Globe Contracting v. Hour

2025 UT App 98
CourtCourt of Appeals of Utah
DecidedJuly 3, 2025
DocketCase No. 20240058-CA
StatusPublished
Cited by3 cases

This text of 2025 UT App 98 (Globe Contracting v. Hour) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Globe Contracting v. Hour, 2025 UT App 98 (Utah Ct. App. 2025).

Opinion

2025 UT App 98

THE UTAH COURT OF APPEALS

GLOBE CONTRACTING LLC, Appellee, v. RAYMOND R. HOUR, KIMBERLY TAING, HOUR TAING ENTERPRISE LLC, AND HOUR CHIROPRACTIC CLINIC INC., Appellants.

Opinion No. 20240058-CA Filed July 3, 2025

Third District Court, Salt Lake Department The Honorable Coral Sanchez No. 170900003

Jeffrey T. Colemere, Tamara J. Hauge, and Emily Adams, Attorneys for Appellants Benjamin S. Ruesch, Tony G. Jones, Travis Dunsmoor, and Jeannette Barney, Attorneys for Appellee

JUDGE RYAN D. TENNEY authored this Opinion, in which JUDGES GREGORY K. ORME and JOHN D. LUTHY concurred.

TENNEY, Judge:

¶1 Dr. Raymond Hour and Globe Contracting LLC (Globe) entered into a contract in which Globe agreed to construct an office building for Hour’s chiropractic clinic. After Hour failed to make the last three payments that were due under the contract, Globe sued, raising several causes of action relating to breach of contract. Hour counterclaimed, asserting that Globe had breached the contract first—and, as a result, that Hour had been justified in not continuing to pay Globe for its work. At the close of a bench trial, the district court ruled that Hour had breached the contract and that he had no justification for doing so. In its findings of fact Globe Contracting v. Hour

and conclusions of law, the district court awarded Globe damages. And after several months of posttrial litigation, the court ordered Hour to pay prejudgment interest, costs, and attorney fees.

¶2 Hour raises several issues on appeal. For the reasons set forth below, we rule as follows:

• First, we affirm the district court’s determinations that Hour was liable for breach of contract (and the other associated claims).

• Second, we affirm the district court’s calculation of Globe’s damages.

• Third, we reverse the district court’s awards of prejudgment interest and costs to Globe, and we remand for further proceedings on those awards.

• Finally, we reverse the district court’s award of attorney fees to Globe, and we remand for further proceedings on that award.

BACKGROUND 1

Contract and Dispute

¶3 Hour is a chiropractor, and Globe is a licensed general contractor. In October 2015, Hour and Globe agreed to a contract under which Globe would construct an office building for Hour’s

1. “On appeal from a bench trial, we view and recite the evidence in the light most favorable to the trial court’s findings; we present additional evidence only as necessary to understand the issues on appeal.” Bountiful City v. Sisch, 2023 UT App 141, n.1, 540 P.3d 1164 (quotation simplified).

20240058-CA 2 2025 UT App 98 Globe Contracting v. Hour

chiropractic clinic. Under the terms of the contract, Hour was to pay Globe $650,000 “subject to additions and deductions for written change orders.” Hour was required to pay Globe through monthly “progress payments” that were due 30 days after Globe sent Hour an application for payment, and Globe’s applications for payment were to be sent “on or before the 30th day of each month for labor and materials delivered to the jobsite during the month.”

¶4 The contract stated that the monthly progress payments could be “withheld” under four delineated circumstances:

1. Work is found defective and not remedied;

2. [Globe] does not make prompt and proper payments to subcontractor;

3. [Globe] does not make prompt and proper payments for labor, materials, or equipment furnished;

4. Another contractor is damaged by an act for which [Globe] is responsible.

¶5 The contract provided that construction was to “begin within seven (7) days after issuance of building permit,” that work was to “be substantially completed two-hundred and ten (210) days after issuance of building permit,” and that “[a]ny request for additional days [was to] be treated as a request for a change order, and must be in writing before it will be considered by” Hour. The contract further provided that the “times stated in” the contract could be “extended by a change order” by Hour or when Globe was “delayed in work progress by changes ordered, . . . weather, . . . or other causes beyond [Globe’s] control or which justif[ied] the delay.”

