Goodrich Quality Theaters, Inc., and Roncelli, Inc. v. Fostcorp Heating and Cooling, Inc., Wilson Iron Works, Inc., and Johnson Carpet, Inc.

39 N.E.3d 660, 2015 Ind. LEXIS 715, 2015 WL 5042137
CourtIndiana Supreme Court
DecidedAugust 26, 2015
Docket64S03-1504-PL-227
StatusPublished
Cited by3 cases

This text of 39 N.E.3d 660 (Goodrich Quality Theaters, Inc., and Roncelli, Inc. v. Fostcorp Heating and Cooling, Inc., Wilson Iron Works, Inc., and Johnson Carpet, Inc.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodrich Quality Theaters, Inc., and Roncelli, Inc. v. Fostcorp Heating and Cooling, Inc., Wilson Iron Works, Inc., and Johnson Carpet, Inc., 39 N.E.3d 660, 2015 Ind. LEXIS 715, 2015 WL 5042137 (Ind. 2015).

Opinion

*661 On Petition to Transfer from the Indiana Court of Appeals, No. 64A03-1308-PL-318

DAVID, Justice.

The question before us is whether, under Indiana’s mechanic’s lien statute, lien-holders are- entitled to collect attorney’s fees incurred in foreclosing upon their liens from a party who posts a surety bond securing the liens. By the statute’s plain language, under the circumstances our answer is yes.

Facts and Procedural History

Goodrich Quality Theaters, Inc. (Goodrich) hired Roncelli, Inc. (Roncelli) to be the general contractor responsible for building an IMAX movie theater in Porter County, Indiana. Roncelli then hired several sub-contractors to provide the labor, services, and materials necessary to construct the theater. Three of these subcontractors—Fostcorp Heating and Cooling, Inc. (Fostcorp); Wilson Iron Works, Inc. (Wilson); and Johnson Carpet, Inc., d/b/a Johnson Commercial Interiors (Johnson)—are parties in this case.

Problems plagued the project, and the theater was completed months behind schedule. After Fostcorp, Wilson, and Johnson failed to receive full payment for their services, all three timely filed mechanic’s liens against the IMAX property pursuant to Indiana Code § 32-28-3-1. The three subcontractors then sued Ron-celli and Goodrich to foreclose on their respective liens in the amount due on their Roncelli contracts. Each requested attorney’s fees.

While the case was pending, Roncelli filed an undertaking and posted a surety bond pursuant to Indiana Code § 32-28-3-11. The bond provided that Roncelli, the bond’s principal, and/or Hartford Fire Insurance Company, its surety, must pay in full any judgment recovered in an action to foreclose on a lien, ■ “including costs and attorney’s fees allowed by the court.” (Appellant’s App. at 655.) Approving the bond, the trial court ordered the mechanic’s liens on the IMAX property released, with the bond to serve as security, in lieu of the real property. Three months later, Goodrich paid Roncelli in full, and Roncelli and Goodrich filed a motion to dismiss the claims for attorney’s fees. 1 The trial court denied the motion.

After a fourteen-day bench trial spanning nearly a year, the trial court awarded Fostcorp separate $489,962.81 judgments against Roncelli ánd Goodrich (later amended to $539,139.11); Wilson a $373,888.22 judgment against Roncelli (later amended to $412,751.84); and Johnson a $55,420.20 judgment against Roncelli. The trial court also awarded attorney’s fees to Fostcorp, Wilson, and Johnson. Specifically, it awarded Fostcorp $97,173.13 and Wilson $355,488.67 in attorney’s fees against Roncelli. The record does not appear to include the amount awarded to Johnson.

