G.M. Sloan Mosaic & Tile Co. v. Newman/Lustig & Associates

557 N.E.2d 403, 199 Ill. App. 3d 518
CourtAppellate Court of Illinois
DecidedJuly 18, 1990
Docket1-88-3139
StatusPublished
Cited by8 cases

This text of 557 N.E.2d 403 (G.M. Sloan Mosaic & Tile Co. v. Newman/Lustig & Associates) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G.M. Sloan Mosaic & Tile Co. v. Newman/Lustig & Associates, 557 N.E.2d 403, 199 Ill. App. 3d 518 (Ill. Ct. App. 1990).

Opinion

PRESIDING JUSTICE CERDA

delivered the opinion of the court:

Plaintiff, G.M. Sloan Mosaic & Tile Co., recovered breach of contract damages after a jury trial against defendant, Newman/Lustig & Associates. Michael Lustig (Lustig) and defendant appeal from the trial court’s award of attorney fees and costs against them, and defendant also appeals from an award against it of prejudgment interest.

Plaintiff’s amended complaint alleged that defendant owed plaintiff $13,100 under a contract for goods and services but refused repeated demands for payment.

Defendant’s answer, which was verified by Lustig as defendant’s president and which was filed on August 18, 1986, denied that plaintiff provided any services and materials to it, that plaintiff demanded payment, that defendant refused to pay, that defendant entered into any agreements with plaintiff, and that defendant was liable for the debt. Defendant alleged that any services were provided to Gardner & North Construction Company (Gardner) and that inadequate materials provided by plaintiff were delivered late and in a disruptive manner that injured defendant.

Plaintiff moved for summary judgment on January 22, 1988. The supporting affidavit of Jerry Janik, an employee of plaintiff, swore that Atul Karkanis signed the contract and that plaintiff performed the resilient tiling work according to the contract. Defendant’s response to the motion filed March 24, 1988, argued that there were disputed issues of fact whether plaintiff had an action against defendant or against Gardner and whether plaintiff was entitled to recover due to its failure to timely perform the contract. Lustig’s supporting affidavit was also filed March 24, 1988, and stated that: (1) Gardner was the general contractor in connection with construction work performed at K&S Photographies, Inc.; (2) defendant was the architect; (3) Gardner orally employed plaintiff to perform the tile subcontract; (4) plaintiff failed to perform the work prior to December 28, 1984; (5) plaintiff requested a written confirmation of the contract that was prepared with a definite completion date of January 4, 1985; (6) plaintiff did not complete the work until March 1, 1985; (7) plaintiff never completed all the required work; and (8) Atul Karkanis was Gardner’s employee and was not authorized to contract on behalf of defendant.

Plaintiff's motion for summary judgment was denied, and on June 23, 1988, a jury returned a verdict in favor of plaintiff for $12,400. The trial transcript does not appear in the record, but filed as a supplemental record by plaintiff was a copy of defendant’s exhibit No. 1, a May 7, 1985, letter in which plaintiff requested payment of $12,400 from Lustig prior to anything being “done about the 2nd or 3rd. [sic] floor.”

Plaintiff filed a motion on July 19, 1988, for attorney fees and expenses pursuant to section 2—611 of the Illinois Code of Civil Procedure (111. Rev. Stat. 1987, ch. 110, par. 2—611) on the basis that defendant’s verified answer denied that plaintiff provided any services and materials to defendant, that defendant owed plaintiff $13,100, that plaintiff demanded payment, and that defendant refused to pay. Plaintiff argued that defendant had no reasonable cause to make these denials and that the jury had found these denials to be untrue. Plaintiff further argued that defendant’s failure to produce any credible evidence to establish its denial of its contractual allegations demonstrated that defendant knew its denials were false. Allegedly as a result of these denials, plaintiff had to proceed to trial to collect the debt at a cost of $7,329.67. Attached as an exhibit to the motion was an itemized statement of plaintiff’s attorney’s services, which included pretrial work.

Plaintiff also filed a motion for an award of prejudgment statutory interest of $2,089.02. Plaintiff argued that the contract was an instrument of writing within the meaning of the Illinois statute governing payment of prejudgment interest (Ill. Rev. Stat. 1987, ch. 17, par. 6402) and that the amount of the debt was ascertainable.

The trial court found that plaintiff was entitled to prejudgment interest because the amount of the debt was easily ascertainable by simple and certain computation, because an exhibit admitted into evidence indicated that this amount was demanded prior to the completion of further work, and because defendant made no effort to settle or to participate meaningfully before pretrial conferences.

After plaintiff’s attorney testified that the total attorney fees would be $7,329.67, the trial court granted the motion for attorney fees. The trial court noted that Lustig had “invited” the lawsuit, found that defendant’s defense was frivolous, and imposed sanctions of fees of $6,920 and disbursements of $380.64 against Lustig personally.

Lustig and defendant argue on appeal that: (1) the trial court erred in imposing sanctions against Lustig because the version of section 2—611 in effect at the time defendant filed its answer subjected only the party pleading the untrue allegations to sanctions (Ill. Rev. Stat. 1985, ch. 110, par. 2—611); (2) the trial court violated Lustig’s due process rights to notice and the opportunity to defend himself because plaintiff had sought fees only against defendant and not against Lustig; (3) plaintiff did not allege or establish that defendant’s denials were untrue; (4) the verdict in plaintiff’s favor was insufficient under section 2—611 to establish an untrue denial; (5) the fact that the verdict was for an amount less than that prayed for demonstrated as a matter of law the reasonableness of defendant’s denial of damages and that defendant’s answer was not sanctionable; (6) the jury’s verdict in a smaller amount demonstrated that even if defendant had admitted liability, defendant was entitled to a trial on damages, and that, therefore, sanctions were improper because plaintiff’s trial expenses could not have been caused by defendant’s pleading; and (7) plaintiff provided a statement of all the fees and costs incurred without designating those expenses it incurred as a result of defendant’s denial of liability.

Procedural due process requires notice, an opportunity to respond, and a hearing before sanctions may be imposed. (See Roadway Express, Inc. v. Piper (1980), 447 U.S. 752, 767, 65 L. Ed. 2d 488, 501-02, 100 S. Ct. 2455, 2464 (attorney fees should not be assessed as a sanction without fair notice and an opportunity for a hearing on the record); Miranda v. Southern Pacific Transportation Co. (9th Cir. 1983), 710 F.2d 516, 522 (sanctions should not be imposed against attorneys without notice, an opportunity to respond, and a hearing).) Sanctions were sought by plaintiff only against defendant so that non-party Lustig did not have fair notice, prior to the trial court’s sua sponte imposition of sanctions against him, of the possibility that he would be sanctioned. Lustig was thereby deprived of a meaningful opportunity to defend his actions. On this basis, the trial court’s imposition of sanctions against Lustig is reversed.

It is also argued that sanctions could not be imposed because the untruth of the denial was not established because the verdict was less than what was prayed for in the complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
557 N.E.2d 403, 199 Ill. App. 3d 518, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gm-sloan-mosaic-tile-co-v-newmanlustig-associates-illappct-1990.