GMS Mine Repair and Maintenance, Inc. v. Mountaineer Contractors, Inc.

CourtWest Virginia Supreme Court
DecidedApril 20, 2020
Docket19-0309
StatusPublished

This text of GMS Mine Repair and Maintenance, Inc. v. Mountaineer Contractors, Inc. (GMS Mine Repair and Maintenance, Inc. v. Mountaineer Contractors, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GMS Mine Repair and Maintenance, Inc. v. Mountaineer Contractors, Inc., (W. Va. 2020).

Opinion

STATE OF WEST VIRGINIA SUPREME COURT OF APPEALS

GMS Mine Repair and Maintenance, Inc., d/b/a GMS Construction, Defendant Below, Petitioner FILED vs.) No. 19-0309 (Pocahontas County 16-C-58) April 20, 2020 EDYTHE NASH GAISER, CLERK SUPREME COURT OF APPEALS Mountaineer Contractors, Inc., OF WEST VIRGINIA

Plaintiff Below, Respondent

MEMORANDUM DECISION

Petitioner GMS Mine Repair and Maintenance, Inc., d/b/a GMS Construction, by counsel William C. Means, appeals the Circuit Court of Pocahontas County’s February 27, 2019, order denying its motion for judgment as a matter of law or, alternatively, a new trial following a jury trial on respondent’s breach of contract and promissory estoppel claims. Respondent Mountaineer Contractors, Inc., by counsel Joshua S. Rogers and David R. Stone, filed a response. Petitioner filed a reply.

This Court has considered the parties’ briefs and the record on appeal. The facts and legal arguments are adequately presented, and the decisional process would not be significantly aided by oral argument. Upon consideration of the standard of review, the briefs, and the record presented, the Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision affirming the circuit court’s order is appropriate under Rule 21 of the Rules of Appellate Procedure.

After soliciting bids in accordance with state law, the West Virginia Department of Transportation, Division of Highways (“DOH”), awarded Respondent Mountaineer Contractors, Inc. (“MCI”) a contract for a sidewalk repair project at Hillsboro Elementary School in Pocahontas County, West Virginia, on June 15, 2016. This contract provided that the project would be completed by or on August 26, 2016, and would begin with a “Notice to Proceed.” It was further agreed between the DOH and MCI that time was of the essence.

Before submitting its bid to the DOH, MCI solicited a bid from Petitioner GMS Mine Repair and Maintenance, Inc., d/b/a GMS Construction (“GMS Construction”). GMS Construction submitted a bid on May 9, 2016, stating that the requested work could be performed for $210,165.75. Because MCI failed to account for West Virginia Code of State Rules § 157-3-10.1, however—requiring that it “shall perform, with his or her own organization, work amounting to not less than 30 percent of the total contract cost” (“30% rule”)—it required GMS Construction to submit a revised bid excluding concrete, which MCI planned to provide to bring it in line with the 30% rule. On June 17, 2016, GMS Construction submitted its revised

1 bid, which contained terms identical to those in its initial bid save for the provision of concrete. GMS Construction quoted a price of $124,124.75. The parties did not execute a subcontractor agreement.

Despite indicating otherwise in its contract with MCI, the DOH did not issue its notice to proceed until September 30, 2016. GMS Construction began working at the site at some point in November of 2016, but it ceased working before completing the job. GMS Construction informed MCI that the change in seasons, increased school traffic, and MCI’s failure to provide necessary support services, such as effective traffic management, rendered the project incompletable at the quoted price, and it requested a modification. After MCI declined to provide additional compensation, GMS Construction withdrew from the worksite.

On December 27, 2016, MCI sued GMS Construction for breach of contract and promissory estoppel. GMS Construction moved for summary judgment, arguing that the parties had no enforceable agreement due to the failure to comply with West Virginia Code of State Rules § 157-3-10.1.a (“subcontract regulation”), which requires that subcontracts be in writing. 1 The circuit court denied this motion, and the three-day trial on MCI’s claims began on October 31, 2018. The jury found that no contract existed between the parties; however, it found GMS Construction liable under the doctrine of promissory estoppel, and it awarded damages in the amount of $105,475.87.

Following trial, GMS Construction moved for judgment as a matter of law or, alternatively, a new trial. GMS Construction argued that the court erred in failing to instruct the jury on the subcontract regulation, that it “watered down” GMS Construction’s jury instruction on the 30% rule by describing it as “context for testimony,” that it erred in failing to give an instruction on time being of the essence, and that MCI could not lawfully pursue a promissory estoppel claim.

