Good v. Central Coal & Coke Co.
This text of 170 F. 416 (Good v. Central Coal & Coke Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
This is the second appearance of this case in this court. 120 Fed. 793, 57 C. C. A. 161. When the case was first here a new trial was ordered, which resulted in a verdict and judgment for the plaintiff. The case was appealed to the United States Court of Appeals for the Indian Territory, and the judgment is affirmed for the reasons stated in the opinion of that court, set out in the record as follows:
.“Statement.
“The original complaint in this cause was filed on the 13th day of October, 1895, at South McAlester. On April 29, 1896, the defendants George S. Good & Co. filed their answer to the complaint. On June 30, 1898, the plaintiff filed its amended complaint, and on the same day the defendant filed its amended answer; a jury was impaneled, and the case proceeded to trial.
“The plaintiff in its amended complaint alleged that on the 15th day of December, A. D. 1894, plaintiff and defendants entered into a written contract in which it was agreed that plaintiff should furnish defendants lumber and piling to be used in the construction of the line of the Choctaw, Oklahoma & Gulf Railroad, and that said defendants should pay plaintiff for such lumber and piling as follows: For all lumber delivered f. o. b. South McAlester, Ind. T., $13.50 per thousand feet, board measure; for all lumber delivered f. o. b. Oklahoma City, Okl. T., $15.50 per thousand feet, board measure; for all piles delivered f. o. b. South McAlester, Ind. T., 13% cents per 'lineal foot; for all piles delivered f. o. b. Oklahoma City, Okl. T., 16 cents' per lineal foot.
“Plaintiff alleges that in all things it had complied with said contract, and furnished to defendants a. large amount of lumber and piling, a statement of which is attached to said complaint, marked ‘Exhibit B’; that defendants accepted and used the same, but have failed and refused to pay for same, and still refuse so to do, although the same is long past due; that there is due plaintiff from defendants for lumber and piling so furnished the sum of $9,02-4.-[417]*41742, together with interest at the rate of 6 per cent, from the 20th day of September, 1805, and asks judgment for the same.
“For a second, cause of action jilaintiff alleges that at the instance and request of defendants it furnished and delivered to defendants, upon said line of -the Choctaw, Oklahoma & Gulf Railroad Company, piling as follows, to wit: On May 2Ü, 1895, 12.957 feet; on July 30, 1895, 2,044 feet; on September 30, 1895, 24.177 feet; that said piling so furnished and delivered at the time of its delivery was reasonably worth the sum of 16 cents per foot, making a total value of ,$6,268.48. Said piling is a part of and included in the account referred to in the foregoing count, which is marked ‘Exhibit B,’ and that defendants have refused to pay for the same; and ask judgment for $6,268.48 as the reasonable value of said piling, with interest at 6 per cent, per annum from the 20th day of September. 1895.
“Defendants in their amended answer, first, deny each and every allegation in the amended complaint filed, and demand strict proof of the same; but defendants admit that they owe the plaintiff the sum of $1,201.04. Defendants further say that they ought not to be held to pay plaintiff any further sum of money, because they have paid M. \V. Osborn the very sum of money which the plaintiff sues for in this case, and the same was paid to the said Osborn under and by virtue of a certain contract entered into between the defendants and the said Osborn on the 7th day of December, 1894.
“Second, the defendants by counterclaim ask damages in the sum of $10,000.
“Thereupon the plaintiff filed its reply to paragraph 2 of said amended answer, and denies all damages alleged by defendants. Thereupon the case was tried by a jury, and on July 2, 1898, the jury returned a verdict for plaintiff in the sum of $1,201.04. On August 30, 1898, motion for new trial was presented and overruled by the court, and .plaintiff appealed to this court.
“On October 5th, 1901, the judgment in this case in the court below was affirmed -by this court, and the plaintiff appealed to the United States Circuit Court of Appeals for the Eighth Circuit, and on April 21, 1903, there was filed with the clerk of this court the mandate of the United States Circuit Court of Appeals for the Eighth Circuit, reversing the judgment of the United States Court for tho Central District of Indian Territory, and ordering a new trial therein in said cause.
“On June 24, 1903, the court below ordered that the venue herein, by agreement of parties, be changed to the Poteau division, and on August 24, 1903, a transcript and all original papers were filed at Poteau, and said cause duly docketed.
“On January 8, 1904, there was filed the third amended answer of the defendants, denying the allegations in plaintiff’s complaint, that it has in all things complied with said contract; deny that there is due from defendants to plaintiff $9,024.44, with interest from the 20th day of September, 1905, or any other sum of money; deny that defendants are indebted to plaintiff in the sum of $6,268.48, or any other sum of money whatever, except as may be hereinafter stated; deny that plaintiff furnished the lumber and piling contained in Exhibit B to said complaint; deny that defendants have refused to pay for any part of the same; deny that on the 15th day of December, 1894, defendants entered into a written contract, by the terms of which it was agreed that plaintiff should furnish lumber or piling to be used in the construction of the Choctaw, Oklahoma & Gulf Railroad; deny that defendants obligated themselves to pay for such lumber and piling in the manner stated and set out in plaintiff’s amended complaint; deny that the defendants have accepted said lumber and piling as charged in said amended complaint; and defendants say a just account between plaintiff and defendants will show that there is due plaintiff by defendants the sum of $1,201.04, subject, however, to damages hereinafter set forth and claimed by defendants against plaintiff.
“Defendants further say they ought not to be held to pay to plaintiff any further sum of money, because they have already paid to one M. W. Osborn the very sum of which plaintiff sues in this case, and that the same was paid under and by virtue of a contract between the defendants and Osborn, entered into on the 7th day of December, 1891. all of which plaintiff knew and agreed to and acquiesced in, and defendants say that said sum was paid to said Os[418]*418born for the lumber and piling for which plaintiff now sues, and was paid to said Osborn with the full understanding and knowledge of the plaintiff, and with its consent.
“further answering, defendants say that prior to the 20th day of May, 1895, Osborn furnished to defendants piling to the amount of $10,000; that monthly estimates were furnished Osborn, and he was paid monthly; that plaintiff knew that defendants were receiving the piles as Osborn’s piles, and did not notify defendants that they were claiming same; that defendants did not know that plaintiff had any arrangement with Osborn to furnish these piles to defendants until May 20th as aforesaid, as the piles of Osborn, furnished under a contract with said Osborn.
“Second.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
170 F. 416, 95 C.C.A. 586, 1909 U.S. App. LEXIS 4719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/good-v-central-coal-coke-co-ca8-1909.