MEMORANDUM OPINION AND ORDER
BOGUE, Senior District Judge.
Facts
On December 27, 1990, Golden Reward Mining Company filed a Complaint in three counts against the Jervis Webb Construction Company of Detroit, Michigan. The Complaint included counts in Negligence, Strict Liability, and Breach of Contract.
Initially, Webb delivered to Golden Reward — sometime in August 1989 — a mobile reclaimer, pursuant to the terms of a contract, to be used in Golden Reward’s heapleach mining process.
The reclaimer apparently was designed to perform spent-ore reclamation at a certain tonnage level, a level which Golden Reward alleges the reclaimer never reached. Golden Reward sought nearly identical damages under each count of the Complaint: economic loss and consequential damages. Because there was no personal injury — and because South Dakota does not recognize recovery of economic loss under theories of negligence and strict liability
— this Court on
April 19, 1991, dismissed at Summary Judgment Count I (Negligence) and Count II (Strict Liability) of Golden Reward’s Complaint. Golden Reward’s breach of contract claim is the only remaining theory of recovery.
Procedure
Following this Court’s order dismissing the first two counts of Golden Reward’s Complaint, Webb petitioned this Court to reconsider its decision to allow Golden Reward to proceed with the breach of contract claim (Count III). In short, Webb argues that Golden Reward cannot recover consequential damages because such damages are specifically prohibited under the terms and conditions of the contract.
Webb’s petition for reconsideration reactivates Webb’s earlier motion for summary judgment. Under Rule 56 of 'the Federal Rules of Civil Procedure, a movant is entitled to relief at summary judgment only if he can “show that there is no genuine issue as to any material fact and that [he] is entitled to judgment as a matter of law.”
Jane Doe A v. Special School Dist. of St. Louis County,
682 F.Supp. 451 (E.D.Mo. 1988), citing
Poller v. Columbia Broadcasting, Inc.,
368 U.S. 464, 82 S.Ct. 486, 7 L.Ed.2d 458 (1962).
In determining whether judgment should issue, the facts and inferences from those facts are viewed in the light most favorable to the nonmoving party and the burden is placed on the moving party to establish both the absence of a genuine issue of material fact and that such party is entitled to judgment as a matter of law. Fed. R.Civ.P. 56(c);
Matsushita Elec. Indus. Co. v. Zenith Radio Corp.,
475 U.S. 574, 106 S.Ct. 1348, 1356-57, 89 L.Ed.2d 538 (1986). Once the moving party has met this burden, the nonmoving party may not rest on the allegations in the pleadings, but by affidavit or other evidence must set forth specific facts showing that a genuine issue of material fact exists, this Court views the evidence presented based upon which party has the burden of proof within the underlying substantive law.
Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 106 S.Ct. 2505, 2513, 91 L.Ed.2d 202 (1986).
Recently, the Supreme Court noted that “summary judgment procedure is properly regarded not as a disfavored procedural shortcut, but rather as an integral part of the Federal Rules as a whole, which are designed to ‘secure the just, speedy, and inexpensive determination of every action.’ ”
Celotex Corp. v. Catrett,
477 U.S. 317, 327, 106 S.Ct. 2548, 2555, 91 L.Ed.2d 265 (1986). Therefore, the nonmoving party “must do more than show that there is some metaphysical doubt as to the material facts,”
Matsushita,
106 S.Ct. at 1356, and “[w]here the record as a whole could not lead a rational trier of fact to find for the nonmoving party, there is no ‘genuine issue for trial.’ ”
Id.
Decision
1.
Sufficient Evidence in the Record
Under South Dakota law, “consequential damages may be limited or excluded [by the warrantor] unless the limitation or exclusion is unconscionable.” S.D. Codified Laws Ann. § 57A-2-719(3).
Further
more, under § 57A-2-302(l),
the issue of uneonscionability is a matter of law to be determined by the trial court.
Johnson v. John Deere,
306 N.W.2d 231, 236 (S.D.1981). As a threshold procedural issue, however, each party must be given a reasonable opportunity to present evidence “as to [the contract’s] commercial setting, purpose and effect to aid the Court in making the determination.” § 57A-2-302(2).
Although this Court contemplated holding a formal hearing on the matter, such an approach is not required under § 57A-2-302(2). Each party must simply “be afforded a reasonable opportunity to present evidence.”
Herrick v. Monsanto Co.,
874 F.2d 594, 597 (8th Cir.1989). As the Eighth Circuit concluded, citing 2 R. Anderson,
Anderson on the Uniform Commercial Code
§ 2-302:95, at 476 (3d ed. 1982), “when all possible evidence is already in the record, a formal hearing on the issue of uneonscionability is unnecessary.”
Id.
