Gomez Pools v. Arizona Registrar
Opinion
NOTICE: NOT FOR OFFICIAL PUBLICATION.
UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.
IN THE
ARIZONA COURT OF APPEALS
DIVISION ONE
GOMEZ POOLS & SERVICE LLC, Plaintiff/Appellant,
v.
ARIZONA REGISTRAR OF CONTRACTORS, Defendant/Appellee.
No. 1 CA-CV 22-0241
FILED 12-15-2022
Appeal from the Superior Court in Maricopa County No. LC2021-000195-001
The Honorable Daniel J. Kiley, Judge
AFFIRMED
COUNSEL
Wheeler Law Group, PLLC, Tempe By Julianne C. Wheeler Counsel for Plaintiff/Appellant
Arizona Attorney General’s Office, Phoenix By Justin Larson Counsel for Defendant/Appellee
Decision of the Court
MEMORANDUM DECISION
Presiding Judge Samuel A. Thumma delivered the decision of the Court, in which Judge Cynthia J. Bailey and Vice Chief Judge David B. Gass joined.
T H U M M A, Judge:
¶1 Gomez Pools & Service, LLC (GPS) appeals from the superior court’s ruling reversing, vacating and remanding for further proceedings an Arizona Registrar of Contractor’s (ROC) decision revoking GPS’ contractor’s license. GPS also challenges the court’s denial of its request for attorneys’ fees. Because GPS has shown no error, the rulings are affirmed.
FACTS AND PROCEDURAL HISTORY
¶2 GPS is an ROC-licensed swimming pool contractor. In October 2019, GPS signed a contract to build a swimming pool at a recreational vehicle park in Tacna, Arizona, owned by Copper Mountain R.V. Park, LLC. The one-page form contract GPS supplied required Copper Mountain to make $73,000 in progress payments. In October 2020, the pool was not finished, and Copper Mountain filed a complaint with the ROC alleging GPS committed fraud and abandoned the project. The parties later reached an Interim Settlement Agreement with a December 2020 completion date, but the pool was still unfinished on that date.
¶3 After an inspection, the ROC issued a written directive requiring GPS to complete the project by early January 2021. When GPS failed to do so, the ROC issued a Citation against GPS’ license. GPS requested a hearing, which was held by an Office of Administrative Hearings Administrative Law Judge (ALJ).
¶4 After receiving evidence and argument, the ALJ issued an eight-page decision, recommending that the ROC revoke GPS’ license. The ALJ recommended revocation as “the appropriate sanction” based on four findings:
[1 GPS’] failure to accept responsibility for its actions, [2] its failure to comply with the Interim Settlement Agreement, [3] that [GPS] made false statements to [Copper Mountain] during the time project was under way, and [4] that after
Decision of the Court
almost a year and a half, the project had not been completed.
The ROC accepted the recommended decision as written and denied GPS’ motion for rehearing.
¶5 GPS appealed to the superior court, also seeking an award of attorneys’ fees and costs under Arizona Revised Statutes (A.R.S.) sections 12-348 and 12-341.01. GPS and Copper Mountain then settled their dispute. GPS filed a stipulation and notice, alerting the court of the settlement and that Copper Mountain had withdrawn its complaint with the ROC. Stating Copper Mountain “has no objection” to the reversal of the ROC decision, the notice added GPS and Copper Mountain “recognize [] the ROC has standing to pursue defense of the appeal.” GPS, however, did not seek dismissal of its appeal.
¶6 GPS’ opening brief in the superior court, filed months later, acknowledged that the ROC had “active party status” and argued the merits of GPS’ appeal. GPS’ opening brief did not ask that its appeal be withdrawn or dismissed. Nor did it request an award of attorneys’ fees. The ROC’s response asked the court to uphold the ROC’s decision.
¶7 After oral argument, the superior court reversed and vacated the ROC’s decision and remanded to the ROC for further proceedings. In doing so, the court noted two issues. First, the court expressed concern that the ALJ may have required corroboration by a GPS witness, but not an ROC witness. Second, the court rejected the decision’s reliance on GPS’ “failure to comply with the Interim Settlement Agreement,” stating that doing so was an “error of law” because deciding the consequences for a contract breach “is a judicial, not an administrative, function.” Accordingly, the court found, a breach of the Interim Settlement Agreement was not a proper basis for revoking GPS’ license.
¶8 Because the record was unclear as to whether the revocation decision would have been the same without relying on GPS’ breach of the Interim Settlement Agreement, the court reversed and vacated the decision and remanded to the ROC for “further appropriate proceedings.” The court also found GPS waived its request for attorneys’ fees and costs by failing to request them in its opening brief. The court entered the ruling as a final judgment. See Ariz. R. Civ. P. 54(c).
¶9 GPS moved to reconsider, arguing for the first time that “no further proceedings [were] appropriate because” Copper Mountain “withdrew the Complaint,” and challenging the waiver finding on fees. In
Decision of the Court
opposition, the ROC argued it had taken an active role in the litigation as authorized under A.R.S. § 32-1154(B)(1) and remand was appropriate. Before the superior court ruled on the motion to reconsider, GPS filed a timely notice of appeal. Because the notice of appeal divested the superior court of jurisdiction, it noted but did not rule on the motion to reconsider. See Aqua Mgmt., Inc. v. Abdeen, 224 Ariz. 91, 93 ¶ 7 n.3 (App. 2010). This court has jurisdiction over GPS’ appeal under Article 6, Section 9, of the Arizona Constitution; A.R.S. §§ 12-913, -120.21(A)(1) and -2101(A)(1) and JRAD Rule 13.
DISCUSSION
¶10 GPS argues the superior court erred by (1) remanding the case because Copper Mountain withdrew its complaint and (2) finding that GPS waived its request for attorneys’ fees and costs.
I. The Superior Court Properly Remanded the Case to the ROC for Further Proceedings.
¶11 Whether remand is appropriate is an issue of law this court reviews de novo. Hafner v. Beck, 185 Ariz. 389, 391 (App. 1995). The Legislature defines the scope of the ROC’s authority. See Roberts v. State, 512 P.3d 1007, 1017 ¶ 36 (2022). Stated generally, the Legislature authorized the ROC to regulate and discipline contractor licenses. See A.R.S. § 32-1100 et seq. Among other things, the ROC can investigate a contractor’s actions upon receiving a private complaint or on its own. See A.R.S. § 32-1154(B). “[A]lthough a private complainant may prompt the Registrar’s initial investigation, the Registrar chooses whether and to what extent to pursue its administrative proceeding, pursuant to A.R.S. § 32–1155.” Mission Hardwood Co., Inc. v. Registrar of Contractors of State of Ariz., 149 Ariz. 12, 16 (App. 1986). The ROC’s investigation of, and discipline against, a contractor’s license is separate and independent of the complainant’s rights to press court proceedings. See Bentivegna v. Powers Steel & Wire Products, Inc., 206 Ariz. 581, 585 ¶14 (App. 2003).
¶12 Both in the stipulation and notice filed in the superior court, and in its opening brief with that court, GPS recognized the ROC has standing to pursue the matter. That tracks Mission Hardwood, which recognized the ROC can “adopt[] the role of an advocate in the appeal to the superior court.” 149 Ariz. at 16. GPS now argues Mission Hardwood does not apply because the complainant in that case had not withdrawn its complaint.
Decision of the Court
Free access — add to your briefcase to read the full text and ask questions with AI
Gomez Pools v. Arizona Registrar (Gomez Pools v. Arizona Registrar) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.