Goldschmid v. The Mayor of the City of New York

14 A.D. 135, 43 N.Y.S. 447
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 15, 1897
StatusPublished
Cited by9 cases

This text of 14 A.D. 135 (Goldschmid v. The Mayor of the City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goldschmid v. The Mayor of the City of New York, 14 A.D. 135, 43 N.Y.S. 447 (N.Y. Ct. App. 1897).

Opinion

Rumsey, J.:

In the year 1892 the plaintiff was thp owner and in the possession •of a lot of land situated bn One Hundred and Eighty-fourth street, near the point where that street intersects Bainbridge avenue. It became necessary to fix the grade of the street in front of the plaintiff’s premises,, and it was established at a height of about twenty-two feet above the surface of the ground along the front of the plaintiff’s lot. The city undertook, through a contractor,'to fill .in the street, and. for that purpose caused to he erected a retaining wall .along the whole front to the necessary height. The wall was located by the engineers in the employ of the city and was built "by the contractor under the direction-of the city officials. It was claimed Toy the plaintiff that this wall was actually built over the line of his premises and that it was so badly constructed that after the earth Lad been filled in behind it on the street, it bulged out so that it' [137]*137projected over his lot for something over a foot, and that stones were continually falling from the wall upon his land, so that it was unsafe to approach near to the wall, and in consequence he was practically deprived of the use of his premises for some considerable distance about the place where the wall stood. For these alleged wrongs he brought, this action against the city, joining as a defendant, also, the contractor who did the work.

Upon the trial of the action the. jury found a verdict in favor of the ■contractor, but' against the city,, for about $800 damages. Upon this verdict a judgment was entered, .and the defendant, by this appeal, seeks to set aside that judgment. Ho claim was made by the plaintiff that he was entitled to any damages because of the change of the grade of the street in front .of his house. On the contrary, any ■claim for damages for depreciation in the value of his lot because of the change of grade was eliminated in the testimony of the witnesses, .and the jury were carefully instructed by the trial judge that if the damages to the plaintiff’s lot were caused by the change' in the grade of the street, or so far as they were caused by such change, the plaintiff was- no.t entitled, to .recover. The right to a recovery was claimed by the plaintiff, and was ruled by the trial judge to arise entirely from the fact th,at the wall as built encroached upon the plaintiff’s premises, and that .the damage was caused solely by ¡such encroachment. There can be no doubt that the jury were fully instructed upon that subject,' and it is not possible, under the •charge, that any portion of the amount,found by the jury as damages could arise from the mere fact of the depreciation in the value ■of the lot caused by the change in the grade of the street. The sole claim .of the. plaintiff was that the wall, as built, was actually located over tbe lot line so that the.bottom of it stood in part upon his land, and that the wall itself, as built, bulged over his land so as to occupy ■some portion.of it and practically deprive him of the use of the land ■over which the .wall, projected. His claim was that the wall was thus located by the direction of the city officials, and that the bulging •of it came about solely because of the manner in which it was built and the poor materials which were put into it, and that the city was responsible for this because it practically had the control and direction of the manner and material of which the. wall was built. Unless [138]*138the .plaintiff was right in that contention, it is clear that, upon the law, he was not entitled to. recover.

■'Whenever a municipal corporation employs an independent contractor to do work which is proper in itself, and which does not-necessarily result in damage to property adjoining the place where the work is done, it is not liable for damages which accrue because of the- fact that the work-was done in a negligent manner or-with improper material's. In such-a case the rule is. well settled that, to-make the city liable it must have retained, by its contract, the power to direct and control the manner of -performing the work in which, the carelessness occurred and which caused the damage.. (Vogel v. Mayor, etc., 92 N. Y. 10, 18, per Earl, J.; City of Chicago v. Joney, 60 Ill. 383, 387; Charlock v. Freel, 125 N. Y. 357, 360 ; City of Cincinnati v. Stone, 5 Ohio St. 38 ; City of St. Patti v. Seitz, 3 Minn. 297.) The liability in such a case arises from the fact that the control which the city retains the right to exercise gives to it the power to-, see -that, the work is properly performed and that lione but proper-materials are used in it; and to that extent, the contractor, although nominally an .independent contractor, is, in fact, the servant of the city and under its control, and, therefore, it is responsible for in juries done by him which it might have prevented, .precisely as it would be for the same results caused by any other servant. This was- the theory upon which.the case was submitted to the jury by the learned judge,, and the jury were instructed that the city was only liable if the line, of the wall was incorrectly located by it, and the wall was directed to be* built upon the plaintiff’s property, or if" the plans and specifications-, prepared hy the city were so imperfect that it was apparent to those familiar with the building of walls that when it was finished it was likely to bulge or shift; This instruction as to ¡the extent of the liability, of the'city was given at the request of its counsel, and it certainly cannot be objected! .to as being too broad. Upon the facts, there was no-doubt that the city did retain the right to specify, the place. where-the wall should he built and the manner of .its construction. It was-ex.pi;essly,.prowided ,in.,the-contraet. that.ilre.retamipg-walls.shorild.be built where they were indicated on the plan, or where they were directed by the engineer -to be built, and that the manner in which the walls shoulcl be built was to be determined by the engineer. It was further agreed in the contract that, during all the time while the-[139]*139work was in progress, the materials used in it should be subject to” the examination of the commissioner, of street improvement, and should be immediately removed if not satisfactory to him. It was proved upon the trial, by the evidence of the witnesses produced om the part of the city, that an inspector was present all the time the1 work was going on, and that he gave directions as to the stone-that was put in the wall. It was also proved, and not disputed, that the place where the wall was located was designated by the engineer employed by the city, and that the trench was dug and the wall was built precisely in the place where the city’s engineers directed it to be done. If, therefore, there was any encroachment upon the plaintiff’s premises, or the wall, when built, was not sufficient for the purpose for which it ivas intended, it is quite clear that, under the:, rule above cited, the city could not escape liability.

That the wall encroached upon the plaintiff’s premises, either because it was set over the line or because it bulged so far as ter overhang the plaintiff’s premises to a considerable extent, was proved beyond any question. The plaintiff testified that, when the trench was dug, a fence which had stood between his lot and the street was taken down, and the trench was dug several feet inside the line which the fence had occupied. But whether or not the fence had stood upon the correct line was not made to appear.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Belott v. State
45 Misc. 2d 1067 (New York State Court of Claims, 1965)
McGraw v. Selkis
157 Misc. 447 (New York Supreme Court, 1935)
Dietzel v. . City of New York
112 N.E. 720 (New York Court of Appeals, 1916)
Dietzel v. City of New York
170 A.D. 571 (Appellate Division of the Supreme Court of New York, 1915)
Mott v. Lewis
52 A.D. 558 (Appellate Division of the Supreme Court of New York, 1900)
Schumacher v. City of New York
40 A.D. 320 (Appellate Division of the Supreme Court of New York, 1899)
Welde v. New York & Harlem Railroad
28 A.D. 379 (Appellate Division of the Supreme Court of New York, 1898)
White v. Mayor of New York
15 A.D. 440 (Appellate Division of the Supreme Court of New York, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
14 A.D. 135, 43 N.Y.S. 447, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goldschmid-v-the-mayor-of-the-city-of-new-york-nyappdiv-1897.