Goetz v. Russell

232 P. 300, 132 Wash. 339, 1925 Wash. LEXIS 782
CourtWashington Supreme Court
DecidedJanuary 9, 1925
DocketNo. 18649. Department Two.
StatusPublished
Cited by4 cases

This text of 232 P. 300 (Goetz v. Russell) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goetz v. Russell, 232 P. 300, 132 Wash. 339, 1925 Wash. LEXIS 782 (Wash. 1925).

Opinion

Mitchell, J.

The board of public works of the city of Seattle called for bids for the construction of what was collectively known as the Lake Youngs Development, it being a part of additions and betterments to, and extensions of, the existing water system of the city, specified pnd adopted by ordinances of the city. Six bids were submitted, that of Jahn & Bressi being the lowest, and that of Goetz & Brennan, a corporation, being next to the lowest. Upon all of the bids being re *340 ferred to the engineering department for computation and report back to the board of public works, and before any other consideration of the bids was given by the board, Herman Goetz, in no way interested in the Goetz and Brennan corporation, as a taxpayer, and Goetz & Brennan, a corporation, commenced this action against the members of the board of public works and its secretary, as such, and against the mayor of the city, to restrain and enjoin the board of public works from giving consideration to the bid of, and from ordering or directing any contract with, Jahn & Bressi, and to restrain and enjoin the defendants and each of them from signing, executing or entering into any written agreement with Jahn & Bressi under their bid, because of the alleged insufficiency of the amount of the certified check accompanying their bid. A temporary restraining and show cause order was entered against and served on the defendants.

Prior to the hearing on the show cause order, Jahn & Bressi, by permission of the court, intervened in the action, uniting with the defendants in resisting the claims and demands of the plaintiffs. On the hearing of the show cause order, the cause was considered as upon a final hearing on the merits, by consent of all the parties. There can be no doubt that the bid of Jahn & Bressi was made in good faith, nor is there any allegation or proof that the amount of their bid is anything other than fair and reasonable, being the lowest of all bids submitted. Prom a judgment dissolving the restraining order and denying the plaintiffs any relief, they have appealed.

The two groups of respondents have jointly moved in this court for an order dismissing the appeal for the reasons that there has been a cessation of the contro *341 versy, and that the right of appellants, if any ever existed, to injunctive relief has ceased to exist.

Before the appeal was heard in this court, which occurred some four months after the judgment appealed from was entered and the notice of appeal given, it was made to appear that, a few days after the judgment of the superior court, the board of public works of the city being free from any restraining or injunctive order, and appreciating the existence of a situation approaching an emergency in the protection of the health and safety of the people of the city, entered into a written contract with Jahn & Bressi according to the terms of their bid, and returned to them, as required by ordinance and the published call for bids, their check or checks in an aggregate amount more than equal to the exact amount required to accompany their bid, which amounts had been placed with the board prior to any consideration of the bids other than to simply refer all of them to the engineer’s department for computation, and prior to the commencement of this action.

It further appears, without contradiction, that, after entering into such written agreement to construct the improvement, Jahn & Bressi, under directions of the board of public works, commenced within fifteen days the performance of their contract, and have at all times since vigorously continued to prosecute and perform it; that the value of the work done and the material placed on such improvement by Jahn & Bressi, according to the engineer’s estimate at the date of the showing in support of the motion to dismiss the appeal, was $68,678.66, of which there had been paid and was to be paid shortly the sum of $49,876.86; that Jahn & Bressi have paid a premium of $18,161.38 upon the surety bond securing the performance of their contract *342 in accordance with its terms and the terms of their hid; that they have obligated themselves upon various items of construction and material necessarily involved for use in the work to be done under the contract in an amount exceeding $520,000; that they have practically completed the clearing and grubbing required by their contract, have driven approximately one thousand feet of tunnel called for by the plans and specifications for the improvement and have lined the same with steel plates; that they have installed and constructed a power line upon the site of the improvement approximately four miles in length, and have procured and purchased a right of way for a construction railroad four miles long, from a station on the Chicago, Milwaukee & St. Paul Railroad to the site of the improvement; and that the materials contracted for by them are for the most part made specially for the particular improvement involved, and to that extent have no use or commercial value otherwise.

In opposing the motion to dismiss the appeal, the appellants insist upon and cite authorities from this and other jurisdictions in support of the power to grant injunctive relief. Of the existence of such power, there can not be any question. However, the pertinent inquiry here is whether, under all the circumstances of this case, that power should be exercised. In this record it is noticeable that the appellants seek no damages. Indeed, under the charter of the city and the call for bids in this case, the board of public works reserved the right to reject any and all bids, and it has rejected the bid of appellant and returned to it the certified check accompanying that bid. Nor can it be said that they can suffer as taxpayers, in the sense that a taxpayer’s suit is generally understood, for the reason that the money .used by the city in paying the *343 cost of the construction involved is not raised hy taxation or special assessment, but out of a special fund provided by the revenues of the public utility which is being bettered and extended, namely, the public water system of the city.

The whole record in this case shows that the sole purpose of the suit and the only relief sought is preventive in its character. To the extent it seeks to enjoin the city authorities from entering into a contract with Jahn & Bressi, the action has now become purposeless because that contract has been entered into, and to that extent the motion to dismiss should prevail under the rule in the case of Vollman v. Industrial Workers of the World, 79 Wash. 192, 140 Pac. 337, and cases there cited. To the extent it seeks to enjoin the carrying out of the contract by Jahn & Bressi, who intervened in the action, it is hostile to important financial interests of theirs, who, if allowed to fully perform and complete their contract, will in no way harm or injure the appellants, or either of them.'

The remedy by injunction is summary and extraordinary and the granting of it must always rest in the exercise of a sound discretion governed by the nature of the particular case. This principle, well established as it is, must be kept in mind in a just and fair consideration of the motion to dismiss this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

London v. City of Seattle
611 P.2d 781 (Washington Supreme Court, 1980)
Venegas v. United Farm Workers Union
552 P.2d 210 (Court of Appeals of Washington, 1976)
Bellingham American Publishing Co. v. Bellingham Publishing Co.
258 P. 836 (Washington Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
232 P. 300, 132 Wash. 339, 1925 Wash. LEXIS 782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goetz-v-russell-wash-1925.