Roncelli then appealed, raising numerous issues primarily relating to breach of contract but also to the award of attorney’s fees. Regarding., the latter, Roncelli claimed that § 32-28-3-14 could not provide a basis for the subcontractors’ attorney’s fees awards for the following three reasons. First, Goodrich paid Roncelli full consideration for the contract, which fulfilled the purpose of the mechanic’s lien statute and left the subcontractors the .sole recourse of seeking contractual remedies from Roncelli. Second, a dispute between a general contractor and subcontractors does not implicate § 32-28-3-14, which was enacted to “prevent the inequity of a *662 property owner enjoying the benefits of the labor and materials furnished by others without recompense.” (Appellant’s Br. at 54-55 (quoting Premier Investments v. Suites of America., Inc., 644 N.E.2d 124, 130 (Ind.1994),)) And third, because there was no statutory authorization to award attorney’s fees to the subcontractors, under § 32-28-3-11 Roncelli’s filing of the bond does not obligate it to pay more than a judgment. For these reasons, Roncelli concluded that the trial court abused its discretion in awarding attorney’s fees to the three subcontractors.

Though they submitted three separate briefs, the subcontractors collectively contended that § 32-28-3-14 allowed the trial court to award attorney’s fees incurred in the foreclosure of their mechanic’s liens and due to them upon their recovery of a judgment against Roncelli. Each challenged Roncelli’s interpretation of § 32-28-3-14 as inequitably enabling general contractors to avoid paying attorney’s fees.

Determining that “[t]he crux of Roncel-li’s argument is the mechanic’s lien statutes in Indiana Code chapter 32-28-3 only apply to the property owners,” which Ron-celli is not, the Court of Appeals agreed with Roncelli that the mechanic’s liens and subsequent attorney’s fees could not be enforced against it. Goodrich Quality Theaters, Inc. and Roncelli, Inc. v. Fostcorp Heating and Cooling, Inc., Wilson Iron Works, Inc., Johnson Carpet, Inc., d/b/a Johnson Commercial Interiors, 16 N.E.3d 426, 441 (Ind.Ct.App.2014). Consequently, the Court of Appeals reversed the trial court’s award of attorney’s fees. Id. On all other issues, the court affirmed the trial court. Id.

Each subcontractor filed for rehearing and claimed, among other things, that under § 32-28-3-11 it was entitled to recover attorney’s fees against the bond Roncelli posted. But the Court of Appeals found that “[although Roncelli’s undertaking assures payment of any judgment plus costs and fees allowed by the court, it does not give the [subcontractors] greater rights or impose greater liability on Roncelli than the underlying obligation.” Goodrich Quality Theaters, Inc. and Roncelli, Inc. v. Fostcorp Heating and Cooling, Inc., Wilson Iron Works, Inc., Johnson Carpet, Inc., d/b/a Johnson Commercial Interiors, 23 N.E.3d 28, 29 (Ind.Ct.App.2014). Arriving back at its previous conclusion that § 32-28-3-14 did not permit the subcontractors to recover attorney’s fees from non-property owner Roncelli, the court reaffirmed its prior holding that the trial court erred in awarding attorney’s fees. Id.

The subcontractors subsequently petitioned this Court for transfer on the question of whether Indiana’s mechanic’s lien statute permits recovery of attorney’s fees from Roncelli under the circumstances. We granted transfer, thereby vacating the Court of Appeals opinions. Goodrich Quality Theaters, Inc. and Roncelli, Inc. v. Fostcorp Heating and Cooling, Inc., Wilson Iron Works, Inc., Johnson Carpet lnc., d/b/a Johnson Commercial Interiors, 29 N.E.3d 124 (table) (Ind.2015); See also lnd. Appellate Rule 58(A). 2

Standard of Review

We review the trial court’s interpretation of Indiana’s mechanic’s lien statute de novo. See Young v. Hood’s Gardens, 24 N.E.3d 421, 424 (Ind.2015). We do so with the knowledge that “[o]ur primary goal in interpreting any statute is to effectuate legislative intent. An unambig *663

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jessica D. Grimes v. Tia L. Houser
108 N.E.3d 397 (Indiana Court of Appeals, 2018)
KS&E Sports and Edward J. Ellis v. Dwayne H. Runnels
66 N.E.3d 940 (Indiana Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
39 N.E.3d 660, 2015 Ind. LEXIS 715, 2015 WL 5042137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodrich-quality-theaters-inc-and-roncelli-inc-v-fostcorp-heating-and-ind-2015.