Goeke v. Houston Lighting & Power Co.

761 S.W.2d 835, 1988 Tex. App. LEXIS 3319, 1988 WL 142637
CourtCourt of Appeals of Texas
DecidedNovember 30, 1988
Docket3-88-053-CV
StatusPublished
Cited by12 cases

This text of 761 S.W.2d 835 (Goeke v. Houston Lighting & Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goeke v. Houston Lighting & Power Co., 761 S.W.2d 835, 1988 Tex. App. LEXIS 3319, 1988 WL 142637 (Tex. Ct. App. 1988).

Opinion

POWERS, Justice.

Houston Lighting & Power Company sued the Public Utility Commission in district court for judicial review of a final order issued by the Commission in a contested case. Public Utility Regulatory Act (PURA), Tex.Rev.Civ.Stat.Ann. art. 1446c, § 69 (Supp.1988); Administrative Procedure and Texas Register Act (APTRA), Tex.Rev.Civ.Stat.Ann. art. 6252-13a, § 19 (Supp.1988). Charles Goeke, a party in the administrative proceeding, intervened in the suit. 1 The district court, after hearing, reversed the agency order and remanded the case to the Commission. Goeke, but not the Commission, appeals to this Court for the further judicial review authorized by APTRA § 20. We will affirm the judgment below.

THE AGENCY PROCEEDING

Houston Lighting & Power Company applied to the Commission for an amendment of the certificate of public convenience and necessity, issued by the agency, under which the company generates, distributes, and sells electric power in a large part of the State. The proposed amendment would authorize the company’s construction of a *838 high-voltage transmission line, traversing a path 100 to 150 feet wide and 46 miles in length, across the Texas counties of Harris, Waller, Austin and Washington. Goeke, joined by about 700 other residents of the three counties last named, intervened in the agency proceeding to oppose the proposed amendment in a 1984 hearing that extended intermittently over several months.

At the conclusion of the hearing, Commission employees (a hearings examiner and an administrative-law judge) delivered to the Commissioners an “Examiners’ Report” wherein they recommended approval of the company’s application, based upon the findings of fact, conclusions of law, and reasoning set forth in the report. Generally speaking, the report determined favorably to the application the ultimate finding PURA § 54(b) required the Commission to make before it might amend the company’s application: that the amendment “is necessary for the service, accommodation, convenience, or safety of the public.” The report also determined favorably to the application those factors the Commission was bound to consider in arriving at that ultimate finding:

(1) the adequacy of existing service, (2) the need for additional service, (3) the effect of the granting of a certificate on the recipient of the certificate and on any public utility of the same kind already serving the proximate area, and (4) on such factors as community values, recreational and park areas, historical and aesthetic values, environmental integrity, and the probable improvement of service or lowering of cost to consumers....
PURA § 54(c) (numbering added); Public Utility Commission v. Texland Elec. Co., 701 S.W.2d 261, 267 (Tex.App.1985, writ ref’d n.r.e.).
THE AGENCY ORDER
Contrary to the recommendation in the “Examiners’ Report,” the Commission denied the company’s application. In the order we now review, the three Commissioners set out differing views and decisions. Commissioners Thomas and Rosson concurred in denying the application on the following grounds:
* * * * * *
2. Houston Lighting and Power Company failed to meet its burden of proving that the need for the proposed ... line outweighs the detrimental impact of the proposed route on the factors set forth in [PURA § 54(c)]. Specifically, Houston Lighting and Power Company failed to present sufficient credible evidence to enable the Commission to weigh and make findings regarding the need for the line against the potential negative effects on the Section 54(c) criteria caused by the proposed route, especially in light of the concerns raised by the intervenors.
3. The Company failed to prove the sufficiency of the routing selection methodology which led to the selection of the proposed route in that it failed to convince the Commission that the methodology employed adequately considered alternative routes using existing rights-of-way and/or parallel lines.
******

Commissioner Thomas determined that the company had established a need for the line. So much is implied in the foregoing quotation from the order; the same is evident in the conclusions of law and findings of underlying fact Commissioner Thomas expressly adopted from the “Examiners’ Report.”

Commissioner Rosson concurred in denying the company’s application and agreed with the “reasons” stated by Commissioner Thomas, except she disagreed with him insofar as he had determined that the proposed line was needed. Commissioner Ros-son stated expressly her determination that the evidence did not show a need for the proposed line. Accordingly, she dissented from Commissioner Thomas’s adoption of six specific findings of underlying fact, included in the “Examiners’ Report,” that suggested a favorable determination of the “need” criterion of PURA § 54(c).

Commissioner Campbell dissented from the order denying the company’s application. She gave the following reasons for her dissent: (1) in its previous decision in *839 the case, the Commission had determined that a need existed for the proposed line and held the issue was not to be further litigated; (2) in denying the company’s application, Commissioners Thomas and Ros-son had not “found that the proposed route violated any of the criteria enunciated in § 54(c)”; (3) “[t]he sole issue has always been whether [the company] properly considered alternative routes,” which is the only ground upon which the two other Commissioners denied the application; and (4) that ground was an impermissible basis for denying the application in light of the holding in Frost v. Public Utility Commission, 672 S.W.2d 883 (Tex.App.1984, writ ref d n.r.e.). 2

No two Commissioners expressly adopted any findings of underlying fact recommended in the “Examiners’ Report.” Commissioner Thomas expressly adopted six. Commissioner Rosson impliedly adopted the same six because they were not listed among those from which she specifically dissented on the public-need factor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
761 S.W.2d 835, 1988 Tex. App. LEXIS 3319, 1988 WL 142637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goeke-v-houston-lighting-power-co-texapp-1988.