Goodrich Retainin Wall and Access

CourtVermont Superior Court
DecidedJune 12, 2014
Docket146-10-13 Vtec
StatusPublished

This text of Goodrich Retainin Wall and Access (Goodrich Retainin Wall and Access) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodrich Retainin Wall and Access, (Vt. Ct. App. 2014).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Vermont Unit Docket No. 146-10-13 Vtec

Goodrich Retaining Wall & Access Application DECISION ON MOTION

Decision on Cross-Motions for Summary Judgment In the pending matter, David Goodrich (“Appellant”) appeals the decision of the Town of Milton Development Review Board (“the DRB”) denying his application to construct a retaining wall adjacent to Lake Champlain on property over which he holds an easement for lake access. The Town of Milton Zoning Administrator (“the ZA”) denied the current application1 because the application form was not signed by the owners of the property as required by the Town of Milton, Vermont Zoning Regulations (“the Regulations”). Appellant timely appealed this determination to the DRB. The DRB affirmed the ZA’s decision and held that the application required the signature of the owner of the property as defined in the Regulations. Appellant appeals that decision to this Court. Appellant now seeks judgment as a matter of law that he is legally permitted to sign as the owner of the property because of the easement interest he holds in that property. The Town of Milton (“the Town”) filed a cross motion for summary judgment asking the Court to deny the application because the fee owner did not sign the application. Appellant was represented before the DRB and is represented in this appeal by Michael D. Johnson, Esq. The Town is represented by David W. Rugh, Esq. Felicia Montineri and Mary Ellen Harvey (“Owners”), the fee owners of the land over which Appellant holds the easement, were represented before the DRB by Carl H. Lisman, Esq. Owners, represented by Attorney Lisman, moved to intervene in this appeal on March 24, 2014, and the Court granted that

1 The record indicates that Mr. Goodrich filed at least two prior applications for the same retaining wall, both of which the ZA denied. The present appeal relates to Appellant’s third application for the retaining wall. As the parties have not briefed the issue of whether the application currently appealed to this Court should be barred by the prior applications, the Court does not consider this issue.

1 motion on March 28, 2014. Owners have chosen not to file memoranda in response to the pending cross-motions for summary judgment. Factual Background For the purpose of putting the pending motions into context, the Court recites the following material facts, which it understands to be undisputed unless otherwise noted: 1. Appellant obtained his property from Owners as part of a six-lot subdivision, referred to by the DRB as the “Clements Subdivision PUD.” Appellant owns Lots 2 and 3 from the subdivision, neither of which front on Lake Champlain. 2. As part of the subdivision, an easement for lake access was granted for the benefit of the owner of Lots 2 and 3 across Lot 4. This easement was located on the southern side of Lot 4. Both Appellant and Owners applied to the DRB to change the easement from the southern side of Lot 4 to the northern side, among other changes to the subdivision approval not relevant here. The change was necessary because the entire project was subject to the PUD/subdivision approval. Owners granted a 32-feet-wide, exclusive easement to Appellant across the northern side of Lot 4. The easement provides lake access and expressly allows Appellant to construct a dock, moorings, or other lake related activities on the portion of the Lot 4 lakefront area subject to the easement. It also requires that Appellant maintain this portion of the lakefront property subject to the easement. 3. In a November 15, 2012 vote, followed by a written decision issued December 13, 2012, the DRB approved Appellant’s and Owners’ subdivision amendment application. However, the DRB stated that the change in the lake access easement from the southern side of Lot 4 to the northern side of Lot 4 was not effective until a revised site plan and plat were submitted to the DRB, approved by the DRB, and recorded in the land records. These requirements were included as conditions of the DRB approval of the subdivision amendment application. 4. On May 3, 2013, Appellant submitted an application to the ZA seeking to construct a retaining wall along the portion of the northern side of Lot 4 subject to the easement. The ZA denied the application that same day because it did not satisfy the subdivision amendment approval conditions, including the requirement to record in the land

2 records the updated site plan and plat depicting the change in the lake access easement. Mr. Goodrich did not appeal the ZA’s May 3, 2013 decision to the DRB. 5. On June 28, 2013, Appellant filed a second application seeking to construct the same retaining wall proposed in the May 3, 2013 application. The record does not indicate whether the conditions of the subdivision amendment approval had been met as of May 3 or whether they have since been met. On July 1, 2013, the ZA denied the application. The ZA stated that the application form required the signature of the owner of the property as defined in the Regulations and that Appellant was not the owner and therefore could not sign as the owner. The ZA determined that because Owners had not signed the application, it must be denied. Appellant did not appeal the ZA’s July 1, 2013 decision to the DRB. 6. On August 8, 2013, Appellant again filed an application seeking to construct the same retaining wall. The drawing depicting the proposed construction is identical on all three applications. Appellant again signed the application as both the owner and applicant. On August 23, 2013, the ZA denied the application because it was not signed by the owner of the property as defined in the Regulations. Appellant timely appealed this decision to the DRB. 7. On September 26, 2013, the DRB held a public hearing on the appeal. After hearing from Appellant and Owners’ attorneys, the DRB voted unanimously to deny the application. A written decision was issued October 10, 2013. The DRB found that the ZA correctly interpreted the Regulations’ definition of owner and properly denied the application by applying that interpretation. The DRB further noted that it did not have the jurisdiction to determine the parties’ property rights. Appellant timely appealed that decision to this Court. Discussion In his motion for summary judgment, Appellant argues that because he has an exclusive easement over the 32-foot stretch of land, he may sign as the “owner of the property” in his application to build a retaining wall on the property subject to the easement. The Regulations define “ownership” as either “fee ownership or a leasehold interest of at least ninety-nine (99) years.” Regulations § 1000(6). The Town argues that the plain language of the Regulations’ definition of “ownership” is clear and unambiguous and should be enforced because it does not lead to irrational results

3 and is not contrary to the purpose of the Regulations. The Town admits for the purpose of the present motions that Appellant has an easement over the property at issue but does not waive its arguments over the scope of that property interest. The Town also argues that in order to adopt Appellant’s view, this Court would have to determine the extent of Appellant’s property rights in the easement. Apart from the dispute over the legal scope of Appellant’s easement, all facts are undisputed by the parties and therefore the issues presented are appropriate for summary judgment. I. Summary Judgment Standard We will grant summary judgment if a moving party demonstrates that “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” V.R.C.P. 56(a). When considering cross-motions for summary judgment, a trial court must consider each motion individually and give the opposing party the benefit of all reasonable doubts and inferences. City of Burlington v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Burlington v. Fairpoint Communications, Inc.
2009 VT 59 (Supreme Court of Vermont, 2009)
Appeal of Weeks
712 A.2d 907 (Supreme Court of Vermont, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Goodrich Retainin Wall and Access, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodrich-retainin-wall-and-access-vtsuperct-2014.