This Court is convinced that each party has been given more than adequate opportunity to make its record on this issue. Webb started the volley with a motion for reconsideration directed specifically at the issues of uneonscionability and limitations on the recovery of consequential damages; Golden Reward responded with a resourceful argument proposing that consequential damages are recoverable in the absence of proof that excluding such [consequential] damages from the terms of the contract is unconscionable.
See Hartzell v. Justus Co., Inc.,
693 F.2d 770 (8th Cir.1982).
This Court then held a hearing on the issue of whether or not Golden Reward must' prove, as a matter of law, that limiting the recovery of consequential damages was unconscionable.
See Johnson,
306 N.W.2d at 238.
Free access — add to your briefcase to read the full text and ask questions with AI
MEMORANDUM OPINION AND ORDER
BOGUE, Senior District Judge.
Facts
On December 27, 1990, Golden Reward Mining Company filed a Complaint in three counts against the Jervis Webb Construction Company of Detroit, Michigan. The Complaint included counts in Negligence, Strict Liability, and Breach of Contract.
Initially, Webb delivered to Golden Reward — sometime in August 1989 — a mobile reclaimer, pursuant to the terms of a contract, to be used in Golden Reward’s heapleach mining process.
The reclaimer apparently was designed to perform spent-ore reclamation at a certain tonnage level, a level which Golden Reward alleges the reclaimer never reached. Golden Reward sought nearly identical damages under each count of the Complaint: economic loss and consequential damages. Because there was no personal injury — and because South Dakota does not recognize recovery of economic loss under theories of negligence and strict liability
— this Court on
April 19, 1991, dismissed at Summary Judgment Count I (Negligence) and Count II (Strict Liability) of Golden Reward’s Complaint. Golden Reward’s breach of contract claim is the only remaining theory of recovery.
Procedure
Following this Court’s order dismissing the first two counts of Golden Reward’s Complaint, Webb petitioned this Court to reconsider its decision to allow Golden Reward to proceed with the breach of contract claim (Count III). In short, Webb argues that Golden Reward cannot recover consequential damages because such damages are specifically prohibited under the terms and conditions of the contract.
Webb’s petition for reconsideration reactivates Webb’s earlier motion for summary judgment. Under Rule 56 of 'the Federal Rules of Civil Procedure, a movant is entitled to relief at summary judgment only if he can “show that there is no genuine issue as to any material fact and that [he] is entitled to judgment as a matter of law.”
Jane Doe A v. Special School Dist. of St. Louis County,
682 F.Supp. 451 (E.D.Mo. 1988), citing
Poller v. Columbia Broadcasting, Inc.,
368 U.S. 464, 82 S.Ct. 486, 7 L.Ed.2d 458 (1962).
In determining whether judgment should issue, the facts and inferences from those facts are viewed in the light most favorable to the nonmoving party and the burden is placed on the moving party to establish both the absence of a genuine issue of material fact and that such party is entitled to judgment as a matter of law. Fed. R.Civ.P. 56(c);
Matsushita Elec. Indus. Co. v. Zenith Radio Corp.,
475 U.S. 574, 106 S.Ct. 1348, 1356-57, 89 L.Ed.2d 538 (1986). Once the moving party has met this burden, the nonmoving party may not rest on the allegations in the pleadings, but by affidavit or other evidence must set forth specific facts showing that a genuine issue of material fact exists, this Court views the evidence presented based upon which party has the burden of proof within the underlying substantive law.
Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 106 S.Ct. 2505, 2513, 91 L.Ed.2d 202 (1986).
Recently, the Supreme Court noted that “summary judgment procedure is properly regarded not as a disfavored procedural shortcut, but rather as an integral part of the Federal Rules as a whole, which are designed to ‘secure the just, speedy, and inexpensive determination of every action.’ ”
Celotex Corp. v. Catrett,
477 U.S. 317, 327, 106 S.Ct. 2548, 2555, 91 L.Ed.2d 265 (1986). Therefore, the nonmoving party “must do more than show that there is some metaphysical doubt as to the material facts,”
Matsushita,
106 S.Ct. at 1356, and “[w]here the record as a whole could not lead a rational trier of fact to find for the nonmoving party, there is no ‘genuine issue for trial.’ ”
Id.
Decision
1.
Sufficient Evidence in the Record
Under South Dakota law, “consequential damages may be limited or excluded [by the warrantor] unless the limitation or exclusion is unconscionable.” S.D. Codified Laws Ann. § 57A-2-719(3).
Further
more, under § 57A-2-302(l),
the issue of uneonscionability is a matter of law to be determined by the trial court.
Johnson v. John Deere,
306 N.W.2d 231, 236 (S.D.1981). As a threshold procedural issue, however, each party must be given a reasonable opportunity to present evidence “as to [the contract’s] commercial setting, purpose and effect to aid the Court in making the determination.” § 57A-2-302(2).