20240058-CA 3 2025 UT App 98 Globe Contracting v. Hour

¶6 The contract also stated that if Globe “default[ed] in performances of any provision” from the contract “or fail[ed] to carry out the construction in accordance with the provision of the contract documents,” Hour was entitled to “terminate” the contract “on thirty (30) days written notice to” Globe, or to instead not terminate the contract but “make good the deficiency of which the default consists, and deduct the cost from the progress payment then or to become due to” Globe. Finally, the contract contained an attorney fee provision, which stated that if “any action is filed in relation to this Agreement, the unsuccessful party in the action shall pay to the successful party, in addition to all the sums that either party may be called on to pay, a reasonable sum for the successful party’s attorney fees.”

¶7 The city issued a building permit on December 1, 2015. As a result, a construction expert later testified at trial (and no party has disputed on appeal) that, under the contract’s 210-day provision, construction was expected to begin on December 7, 2015, and be “substantially completed” by July 5, 2016. In late 2015 and early 2016, however, there were construction delays caused by “abnormally cold weather,” “rain fall and subsequent mud,” and the discovery of “[c]oncealed debris” on the building site.

¶8 On June 7, 2016, Hour, through his attorney, sent a letter to Globe stating that “as of this time, it is apparent that there is no way the work can be completed by [the required] date.” Hour informed Globe that he was giving “notice pursuant to the contract that [Globe was] in default” and that he was also giving “30 days notice of his termination of the contract.” On July 18, 2016, Hour’s attorney sent another letter to Globe stating that because “the building [was] not substantially completed within two hundred and ten days as required” by the contract, Globe was “in default” and the contract was “no longer binding on . . . Hour.”

¶9 But although these letters spoke of “termination,” Hour later informed Globe that he would give it “till the end of

20240058-CA 4 2025 UT App 98 Globe Contracting v. Hour

September” to complete the project. 2 Moreover, during construction, “Hour initiated 24 changes” to the project, “most of which were substantial changes that affected the finished portions of construction and were initiated after the date of Hour’s 30-day notice to terminate” the contract “for lack of progress,” and at least some of which were requested after the July 2016 letter.

¶10 Hour made timely payments for the first seven progress payments, the seventh of which was linked to the June pay application. But Hour did not make the eighth, ninth, or tenth progress payments, which were due, respectively, at the end of August, September, and October. Even though Hour stopped paying, Globe continued with its construction work until the end of September 2016.

¶11 On September 22, 2016, Hour notified Globe that he was dissatisfied with the quality of the workmanship. On September 28, 2016, Hour terminated the contract. As of September 28, however, both Hour and a new contractor that he had hired to take over the project believed that the project “was substantially complete.” The next day, the city performed a “scheduled” inspection for temporary occupancy. The building did not pass the inspection because, among other reasons, the stairwell doors were not fire rated.

Complaint, Counterclaim, and Pretrial Litigation

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hasemeyer v. Lefevre
Court of Appeals of Utah, 2026
Tripp v. Zen Zone Homes
Court of Appeals of Utah, 2026
OLoughlin v. AESA Enterprises
2026 UT App 41 (Court of Appeals of Utah, 2026)
Gallegos v. One Commerce Street
2025 UT App 196 (Court of Appeals of Utah, 2025)
CWS v. Montgomery
2025 UT App 183 (Court of Appeals of Utah, 2025)
Pera v. Glide Transportation
2025 UT App 167 (Court of Appeals of Utah, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2025 UT App 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/globe-contracting-v-hour-utahctapp-2025.