Goljac, LLC v. Emerald Bay Developers, Llc.

CourtNew Jersey Superior Court Appellate Division
DecidedMarch 19, 2024
DocketA-1154-23
StatusUnpublished

This text of Goljac, LLC v. Emerald Bay Developers, Llc. (Goljac, LLC v. Emerald Bay Developers, Llc.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goljac, LLC v. Emerald Bay Developers, Llc., (N.J. Ct. App. 2024).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1154-23

GOLJAC, LLC,

Plaintiff-Appellant,

v.

EMERALD BAY DEVELOPERS, LLC, CRAIG ROPER, DYKES LUMBER COMPANY, INC., REYNAERS, INC. and MELMOUSE, LLC,

Defendants-Respondents. ________________________________

Argued March 6, 2024 – Decided March 19, 2024

Before Judges Accurso and Vernoia.

On appeal from an interlocutory order of the Superior Court of New Jersey, Law Division, Hudson County, Docket No. L-1353-20.

Bernadette Hamilton Condon argued the cause for appellant (Lum, Drasco & Positan, LLC, attorneys; Paul A. Sandars, III, of counsel and on the brief; Bernadette Hamilton Condon, on the brief).

Respondents have not filed briefs. PER CURIAM

By leave granted, plaintiff Goljac, LLC appeals from orders denying its

motion for leave to file a third-amended complaint adding as defendants J.

Cullen Alterations (J. Cullen), Titan Construction Management Services, Inc.

(Titan) and Titan Building Co. (Titan Building). 1 Based on our review of the

record, and having concluded the court abused its discretion by denying the

motion, we reverse.

This matter arises out of a dispute concerning the construction of a multi-

million-dollar home (the project) in Sagaponak, New York. Plaintiff owns the

property.

According to plaintiff's counsel's certification supporting the motion for

leave to file a third-amended complaint, in 2018, Dykes Lumber Company, Inc.

(Dykes Lumber) filed an action against Emerald Bay Developers, LLC (Emerald

Bay) and Craig Roper (Roper) for sums due for materials supplied for the

1 Plaintiff appeals from a November 3, 2023 order denying its motion for leave to file a third-amended complaint adding J. Cullen as a defendant and a November 14, 2023 order denying its motion for leave to file a third-amended complaint adding Titan and Titan Building as defendants. Entry of the orders followed plaintiff's filing of a single motion for leave to file a third-amended complaint adding all three entities as defendants. The court filed a single written opinion dated November 3, 2023, supporting its denial of plaintiff's motion but entered separate orders denying the requested relief. A-1154-23 2 construction of the project. 2 In that matter, Emerald Bay and Roper filed a third-

party complaint against plaintiff and Steven Dorsky (Dorsky).

In 2020, plaintiff and Dorsky separately filed this action against Emerald

Bay and Roper, asserting "claims for construction defects and delay." The initial

complaint, and the subsequent first- and second-amended complaints, are not

included in the record on appeal. The court later consolidated this matter for

discovery purposes with the prior action filed by Dykes Lumber.

In support of the motion for leave to file the third-amended complaint,

plaintiff's counsel represented that documents produced by Emerald Bay in

discovery included a construction supervision agreement between Emerald Bay

and J. Cullen and a framing contract between Emerald Bay and Titan and Titan

Building. According to plaintiff's counsel, Emerald Bay had construction

management responsibilities at the project and had "subcontracted its

construction management responsibilities to" J. Cullen.

Plaintiff obtained a December 8, 2022 expert report concerning

construction management at the project that identified J. Cullen, Titan, and Titan

Building as "parties" on the project and explained J. Cullen's responsibilities on

2 The matter is captioned as Dykes Lumber Company, Inc. v. Emerald Bay Developers, LLC and Craig Roper, under Docket No. HUD-L-2129-19. A-1154-23 3 the project. The report further concluded "the Construction Manager did not

meet industry standards of care" on numerous aspects of the construction

management on the project.