The circuit court denied GMS Construction’s post-trial motion on February 27, 2019. Preliminarily, the court concluded that GMS Construction’s motion for judgment as a matter of law was untimely in light of its failure to make that motion before the case was submitted to the jury. 2 The court further found that GMS Construction was not entitled to a new trial. It found that GMS Construction was not unduly prejudiced by the court’s refusal to give the requested instructions or its commentary regarding the instruction on the 30% rule. Finally, the court noted that GMS Construction raised an objection to the promissory estoppel instruction for the first time at the hearing on its post-trial motion. The court found the objection waived, but it also concluded that the instruction properly stated the applicable law. Petitioner now appeals.

1 This DOH regulation provides, in part, that “[e]ach subcontract, including lower-tier subcontracts, shall be in writing and shall physically contain all the applicable provisions, requirements, and specifications.” W. Va. Code R. § 157-3-10.1.a. 2 GMS Construction does not challenge this conclusion on appeal.

2 In reviewing a circuit court’s rulings on a motion for a new trial, this Court employs an abuse of discretion standard of review. Tennant v. Marion Health Care Found., 194 W. Va. 97, 104, 459 S.E.2d 374, 381 (1995).

Thus, in reviewing challenges to findings and rulings made by a circuit court, we apply a two-pronged deferential standard of review. We review the rulings of the circuit court concerning a new trial and its conclusion as to the existence of reversible error under an abuse of discretion standard, and we review the circuit court’s underlying factual findings under a clearly erroneous standard. Questions of law are subject to a de novo review.

Id.

GMS Construction raises five assignments of error on appeal, one of which concerns the circuit court’s denial of its motion for summary judgment on MCI’s promissory estoppel claim. GMS Construction argues that the parties’ failure to abide by the subcontract regulation and reduce their subcontract to writing precludes recovery under promissory estoppel. GMS Construction acknowledges that various statutes of frauds “are amenable to promissory estoppel exceptions,” but claims that “no such exception presently exists.” In support of its assertion that subcontracts of this sort must be reduced to writing, it cites Knotts v. Board of Education of the Independent District of Bridgeport, 113 W. Va. 56, 166 S.E. 703 (1932), Burgess v. City of Cameron, 113 W. Va. 127, 166 S.E. 113 (1932), and English Moving & Storage Co. v. Public Service Commission of West Virginia, 143 W. Va. 146, 100 S.E.2d 407 (1957). These cases, GMS Construction contends, stand for the propositions that where taxpayer money is spent on public works, the requirement to reduce a contract to writing cannot be ignored, and that “there are legal consequences for noncompliance with applicable law.”

We review de novo a circuit court’s denial of a motion for summary judgment. Syl. Pt. 1, Findley v. State Farm Mut. Auto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Findley v. State Farm Mutual Automobile Insurance
576 S.E.2d 807 (West Virginia Supreme Court, 2003)
Everett v. Brown
321 S.E.2d 685 (West Virginia Supreme Court, 1984)
State v. Miller
459 S.E.2d 114 (West Virginia Supreme Court, 1995)
Tennant v. Marion Health Care Foundation, Inc.
459 S.E.2d 374 (West Virginia Supreme Court, 1995)
Hoover v. Moran
662 S.E.2d 711 (West Virginia Supreme Court, 2008)
Maples v. West Virginia Department of Commerce
475 S.E.2d 410 (West Virginia Supreme Court, 1996)
English Moving & Storage Co. v. Public Service Commission
100 S.E.2d 407 (West Virginia Supreme Court, 1957)
Foster v. Sakhai
559 S.E.2d 53 (West Virginia Supreme Court, 2001)
Shia v. Chvasta
377 S.E.2d 644 (West Virginia Supreme Court, 1988)
Burgess v. City of Cameron
166 S.E. 113 (West Virginia Supreme Court, 1932)
Knotts v. Board of Education
166 S.E. 703 (West Virginia Supreme Court, 1932)
Honaker v. Board of Education
32 L.R.A. 413 (West Virginia Supreme Court, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
GMS Mine Repair and Maintenance, Inc. v. Mountaineer Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gms-mine-repair-and-maintenance-inc-v-mountaineer-contractors-inc-wva-2020.