Goodwill Community Chapel v. General Motors Corp.

503 N.W.2d 705, 200 Mich. App. 84, 1993 Mich. App. LEXIS 225
CourtMichigan Court of Appeals
DecidedJune 7, 1993
DocketDocket 130845
StatusPublished
Cited by5 cases

This text of 503 N.W.2d 705 (Goodwill Community Chapel v. General Motors Corp.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodwill Community Chapel v. General Motors Corp., 503 N.W.2d 705, 200 Mich. App. 84, 1993 Mich. App. LEXIS 225 (Mich. Ct. App. 1993).

Opinion

MacKenzie, J.

Plaintiff appeals as of right from an order granting summary disposition in favor of defendant. We affirm.

On November 24, 1980, the City of Detroit commenced a condemnation action against plaintiff and other property owners as part of the so-called "Poletown” project. The city offered and plaintiff accepted a settlement regarding plaintiff’s property. Plaintiff, however, subsequently sought to set aside the settlement as fraudulently induced by the city. The trial court summarily denied plaintiff’s motion to set aside the settlement; this Court remanded for a full review of plaintiff’s claims against the city. In re Acquisition of Land for the Central Industrial Park Project, 127 Mich App 255; 338 NW2d 204 (1983) (Acquisition I).

On remand, the trial court set aside the settlement and the case went to trial to decide the issue of just compensation. A jury awarded plaintiff *86 $95,000. Plaintiff moved to dismiss on the ground of lack of subject-matter jurisdiction, and also moved for a new trial on the ground of juror bias. The trial court denied the motion to dismiss, but granted a new trial. Following a second trial, the jury awarded plaintiff $118,025 as just compensation. Plaintiff again appealed. This Court held that the trial court lacked subject-matter jurisdiction with regard to the condemnation proceeding and hence should have dismissed the action. In re Acquisition of Land for the Central Industrial Park Project, 177 Mich App 11; 441 NW2d 27 (1989) (Acquisition II). The panel found that the city’s tender of a good-faith offer to purchase plaintiff’s property was mandatory to invoke the court’s jurisdiction over condemnation proceedings, and read this Court’s opinion in Acquisition I as concluding that the city did not make a good-faith offer to plaintiff. 177 Mich App 17. Accordingly, the case was remanded for dismissal without prejudice. The city refiled its condemnation action, and plaintiff has been compensated for the taking.

In the meantime, the city had conveyed the subject property to defendant by warranty deed on January 15, 1982, while plaintiff’s first appeal in the condemnation case was pending. Defendant subsequently demolished the building on the property, and the property became part of defendant’s Detroit/Hamtramck assembly plant.

After this Court ordered dismissal of the city’s condemnation action in Acquisition II, plaintiff filed this suit against defendant alleging that defendant had trespassed on plaintiff’s property. According to plaintiff, the city never obtained good title to the property and therefore could not pass good title to defendant. The trial court granted summary disposition in favor of defendant, concluding that the so-called "quick take” provision of *87 the Uniform Condemnation Procedures Act, MCL 213.57; MSA 8.265(7), automatically vested title to the property in the city when it commenced the condemnation action, and that title did not revert to plaintiff once it was ultimately determined that the city’s condemnation proceeding was jurisdictionally defective.

In two related arguments on appeal, plaintiff contends that the trial court erred in ruling that title to the subject property automatically vested in the city pursuant to MCL 213.57; MSA 8.265(7) because, as determined by this Court in Acquisition II, the complaint in the condemnation action was defective. Plaintiff reasons that the condemnation action was void ab initio, and, therefore, the city did not transfer valid title to defendant, thus making defendant liable as a trespasser. We disagree.

MCL 213.57; MSA 8.265(7) provides in relevant part:

[T]he title to the property described in the petition [for condemnation] shall vest in the [public] agency as of the date on which the complaint was filed. The right to just compensation shall then vest in the persons entitled to the compensation and be secured as provided in this act.

The primary goal of statutory construction is to ascertain and give effect to the intent of the Legislature. Legislative intent can be ascertained from examining the language of the act, the subject matter under consideration, the scope and purpose of the act, and other preceding statutes. Richmond Twp v Erbes, 195 Mich App 210, 221-222; 489 NW2d 504 (1992). The purpose of the condemnation act and its "quick take” provision is to enable governmental agencies to quickly obtain title so *88 that public projects can proceed without the delays of normal civil litigation:

The Michigan condemnation act, MCL 213.361 et seq.; MSA 8.261(1) et seq., represents an attempt by the Legislature to enable various condemning governmental agencies, in the absence of any controversy as to the necessity of the taking, to quickly obtain title and possession of condemned real property without the inherent delay found in a normal civil action. To do so, the Legislature has allowed the petitioning governmental agency to gain quick title to the premises, while insuring that the private property owner will have the right to receive just compensation for his property.
The effect of the several statutory provisions is to permit the condemning authority to quickly acquire title to the subject property upon the performance of certain acts while attempting to secure and protect the rights of the condemnee on the issue of just compensation for the taking within the meaning of the provisions of the Federal and Michigan constitutions, US Const, Am V; Const 1963, art 10, § 2, which prohibits the state from taking any private property without just compensation being provided to the property owner. [City of Fenton v Lutz, 73 Mich App 117, 120-122; 250 NW2d 579 (1977).]

In light of the Legislature’s intent that the condemning authority gain quick title without the delays of normal civil litigation, we think that MCL 213.57; MSA 8.265(7) must be construed as vesting title in that authority once a complaint for condemnation is filed. This reading does not destroy the condemnee’s right to challenge the complaint or the validity of any offers received from the condemning authority. Instead, it holds in abeyance resolution of such challenges without causing undue delay in the transfer of title. To *89 hold that title does not vest in the condemning authority until the propriety of the complaint for condemnation is resolved, as plaintiff urges, would completely frustrate the Legislature’s intent to promote quick vesting, as this case well illustrates. Here, the original complaint for condemnation was filed in November 1980. The propriety of the complaint was not finally resolved until May 1989, after two pretrial hearings, two trials, three trips to this Court, and one trip to the Supreme Court. Postponing the vesting of title in the city during the pendency of these proceedings would be wholly at odds with the legislative purpose of "quickly obtaining] title and possession of condemned real property without the inherent delay found in a normal civil action.” City of Fenton, supra, p 120.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
503 N.W.2d 705, 200 Mich. App. 84, 1993 Mich. App. LEXIS 225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodwill-community-chapel-v-general-motors-corp-michctapp-1993.