Although this Court contemplated holding a formal hearing on the matter, such an approach is not required under § 57A-2-302(2). Each party must simply “be afforded a reasonable opportunity to present evidence.”
Herrick v. Monsanto Co.,
874 F.2d 594, 597 (8th Cir.1989). As the Eighth Circuit concluded, citing 2 R. Anderson,
Anderson on the Uniform Commercial Code
§ 2-302:95, at 476 (3d ed. 1982), “when all possible evidence is already in the record, a formal hearing on the issue of uneonscionability is unnecessary.”
Id.
This Court is convinced that each party has been given more than adequate opportunity to make its record on this issue. Webb started the volley with a motion for reconsideration directed specifically at the issues of uneonscionability and limitations on the recovery of consequential damages; Golden Reward responded with a resourceful argument proposing that consequential damages are recoverable in the absence of proof that excluding such [consequential] damages from the terms of the contract is unconscionable.
See Hartzell v. Justus Co., Inc.,
693 F.2d 770 (8th Cir.1982).
This Court then held a hearing on the issue of whether or not Golden Reward must' prove, as a matter of law, that limiting the recovery of consequential damages was unconscionable.
See Johnson,
306 N.W.2d at 238. At that hearing, each party discussed the genesis of the contract negotiations; the negotiations involved in reaching an agreement; the problems which ultimately arose; and Webb’s response to the alleged untimely and frequent breakdowns of the reclaimer. Finally, this Court ordered Golden Reward and Webb to brief thoroughly four (4) separate issues related to consequential damages and uneonscionability in light of the facts of this case.
See
Order, dated July 29, 1991. In response, each party filed both an initial brief and a response brief. Thus, both parties have provided this Court with enough evidence to ensure that neither party will be prejudiced in the absence of a hearing.
2.
Unconscionability and Consequential Damages
This Court is presented with a single issue: Is the clause in the contract between Golden Reward and Webb Construction Co. which, in the event of breach, prohibits Golden Reward from recovering consequential damages, unconscionable as a matter of law? Given the commercial nature of the parties and the circumstances surrounding creation of the contract, this Court finds that the clause prohibiting recovery of consequential damages is not unconscionable.
Resolution of this issue turns on the analysis of two sections of South Dakota’s version of the Uniform Commercial Code, namely SDCL 57A-2-802,
and SDCL 57A-2-719
. Thus, once a remedy provision within a contract “fail[s] of its essential purpose, [extra-contractual] remed[ies] may be had as provided in this title.”
See
§ 57A-2-719(2). The aggrieved party must prove, however, that the limitation on recovery of consequential damages [contained in the contract] is unconscionable before recovery of consequential damages is allowed.
As (3) [of § 57A-2-719] provides, “consequential damages may be limited or excluded unless the limitation or exclusion is unconscionable.”
See
2-719(3).
By the terms of the contract, Golden Reward and Webb established that:
(1) The “repair and replacement” remedy provided in the agreement is the exclusive remedy.
See
Contract, and section 57A-2-719(l)(b).
(2) Consequential damages are excluded.
Several issues are worth noting for purposes of clarification. First, we are discussing two separate, but necessarily related, legal issues. On the one hand, the contract [between Webb and Golden Reward] contains a provision which states, in effect, that the exclusive remedy available in the event of breach by Webb is “repair or replacement” of the defective component. In other words, if the reclaimer breaks down, Webb will fix it. Under South Dakota law, such a provision is entirely proper. As section 57A-2-719(l)(a) provides: “The agreement may provide for remedies in addition to or in substitution for those provided in this chapter and
may limit or alter the measure of damages recoverable under this chapter, as payment of the price or to repair and replacement of nonconforming goods or parts.”
[emphasis added].
Second, not only does the contract contain an “exclusive remedy” provision, it also contains a “limitation of remedy” provision which prohibits recovery of consequential damages. This provision, like the “exclusive remedy” provision, is also proper under South Dakota law. As § 57A-2-719(3) states, “[consequential damages may be limited or excluded unless the limitation or exclusion is unconscionable.” Thus, the real issue is not whether the “repair or replace” provision is (or was) unconscionable at the time the contract was created, but whether limiting consequential damages (and, in effect, limiting the scope of potential damages) was unconscionable at the time of the creation of the contract.
See Johnson,
306 N.W.2d at 237-38.
As the South Dakota Supreme Court reasoned, separating these issues is important:
Thus, although the repair and replacement warranty may have subsequently failed of its essential purpose, thereby entitling him to general damages for breach of contract as outlined in the code, the limitation on remedy was not unconscionable at the time the contract was made, either procedurally or substantively, and he would not be entitled to recover consequential damages.
Johnson,
306 N.W.2d at 238.
The “exclusive remedy” provision relates to whether or not the remedy provision provided in the contract failed of its essential purpose, and that is a fact issue for the jury.