In plaintiff's counsel's certification, he noted that Emerald Bay had

submitted an expert report in discovery, explaining Emerald Bay had engaged J.

Cullen as "a construction project supervisor" to "provide full-time onsite

construction project supervision."

Plaintiff's counsel further explained that Emerald Bay had subcontracted

with Titan and Titan Building to perform framing work on the project.

Additionally, plaintiff's expert's report explained the project suffered from

"extensive framing defects."

Plaintiff's counsel asserted the addition of J. Cullen, Titan, and Titan

Building as defendants in the proposed amended-third-party complaint was

required because plaintiff had determined their work on the project was

defective and contributed to plaintiff's alleged damages. Plaintiff's counsel also

represented that plaintiff had expected Emerald Bay would implead J. Cullen,

Titan, and Titan Building after their work was described as defective in

plaintiff's expert's report because those proposed defendants had been Emerald

Bay's subcontractors.

A-1154-23 4 Counsel further explained the addition of J. Cullen, Titan, and Titan

Building as defendants in plaintiff's complaint was discussed at an October 11,

2023 conference with the court, and the case management order entered that day

authorized plaintiff to move for leave to amend its complaint to add them as

defendants. Counsel also represented that an order granting plaintiff leave to

file the third-amended complaint would not prejudice any of the other parties

because "fact discovery [was] still open[,]" "fact depositions [were] not

completed and expert depositions [had] not yet occurred." Counsel asserted

plaintiff "would be prejudiced if it were not allowed to recover any of its

provable damages from any parties," including J. Cullen, Titan, and Titan

Building, "responsible for causing its damages."

None of the other parties in the consolidated matters filed opposition to

plaintiff's motion. Thus, none claimed they would be prejudiced by plaintiff's

proposed amendment adding J. Cullen, Titan, and Titan Building as parties.

Similarly, none of the other parties oppose plaintiff's appeal from the court's

orders denying its request to file the proposed third-amended complaint.

In the court's written opinion, it found that "in all likelihood" the

document that provided impetus for plaintiff's expert's report identifying J.

Cullen's, Titan's, and Titan Building's role in the construction of the project had

A-1154-23 5 been supplied in discovery "many months ago," and that prior to plaintiff's

expert's report, no other expert in the case had implicated J. Cullen in the project.

The court also found that "in all likelihood," the construction supervision

agreement between Emerald Bay and J. Cullen "had . . . been produced in

discovery . . . well before" the court had entered a June 9, 2023 case

management order, which "limited expert reports to certain topics."

The court explained no trial date in the matters had been set and

"Administration for the Hudson County Court System ha[d] determined that no

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavuoti v. New Jersey Transit Corp.
735 A.2d 548 (Supreme Court of New Jersey, 1999)
Kernan v. One Washington Park Urban Renewal Associates
713 A.2d 411 (Supreme Court of New Jersey, 1998)
Bustamante v. Borough of Paramus
994 A.2d 573 (New Jersey Superior Court App Division, 2010)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
Iliadis v. Wal-Mart Stores, Inc.
922 A.2d 710 (Supreme Court of New Jersey, 2007)
Notte v. Merchants Mutual Insurance
888 A.2d 464 (Supreme Court of New Jersey, 2006)
US Bank National Ass'n v. Guillaume
38 A.3d 570 (Supreme Court of New Jersey, 2012)
Murray v. Plainfield Rescue Squad
15 A.3d 30 (New Jersey Superior Court App Division, 2011)
Murray v. Plainfield Rescue Squad
46 A.3d 1262 (Supreme Court of New Jersey, 2012)
State ex rel. A.R.
188 A.3d 332 (Supreme Court of New Jersey, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Goljac, LLC v. Emerald Bay Developers, Llc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/goljac-llc-v-emerald-bay-developers-llc-njsuperctappdiv-2024.