Gold Ridge Mining Co. v. Tallmadge

74 P. 325, 44 Or. 34, 1903 Ore. LEXIS 7
Oregon Supreme Court·Decided November 23, 1903·Published·Cited by 13 cases

Opinion

Mr. Justice Bean

delivered the opinion.

The plaintiff corporation is the owner of a placer mine on Thorn Gulch, near Sparta, in Baker County. The defendant F. W. Tallmadge owns a mine at the head of the gulch above the plaintiff’s. He is also the owner of a water right and ditch known as the “ Sparta Ditch,” through which water is conveyed from Eagle Creek to a point above, but near, the Town of Sparta. Between the Sparta ditch and the head of Thorn Gulch is a low depression, owing to which water from the ditch could not be used for mining purposes on Thorn Gulch at the time the contract in controversy was made. In July, 1897, the plaintiff sought to obtain water from defendant F. W. Tallmadge for use at its mine, and applied to him to extend his ditch so as to supply it with water; but, as he did not have funds available for this purpose, a written contract was entered into between him and the plaintiff, wherein the latter agreed to furnish all the labor, money, and material necessary to lay a sixteen inch steel pipe line from a point at or near the reservoir on defendant’s ditch across the low land to the opposite ridge of hills near the head of Thorn Gulch, a distance of 3,650 feet, and in payment therefor the defendant agreed “to deliver there, through and by such appliances as he may adopt, at least two hundred full miner’s inches of first or second water to and at the placer mines of” the plaintiff, “and to maintain said supply of water at said point continuously so long as water will flow in said ditch,” until the plaintiff should be fully repaid in water for the cost and expense of constructing such pipe line at the rate of $20 a day for each day of 24 hours.' The [38] plaintiff complied with all the terms of the contract on its part, and put in the pipe line at a cost of $2,942.97, and soon thereafter filed a lien on the Sparta Ditch, its feeders, laterals, reservoirs, and appurtenances, to secure the payment of the amount so expended. After the completion of the pipe line the defendant turned into it from his ditch water which he used in mining his own ground at the head of the gulch, and then allowed the quantity which he agreed to furnish the plaintiff to flow down the natural channel of the gulch to the mine of the plaintiff without being slummed or the tailings removed therefrom, and so loaded with sand, mud, and débris as to be useless for mining purposes.

Farlaman, who was the manager of the plaintiff company from July to November, 1897, testified that the water as it came down to the plaintiff from the defendant’s mine was filled with mud, sand, and gravel just as it came from the mine and was of very little use to the plaintiff; that it filled the plaintiff’s reservoirs and ditch so full that they were of no use at all; that it kept two or three men busy all the time shoveling the sand from the ditch; that the water was two-thirds sand; that he spoke to the defendant about it several times, and he promised to remove the trouble, but never did; that, as delivered, the water was of no value to the plaintiff. Banfield, who was superintendent for the plaintiff in 1898, and in charge of its mine, says that during that season the water was delivered during the first week clean, but after that it was used by the defendant, and the tailings and débris from his mine were carried down to plaintiff’s to such an extent that it would fill the ditches so that the water ran out over the ground instead of down the ditches; that it also filled the sluice boxes and penstock, and cut the giant to pieces. George G. Sears, president of the plaintiff company, testified that the water as it came down to plaintiff’s mine was about [39] one-half débris, and of such a character that it could not be used through the pipe; that all the tailings and wash from the 'defendant’s mine came down with the water; that the plaintiff could not use the water for any purpose; that it took two-thirds of the time of plaintiff’s employés to keep the mine clean, and because of the condition of the water the plaintiff could not mine at all; that plaintiff had been to considerable expense in preparing to use the water, and did not get any substantial benefit from its use. Colonel Drake, a member of the plaintiff company, says that the water as it came down from the defendant’s mine was loaded with a sort of granite or quicksand; that it came down heavily charged with such material from the workings above; that it was hard to describe the material, but it would roll right along with the water, and fill the ditches and tail-races very readily; that it was the débris and tailings from the defendant’s mine that came down with the water, and that it was not possible to mine with the water in its then condition; that plaintiff was not able to make a clean-up with the water. Mr. Morrill says that he was on the mining ground the season of 1897, while Farlaman was in charge ; that the water which the plaintiff was trying to use could hardly be called Avater; that it might more properly be called granite sand mixed with water.

Free access — add to your briefcase to read the full text and ask questions with AI

Gold Ridge Mining Co. v. Tallmadge, 74 P. 325, 44 Or. 34, 1903 Ore. LEXIS 7 (Or. 1903).

74 P. 325 (Gold Ridge Mining Co. v. Tallmadge) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McHutchinson & Co. v. Snow
28 Pa. D. & C. 693 (Delaware County Court of Common Pleas, 1936)
G. M. C. Truck Co. v. Kelley
1924 OK 1132 (Supreme Court of Oklahoma, 1924)
McCargar v. Wiley
229 P. 665 (Oregon Supreme Court, 1924)
Durbin v. Denham
210 P. 165 (Oregon Supreme Court, 1922)
Patterson v. Orangeburg Fertilizer Co.
108 S.E. 401 (Supreme Court of South Carolina, 1921)
Skalsky v. Johnson
164 N.W. 978 (Supreme Court of Minnesota, 1917)
Swank v. Battaglia
164 P. 705 (Oregon Supreme Court, 1917)
Bouchet v. Oregon Motor Car Co.
152 P. 888 (Oregon Supreme Court, 1915)
Standard Sewing MacH. Co. v. New State Shirt & Overall Mfg. Co.
1914 OK 239 (Supreme Court of Oklahoma, 1914)
Walrus Mfg. Co. v. McMehen
1913 OK 676 (Supreme Court of Oklahoma, 1913)
Kitchin v. Oregon Nursery Co.
130 P. 408 (Oregon Supreme Court, 1913)
Mine Supply Co. v. Columbia Mining Co.
86 P. 798 (Oregon Supreme Court, 1906)
Lenz v. Blake
76 P. 356 (Oregon Supreme Court, 1904)