Goldauskas v. Elyria Foundry Co.

763 N.E.2d 645, 145 Ohio App. 3d 490, 2001 Ohio App. LEXIS 3665
CourtOhio Court of Appeals
DecidedAugust 22, 2001
DocketC.A. No. 00CA007744.
StatusPublished
Cited by6 cases

This text of 763 N.E.2d 645 (Goldauskas v. Elyria Foundry Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goldauskas v. Elyria Foundry Co., 763 N.E.2d 645, 145 Ohio App. 3d 490, 2001 Ohio App. LEXIS 3665 (Ohio Ct. App. 2001).

Opinions

Batchelder, Presiding Judge.

Appellants, Peter and his wife Tanya Goldauskas and the law firm of Berger & Zavesky Co., L.P.A., 1 appeal the judgment of the Lorain County Court of Common Pleas. We modify the trial court’s judgment.

I

In 1995, Mr. Goldauskas began working at the Elyria Foundry Company, Incorporated, appellee, a metal foundry and casting plant. His job involved pulling casings out of the foundry pit, breaking apart molds, and loading the castings for shipment. The castings and molds were often tall, and, therefore, were often placed in a deep pit in the foundry. In order to accomplish his job, Mr. Goldauskas was required to attach a chain from a crane to the top of the mold or casting. The only way to access the top of the molds was, apparently, by riding the chains of the cranes, as no ladders were provided. On June 30, 1998, Mr. Goldauskas was, apparently, instructed to ride the chain to the top of a twenty-five-foot-tall casting flask so that he could disassemble it. However, the crane malfunctioned and did not stop lifting at the appropriate time; rather, it lifted Mr. Goldauskas higher and higher. Finally, the crane reached its limit switch, which sheared off a pin and sent Mr. Goldauskas and the chains on which he was riding plummeting to the floor, some thirty feet below. Momentarily, Mr. Goldauskas landed atop the mold onto which he was planning to attach the chain that he had been riding. However, he was knocked off the mold by falling debris. Mr. Goldauskas was injured as he fell from the top of the mold, landing upon the concrete floor far below. At that point, a block broke free from the crane and plummeted to the ground. It landed atop Mr. Goldauskas’s leg, severing it from his body. An ambulance was immediately summoned; however, despite medical care, Mr. Goldauskas’ leg had to be amputated.

*493 Mr. Goldauskas retained Friedman, Domiano & Smith Co., L.P.A. (“the Friedman firm”) on or about July 2, 1998, as counsel to pursue an action in tort against Elyria Foundry for the injuries that he had suffered in his fall. The Friedman firm filed a complaint on his behalf in the Lorain County Court of Common Pleas on December 4,1998. The firm filed interrogatories and requests for the production of documents on the same day. The Friedman firm pursued discovery in the following months. Depositions were taken of Lowell Morrow, a supervisor in the area in which Mr. Goldauskas worked and witness to the accident, Floyd Baum, vice-president of Elyria Foundry, Tod Blair, safety manger at Elyria Foundry, and Duane Warner, night shift supervisor for shakeout, 2 among other depositions and interviews.

