Goff v. United States Fidelity & Guaranty Co.

51 A.2d 558, 72 R.I. 363, 1947 R.I. LEXIS 15
CourtSupreme Court of Rhode Island
DecidedMarch 14, 1947
StatusPublished
Cited by2 cases

This text of 51 A.2d 558 (Goff v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goff v. United States Fidelity & Guaranty Co., 51 A.2d 558, 72 R.I. 363, 1947 R.I. LEXIS 15 (R.I. 1947).

Opinion

*364 Flynn, C. J.

This is a bill in equity for an accounting. The complainant is the assignee of a building contractor under the latter’s general assignment for the benefit of creditors. The respondents are the owner of the building, which the contractor was to construct according to a contract, and the surety on the contractor’s bond. The surety, by virtue of *365 the contractor’s agreement to indemnify it against loss arising out of its obligations under the bond, was also an assignee of all the rights, moneys and property of the contractor that were due under, or related to, the building contract. After a hearing in the superior court on bill, answers, replication and proof, a decree was entered denying and dismissing the bill as against the owner but ordering an account to be filed within thirty days by the surety. From this decree the complainant took no appeal, and the cause is before this court on the single appeal of the respondent surety company.

From the bill of complaint and the evidence the following facts appear. Omer Lavigne and Simeon Lavigne, copartners doing business as O. & S. Lavigne Co., called the contractor, entered into an agreement, dated September 12, 1930, with Saint "Vincent de Paul Infant Asylum, a Rhode Island corporation, herein called the owner. The contractor thereby agreed to furnish all materials and labor and to build, in accordance with the specifications and provisions of the contract, a three story and basement brick addition to certain premises of the owner. The contract contained many provisions, which we need not state in full, and called for payment by the owner to the contractor of a total sum of $122,900. Provision was made for payments to the contractor, as the work progressed, in accordance with certain specifications which were in the contract and which included certification by the architect, and also the owner’s right to retain, until the completion of the contract and for the purpose of indemnifying it against claims and loss, 15% of all amounts due from time to time under the contract.

On the same date, September 12, 1930, the contractor as principal and the respondent surety company as surety executed and delivered to the owner a common-law form of indemnity bond which is conditioned upon the full performance of the contract in accordance with its terms and provisions. Such bond was in the penal sum of $61,450 and, immediately following the condition therein, contained the *366 provision: “It is, however, mutually understood between the parties hereto, That in no event shall the Surety bediable f’or a greater sum than the penalty of this bond, or subject to any suit, action or other proceeding thereon that is instituted later than the first day of July, A. D. 1932.”

Apparently on the same date, to indemnify the surety against loss arising out of its obligations under the bond, the contractor in writing assigned to the surety all the tools, equipment and materials on the job, or otherwise chargeable to said contract; all rights in and to all subcontracts; and all rights, properties and moneys, including deferred payments and retained percentages, then due or to become due to the contractor under the contract, such assignment to become effective upon any default by the contractor under the building contract. While this assignment to the surety purported to be absolute, it also expressly provided that the assigned rights, properties and moneys therein mentioned were “to be by it credited upon any loss, damage, charge and expense sustained or incurred by it as above set forth under its bond of suretyship.”

On June 1, 1931, after the work'had progressed to a degree not made clear in the evidence, the contractor became insolvent and made to the complainant Walter W. Goff a general assignment for the benefit of creditors. Notice of the contractor’s inability to carry out the contract was given to the owner and upon the complainant’s acknowledgment of the default thereunder and his abandonment thereof, completion of the work in accordance with the contract was taken over by the surety. Thereafter, by letter of July 7, 1931, the complainant formally notified the surety that he was holding the owner liable for the amounts of money due for work and labor performed and for materials furnished on the job by certain subcontractors and materialmen prior to the contractor’s default and for which complainant held releases of their claims.

On July 11, 1931, the complainant reaffirmed this notice and claim. By letter of that date to the surety he set forth *367 the particular materialmen and subcontractors and the specific amounts due each for which the complainant stated that he held corresponding releases in the total amount of $16,654.47 and that he claimed the owner was liable for these sums to him as he was the assignee of the contractor for the benefit of the latter’s creditors. Later, on November 20, 1931, the complainant agreed that the surety might pay certain other claims of materialmen and subcontractors totaling $29,430.34, because they represented claims for material and labor furnished subsequently to the contractor’s default, or claims for which liens had not been released or waived.

The contract was completed by the surety, in accordance with the contract and bond, prior to July 1, 1932. The complainant admitted that he knew that the contract was completed but he testified that he did not know the exact date of its completion; and that he received no information from the owner or surety as to payments made by or to them in the course of completing the contract, or in finally adjusting certain controverted claims. He testified that he left a meeting in 1937, at which the surety was represented, under the belief that it was agreed that such information would be given to him when final adjustment was made by the surety with the owner; and that he had made no further inquiry for that reason. He testified that such information did not come to him until after the present bill in equity was brought in October, 1945 and that he did not have a specific knowledge of what payments were made by the owner to the surety or what credits were given to the contractor by the surety against its claim of loss sustained in completing the contract.

The respondents filed separate, though substantially identical, answers in which they admitted the contract and bond and also that there was an agreement between the contractor and surety in connection with indemnifying the latter against loss as alleged; but they neither admitted nor denied, and left complainant to prove, other pertinent paragraphs of the bill which involved his claims to retained percentages as allegedly demanded. They also added, by the ninth paragraph, *368 an allegation that the complainant was guilty of laches in waiting from 1932 to 1945 before taking any action or proceeding at law or in equity, and prayed that the bill be dismissed.

Following the trial justice’s decision a decree was entered: (1) Denying and dismissing the bill as against the respondent St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavanagh v. Bostitch, Inc.
162 A.2d 785 (Supreme Court of Rhode Island, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
51 A.2d 558, 72 R.I. 363, 1947 R.I. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goff-v-united-states-fidelity-guaranty-co-ri-1947.