Gold Kist, Inc. v. Base Manufacturing, Inc.

658 S.E.2d 228, 289 Ga. App. 690, 2008 Fulton County D. Rep. 595, 2008 Ga. App. LEXIS 181
CourtCourt of Appeals of Georgia
DecidedFebruary 21, 2008
DocketA07A1944, A07A1945
StatusPublished
Cited by3 cases

This text of 658 S.E.2d 228 (Gold Kist, Inc. v. Base Manufacturing, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gold Kist, Inc. v. Base Manufacturing, Inc., 658 S.E.2d 228, 289 Ga. App. 690, 2008 Fulton County D. Rep. 595, 2008 Ga. App. LEXIS 181 (Ga. Ct. App. 2008).

Opinion

Ruffin, Judge.

Gold Kist, Inc. (“Gold Kist”) sued Base Manufacturing, Inc. (“Base”), asserting claims for breach of contract, negligence, fraud, *691 and punitive damages. Following trial, a jury found in favor of Gold Kist and awarded damages against Base on the breach of contract and negligent design claims. Gold Kist appeals in Case No. A07A1944, alleging that the jury’s award of damages was inadequate. Base cross-appeals in Case No. A07A1945, contending that the trial court erred in denying its motion for directed verdict as to Gold Kist’s claims for fraud and punitive damages. For reasons that follow, we affirm the judgment in Case No. A07A1944 and dismiss as moot the cross-appeal in Case No. A07A1945.

Construed in favor of the verdict, 1 the evidence shows that Gold Kist and Base entered into contracts in which Base agreed to supply metal storage rack systems for Gold Kist’s chicken processing facilities in Alabama and South Carolina. Under the contracts, Base agreed to provide the racks according to Gold Kist’s specifications and warranted that they would be free from defects; upon breach of the warranties, Base agreed to correct the problem or to pay for a replacement rack(s).

Thereafter, one of the racks at the South Carolina facility collapsed, and Gold Kist investigated and determined that the racks at both facilities were improperly designed, manufactured, and installed. 2 Thus, Gold Kist filed a breach of contract action against Base and later amended the complaint to add claims for negligence, fraud, and punitive damages. After Gold Kist rested, Base moved for a directed verdict as to fraud and punitive damages, but the trial court denied the motion. The jury found in favor of Gold Kist as to its claims for breach of contract and “negligent design, construction, or installation” as to the racks for both the South Carolina and Alabama facilities. However, the jury found in favor of Base as to Gold Kist’s claims for negligent misrepresentation, fraud, attorney fees, prejudgment interest, and punitive damages. The damages awarded were significantly less than the amounts Gold Kist sought at trial. 3 Gold Kist moved for a new trial as to damages only, contending that the jury’s award was not supported by the evidence, and the trial court denied the motion.

*692 Case No. A07A1944

1. Gold Kist contends that the jury’s damages award was not supported by the evidence and, thus, the trial court erred in entering judgment based upon the verdict. We disagree.

With the consent of the parties, the trial court submitted a special verdict form to the jury which required it to allocate damages for certain claims. With regard to the South Carolina facility — where the rack actually collapsed — the jury awarded damages to Gold Kist for breach of contract in the sum of $250,979.96, with the following allocations: rack; freezer rack labels; base rack demolition; consulting fees; outside storage; freight to and from outside storage; rack collapse cleanup; damaged product; labor to rework damaged product; and temporary accounting costs. 4 With regard to the Alabama facility, the jury awarded damages to Gold Kist for breach of contract in the sum of $383,159.68, with the following allocations: $0 for Interlake rack, installation, freight, tax, and consulting fees; $78,750 for base rack demolition; $58,100 for freight to move food; $161,846.28 for outside cold storage; and $84,463.40 for “other.”

Under the terms of the parties’ contracts, Gold Kist was entitled to recover all costs resulting from Base’s breach, including the replacement of the faulty racks. Gold Kist maintains that — with the exception of the cost of the replacement racks — Base failed to present any evidence or to dispute the evidence presented by Gold Kist for the aforementioned categories. Thus, Gold Kist contends, the jury’s award is not supported by and is contrary to the undisputed evidence.

“[A]n excessive or inadequate verdict is a mistake of fact rather than of law and addresses itself to the discretion of the trial judge who, like the jury, saw the witnesses and heard the testimony.” 5 Although this Court may set aside an inadequate verdict under OCGA § 51-12-12 (a), the threshold is extremely high. 6 Generally,

the jury’s award cannot be successfully attacked so as to warrant a new trial unless it is so flagrantly excessive or inadequate, in light of the evidence, as to create a clear implication of bias, prejudice or gross mistake on the part of the jurors. Even though the evidence is such as to authorize a greater or lesser award than that actually made, the appellate court will not disturb it unless it is so flagrant as to shock the conscience. Moreover, the trial court’s approval *693 of the verdict creates a presumption of correctness that will not be disturbed absent compelling evidence. 7

Gold East essentially argues that the jury was required to return a verdict in the precise amounts proven at trial. But the law provides no support for this position. 8 “ ‘Indeed, we have often upheld jury verdicts that awarded less than the amount proven at trial, holding only that the amount must be within the range of damages shown.’ ” 9

A jury is not obligated to accept a witness’s testimony even when it is uncontradicted. 10 Thus, the jury was not required to conclude that Gold East’s proposed damage amounts constituted the precise measure of damages. Moreover, as the jury was properly instructed— with no objection from Gold East — that

[wjhere a contract is breached[,] damages are given as compensation for injuries sustained. ... If you find the defendants breached the contract with the plaintiff[,] then the plaintiff is entitled to recover such damages as arise naturally and according to the usual course of things from the breach and such as the parties contemplated when the contract was made as the probable result of the breach. 11

Thus, the jury was authorized to award only those damages it determined flowed directly from the breach. 12 The jury was also charged — again without objection from Gold East — that Gold Kist had a duty “to lessen [its] damages as far as is practicable by the use of ordinary care.”

There was evidence presented that the South Carolina rack sustained damage as a result of forklift strikes, which the jury might have concluded did not flow directly from the breach. And one of Gold *694

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JOAN ELIZABETH GEE v. TYLER & COMPANY, LLC
Court of Appeals of Georgia, 2024
Wright v. Apartment Investment & Management Co.
726 S.E.2d 779 (Court of Appeals of Georgia, 2012)
Turner Broadcasting System, Inc. v. McDavid
693 S.E.2d 873 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
658 S.E.2d 228, 289 Ga. App. 690, 2008 Fulton County D. Rep. 595, 2008 Ga. App. LEXIS 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gold-kist-inc-v-base-manufacturing-inc-gactapp-2008.