Mr. Goldauskas then terminated his relationship with the Friedman firm and retained Berger & Zavesky Co., L.P.A. (“the Berger firm”) in November 1999. The Berger firm continued the discovery process, moving for additional time to produce expert reports on November 24,1999. The trial court granted additional time on December 2, 1999. On May 5, 2000, Elyria Foundry moved for summary judgment. The Berger firm filed its brief in opposition to summary judgment on May 31, 2000, and attached numerous depositions and expert reports. A number of these documents were produced in part or in toto through the efforts of the Berger firm, after the Friedman firm had been discharged. Among these was that of Richard E. Harkness, who prepared an expert report detailing the causal chain leading up to the accident, Gerald C. Rennell, who provided an expert report on the safety conditions and procedures at Elyria Foundry, Scott Sham-blin, a crane operator at Elyria Foundry, Rodney Coker, a crane operator at Elyria Foundry, and Jeff Lauren, an employee at Elyria Foundry. However, the Berger firm also used the deposition of Tod Blair, safety manager at Elyria Foundry, the deposition of Greg Fretch, a night supervisor at Elyria Foundry, which had been produced solely through the efforts of the Friedman firm, and a discovery deposition taken by Elyria Foundry during Mr. Goldauskas’s representation by the Friedman firm. Further, Harkness and Rennell had both been originally retained by the Friedman firm, and, hence, had begun work on their reports prior to the Friedman firm’s dismissal and the Berger firm’s entry into the case. The motion for summary judgment was not ruled upon, however, as the Berger firm settled Mr. Goldauskas’s claim for a sealed 3 amount prior to the *494 trial court’s ruling. The trial court was notified of the settlement on June 13, 2000.

In a conference between Domiano of the Friedman firm and Zavesky of the Berger firm, Mr. Domiano “asked [Zavesky] if [he] would protect [the Friedman firm’s] interest, and [Zavesky] told [Domiano] that [he] would, and [Zavesky] asked [Domiano] to please send [Zavesky] a letter.” Later, on March 16, 2000, the Friedman firm sent a letter to the Berger firm stating that “[m]y firm is seeking to recover $25,077.33 [in] quantum meruit.” Further, on March 31, 2000, the Friedman firm mailed the Berger firm a document entitled “Notice of Charging Lien” in regard to the services rendered by the Friedman firm. On June 30, 2000, the Friedman firm filed a motion to declare and enforce the charging lien on the settlement proceeds and documents in support of the motion in the Lorain County Court of Common Pleas. The Berger firm filed a brief and exhibits in opposition on July 7, 2000. Numerous depositions were taken and discovery was had. On August 10, 2000, Mr. Goldauskas and Elyria Foundry filed a motion to dismiss the cause between them with prejudice. The trial court dismissed the cause between those parties on August 14, 2000. The matter of the division of attorney fees was heard by the trial court on, inter alia, October 26, 2000 and November 22, 2000. On December 1, 2000, the trial court entered judgment in favor of the Friedman firm in the amount of three hundred thousand dollars, fees and costs inclusive, with the balance of the contingency fee going to the Berger firm. This appeal followed.

II

The Berger firm asserts three assignments of error. We will address each in due course, consolidating the Berger firm’s first two assignments of error to facilitate review.

A

First Assignment of Error

“The trial court erred by not estopping the Friedman firm from claiming an amount of quantum meruit in excess of the agreed upon fee.”

Second Assignment of Error

“The trial court erred in denying appellants[’] motion for a directed verdict.”

The Berger firm avers that the trial court erred in that its decision was contrary to the evidence presented and applicable law. Essentially, the Berger firm argues that the Friedman firm was estopped from demanding more than the amount stated in its March 16, 2000 letter and that the trial court abused its *495 discretion in awarding the Friedman firm $300,000 in attorney fees. We find that the Friedman firm was not estopped, but agree that the trial court acted unreasonably in determining the fee in quantum meruit and modify its holding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dickson & Campbell, L.L.C. v. Marshall
2017 Ohio 1032 (Ohio Court of Appeals, 2017)
Doellman v. Midfirst Credit Union, Ca2006-06-074 (11-5-2007)
2007 Ohio 5902 (Ohio Court of Appeals, 2007)
In Re J.F.
834 N.E.2d 876 (Ohio Court of Appeals, 2005)
Rust v. Harris-Gordon, Unpublished Decision (3-31-2004)
2004 Ohio 1636 (Ohio Court of Appeals, 2004)
Mark-It Place Foods, Inc. v. New Plan Excel Realty Trust, Inc.
804 N.E.2d 979 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
763 N.E.2d 645, 145 Ohio App. 3d 490, 2001 Ohio App. LEXIS 3665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goldauskas-v-elyria-foundry-co-ohioctapp-2001.