See Johnson,
306 N.W.2d at 237. The issue of whether or not the limitation on remedies [excluding consequential damages] is unconscionable is a question of law to be decided by the Court.
Id.
at 237-38. As the high court concluded, “[failure of the warranty to fulfill its purpose is necessarily determined by circumstances occurring after the contract is made, whereas unconscionability is to be determined as of the making of the contract.”
Id.
at 238.
Furthermore, the South Dakota Supreme Court concluded, as have most courts and commentators
[see
White
&
Summers,
Uniform Commercial Code,
472-75, 2d ed. 1980], that “unconscionability” is much different when a commercial party is involved, as opposed to a lay consumer.
“As we have previously noted, the courts are much more inclined to sustain [a finding of unconscionability] in the case of the downtrodden consumer than they are in the case of the commercial consumer who presumably has a far more meaningful choice.”
Johnson,
306 N.W.2d at 238.
Golden Reward is neither a downtrodden consumer nor a small business suffering the ill effects of an adhesion contract.
Before an agreement was reached, Bate-man Engineering
and Webb communicated with each other regarding proposed changes in the contract. Some of Webb’s demands were met, others were not. Eventually, however, a contract was completed to which both parties agreed.
The Ninth Circuit, in
Milgard Tempering, Inc. v. Selas Corp. of Am.,
902 F.2d 70S (9th Cir.1990), addressed the fundamental problem Courts face when tempted to interfere with negotiated business transactions which have gone sour:
Parties of relatively equal bargaining power negotiated an allocation of their risks of loss. Consequential damages were assigned to the buyer, Wilson. The machine was a complex piece of equipment designed for the buyer’s purposes. The seller Smith did not ignore his obligation to repair, he simply was unable to perform it. This is not enough to require that the seller absorb losses the buyer plainly agreed to bear. Risk shifting is socially expensive and should not be undertaken in the absence of a good reason. An even better reason is required when to so shift is contrary to a contract freely negotiated. The default of the seller is not so total and fundamental as to require that its consequential damage limitation be expunged from the contract.
Id.
at 708, citing
S.M. Wilson & Co. v. Smith Int’l., Inc.
587 F.2d 1363, 1375 (9th Cir.1978).
The Ninth Circuit, in
Milgard,
went on to reason that the phrase “total and fundamental [default]” is not magical. The real issue is whether the breach by Webb caused a loss which was not part of the bargained-for allocation of risk.
Id.
at 709.
With that in mind, Golden Reward provided arguments which are both resourceful and creative. This Court cannot imagine, however, that Golden Reward, as it contemplated the venture upon which it was about to embark, did not fully understand that a limitation on recovery of consequential damages was a necessary prerequisite to participation in the contract. Certainly, Webb would not consider build
ing this reclaimer if the reclaimer’s potential breakdown might ultimately generate liability [for Webb] for an incalculable amount of gold.
Both parties realized, at the time of negotiations, that this was a prototypical machine, designed and built to achieve a production result heretofore unknown to both parties. No doubt, Golden Reward realized that to encourage successfully Webb’s participation in this project, the fear of consequential damages in a volatile precious metals market must be removed. By the same token, Webb demanded only a warranty which encouraged innovation — without the fear of financial paralysis if projected, but yet untested, production goals were not met. A contract, under these circumstances, which omits a clause prohibiting the recovery of consequential damages would, perhaps, be more of a surprise than, one which did not.
Golden Reward argues that the end result of the reclaimer’s breakdown leaves Golden Reward with no remedy. This is not true. Golden Reward is still entitled to seek all other damage remedies available in •the code.
CONCLUSION
Golden Reward and Webb Construction are large commercial entities which negotiated for the purchase of the subject reclaimer at arms length.
When the contract excluded recovery for consequential damages, both parties were aware of what this meant in the context of their agreement. The end result is no more or less oppressive than the parties perceived it to be. This Court will not interfere with what is simply a bargained-for allocation of risk.
The trilogy of
Celotex, Anderson,
and
Matsushita
provide this Court with a methodology for analyzing Defendant’s motion for summary judgment. Under this trilogy, it is incumbent upon Plaintiffs, based upon the showing set forth by Defendant, to come forward with specific facts demonstrating that there is a genuine issue in order to counter Defendant’s summary judgment motion.
Cf Women’s Health of W. County v. Webster,
871 F.2d 1377, 1383 n. 9 (8th Cir.1989). Plaintiffs have failed to meet this burden. Therefore, there being good cause appearing, it is hereby
ORDERED that Defendant’s motion to dismiss Plaintiffs’ claim for consequential damages within Count III (Breach of Contract) of Plaintiffs’ Complaint is granted.
IT IS FURTHER ORDERED that this order has no force and effect as to Golden Reward’s claim for general damages under Count III (Breach of Contract) of the complaint.