex. 7 at 14. 3 Submittals are drawings or diagrams which illustrate some portion of the work to be performed. submittal after receipt of purchase order.” Pl.’s Ex. 7 at 10. The contract further states that “Aero-Mod will provide the detailed plan/construction submittal drawings in a timely

manner to assure proper and timely construction.” Id. 8. In an email dated June 27, 2018, Robert Mahan, Aero-Mod’s vice president and regional sales manager, wrote to Bryan Goodwin: There were many changes during the design of this project and confusion is to [be] expected. Our recommendation will be to build from our approved submittal drawings because they will be most consistent with the intended design. Changes will have no [e]ffect on the construction other than the locations of [] some wall inserts and piping. As soon as submittals are complete, we will send them out for review.

Pl.’s Ex. 8 at 1-2. Mahan testified that, although a change in tank-wall height constitutes a change in construction, at the time he emailed Bryan Goodwin, he understood that NHA’s plans had been amended—by virtue of Addendum No. 2—to reflect eighteen-foot, as opposed to twenty-two-foot, tank walls. 9. Aero-Mod finalized its submittals in late July of 2018. Consistent with Addendum No. 2, the submittals depicted eighteen-foot tank-walls. See Aero-Mod’s Ex. 10. These submittals were electronically transmitted, via email, to Scott Neel on July 25, 2018. See Aero-Mod’s Ex. 9. Alex Peterson, Aero-Mod’s assistant project manager, testified that she also mailed hard copies of the submittals to G & G’s office in early August. See also Aero-Mod’s Ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weldon v. Dunn
1998 OK 80 (Supreme Court of Oklahoma, 1998)
Delbrel v. Doenges Bros. Ford, Inc.
1996 OK 36 (Supreme Court of Oklahoma, 1996)
Mercury Investment Co. v. F.W. Woolworth Co.
1985 OK 38 (Supreme Court of Oklahoma, 1985)
Dirickson v. Mings
1996 OK 2 (Supreme Court of Oklahoma, 1996)
Digital Design Group, Inc. v. Information Builders, Inc.
2001 OK 21 (Supreme Court of Oklahoma, 2001)
Stroud v. Arthur Andersen & Co.
2001 OK 76 (Supreme Court of Oklahoma, 2001)
Wofford v. Eastern State Hospital
1990 OK 77 (Supreme Court of Oklahoma, 1990)
WOOD v. MERCEDES-BENZ OF OKLAHOMA CITY
2014 OK 68 (Supreme Court of Oklahoma, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Goodwin & Goodwin, Inc. v. Neel, Harvell and Associates, PC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodwin-goodwin-inc-v-neel-harvell-and-associates-pc-oked-2023.