Goddard College CU

CourtVermont Superior Court
DecidedJanuary 6, 2014
Docket175-12-11 Vtec
StatusPublished

This text of Goddard College CU (Goddard College CU) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goddard College CU, (Vt. Ct. App. 2014).

Opinion

STATE OF VERMONT SUPERIOR COURT — ENVIRONMENTAL DIVISION

{ Goddard College Conditional Use { Docket No. 175-12-11 Vtec { Goddard College Act 250 Reconsideration { Docket No. 173-12-12 Vtec {

Decision on the Merits

The two matters pending before the Court relate to a proposal by Goddard College (Goddard) to replace its current 23 independent heating systems for 23 college buildings with a single woodchip heating system on Goddard’s property in the Town of Plainfield, Vermont. This proposed development requires both local and state (Act 250) approval. In the first matter, Rhea Wilson appeals a decision of the Town of Plainfield Development Review Board (DRB) finding that the site plan approval criteria were satisfied and granting Goddard a conditional use permit to construct a central woodchip heating system and building (Municipal Appeal). In the second matter, Karen Bouffard, Yvonne Byrd, Sam Davis, Rick Levy, Ken Smith, Dan Towner, and Rhea Wilson (Act 250 Appellants) appeal a September 10, 2012 District 5 Environmental Commission decision approving the construction of a woodchip heating system at Goddard, including a 2,469 square foot building, a woodchip storage area, distribution piping to 23 campus buildings, and an access roadway off of Vermont Route 214 (Act 250 Appeal). We considered the two pending matters in a coordinated single merits hearing to promote expeditious and fair proceedings pursuant to Vermont Rules for Environmental Court Proceedings Rule 2(b). The Court conducted a site visit at the subject property and surrounding area on the morning of October 1, 2013, followed by a merits hearing at the Environmental Division in Berlin, Vermont. Appearing at the site visit and merits hearing were Appellants and their attorney, Erick E. Titrud, Esq., and Goddard and its attorneys, Elizabeth H. Catlin, Esq. and Geoffrey H. Hand, Esq. Although the Town of Plainfield (the Town), represented by Robert Halpert, Esq., was active in pre-trial proceedings, it did not attend or participate in the site visit or merits hearing. Based upon the evidence presented at trial, including that which was put into context by the site visit, the Court renders the following Findings of Fact and Conclusions of Law.

1 Findings of Fact 1. Goddard is a private educational institution approved by the Vermont Department of Education. 2. Goddard’s campus is located on a single lot of land, comprising approximately 117 acres, within the Town’s Rural Residential Zoning District. 3. Goddard proposes to construct a woodchip heating system, primarily housed in a new standalone building, to provide heat and hot water to the existing campus buildings (the Project). 4. As proposed, the woodchip boiler building will be approximately 2,500 square feet in size. The building will be 25 to 29.5 feet wide and 90 feet long. The building will have a pitched or hip roof with asphalt shingles and vertical wood siding. 5. The Project has an 82-foot east side setback from the center of Route 214 and a 161-foot setback from the north property line. Both the southern and western parcel boundaries are considerable distances from the Project. 6. Two large overhead doors, both 12 feet wide by 15 feet tall, are located toward the eastern end of the south-facing side of the building. 7. The building is otherwise residential in character. 8. No outdoor storage areas are associated with the proposed building. 9. The building will be dark or medium brown and is generally south facing. As viewed from the south, the western end of the building will be 20 feet high and the eastern end will be 23 feet high. 10. A 35-foot-tall corten steel chimney, 24 inches in outside diameter, will be located at the back, or north side, of the building. The chimney will be dark brown. 11. The proposed building will only house the woodchip heating system, including the woodchip storage bins; it will not be used for classrooms, office space, storage space, or any other institution uses. 12. The Project will burn woodchips to heat water that will be circulated through underground pipes to 23 other existing buildings on campus. 13. The 23 buildings are presently heated by individual oil fired systems. 14. The woodchip fired boiler is manufactured by Messersmith, which has a good reputation. 15. The Project’s boiler has a thermal efficiency of approximately 80%.

2 16. Operation of the boiler is automated. The air/fuel ratio is continually adjusted to achieve thorough combustion. The unit uses a high temperature burn with both under fire and over fire successive stage burns, resulting in heightened thermal efficiency. 17. The Project will include an electrostatic precipitator (ESP) for added pollution control. Weise Environmental makes the ESP for Messersmith. 18. Ultrafine particles are less than 0.1 micron in size and are commonly generated by combustion, friction, and cooking. 19. The ESP equipment controls ultrafine particles. 20. The Project will accept deliveries of woodchips by tractor-trailer truck roughly once per week during colder seasons, with up to two deliveries per week during the coldest periods and less frequent deliveries during the summer. In total, Goddard expects the heating system to require roughly 36 tractor-trailer trips per year to supply woodchips. Woodchip deliveries will not take place on weekends or after 5:00 p.m. daily. Offloading of woodchips will take less than one-half hour to complete. 21. There are 10 to 15 other trucks presently on campus weekly, including kitchen supply delivery trucks, garbage trucks, and other supply trucks. 22. Woodchips will be delivered to one of the two overhead doors in the eastern section of the building. Trucks will unload chips using a “live bed” system that moves the chips off the truck without raising the truck bed. The trucks will leave the site after unloading the chips. 23. Chips will fall into a 14-foot-deep bin within the building. Chips will then be moved by conveyors to the boiler. 24. The Project will be accessed from Goddard’s main parking lot off Pitkin Road and Route 214. The Project’s access drive will take the place of an existing fire truck access clearing off of Route 214. The fire truck access will be permanently closed if the Project is constructed. 25. Existing trees will be retained to the east and north of the building. This will result in approximately 40 to 50 feet of treed buffer along most of Route 214. 26. Goddard will plant new trees and shrubs around three sides of the building and in the existing fire truck access area. Goddard will plant 50 evergreen trees along Route 214. These trees will range from 5 to 12 feet tall at planting. An additional 16 evergreens will be planted to the west of the building. Around the building, Goddard will plant 11 deciduous trees and 19 native shrubs which will mature at 8 to 10 feet in height.

3 27. Aboveground electric service will be provided to a pole approximately 20 feet east of the building. A 24-foot-wide-by-50-foot-long clearing in the trees will be required for this aboveground electric service. This clearing will be planted with Arrowwood, Nannyberry, Viburnum, and Serviceberry. 28. Underground electric lines will connect the pole to the building. Spruce, Fir, and Hemlock trees, 8 to 10 feet tall at planting, will be planted between the last power pole and the building in the area of the underground electric lines. 29. The Project will not require any new employees. 30. During cold weather a vapor plume may be visible from the chimney. 31. Vermont is in attainment with all National Ambient Air Quality Standards (NAAQS). 32. The American Meteorological Society/Environmental Protection Agency Regulatory Model (AERMOD) was used to model air quality for the Project. This modeling accounted for the topography of the Project area, meteorology, and building geometry, including air turbulence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Route 103 Quarry
2008 VT 88 (Supreme Court of Vermont, 2008)
In Re Rinkers, Inc.
2011 VT 78 (Supreme Court of Vermont, 2011)
In re Wildcat Construction Co.
648 A.2d 827 (Supreme Court of Vermont, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Goddard College CU, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goddard-college-cu-vtsuperct-2014.