Global Minerals Corporation v. Nucor Steel Tuscaloosa, Inc.

490 F. App'x 239
CourtCourt of Appeals for the Eleventh Circuit
DecidedSeptember 20, 2012
Docket12-12186
StatusUnpublished

This text of 490 F. App'x 239 (Global Minerals Corporation v. Nucor Steel Tuscaloosa, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Global Minerals Corporation v. Nucor Steel Tuscaloosa, Inc., 490 F. App'x 239 (11th Cir. 2012).

Opinion

PER CURIAM:

Global Minerals Corporation (Global) appeals from the district court’s grant of summary judgment in favor of defendants Nucor Steel Tuscaloosa, Inc. (NSTI) and Nucor Corporation (NC) in this breach-of-contract action. 1 Because we agree with the district court that there was no breach, we affirm.

I.

NC is the largest steel producer in the United States and owns NSTI, which is engaged in the production of steel using raw minerals such as ferrosilicon. In February 2008, NSTI purchasing supervisor James Yerkes requested from several entities a price quote for ferrosilicon. Although Global’s quote was not the lowest, NSTI agreed to a trial order from Global to qualify Global for future purchases. In March 2008, NSTI and Global entered into a deal for 100 net tons of ferrosilicon to be delivered from October through December of that year. The purchase order (PO) explained: “NSTI makes no commitment or guarantee with regard to the actual quantity of product released under this purchase order. However, shall not exceed 100 net tons without agreement with Global Minerals.” There is no dispute that both parties fulfilled their obligations under this contract.

During the spring of 2008, the price of ferrosilicon rose rapidly. To ensure that it had sufficient supply, NSTI issued another PO on June 3, 2008 (the June PO), before the trial delivery period even began but subject to satisfactory performance of the trial order. In the June PO, NSTI ordered 600 net tons of ferrosilicon to be delivered between September and December 2008 at the price of $1.48 per pound. This quantity was changed to 600 metric tons at Global’s request. The June PO contained the same “no commitment of guarantee with regard to the actual quantity of product released under this purchase order” language, as well as the “not to exceed” language.

Thereafter, the demand for, and price of, ferrosilicon dropped. Yerkes approached Global to renegotiate the price, but Global declined to do so. From September through December 2008, NSTI took delivery of only 29.79 tons from the June PO. On December 29, 2008, Yerkes sent an email to Global’s vice president of sales, Dan Ritter, informing Ritter that NSTI *241 would not be taking any more ferrosilicon under the June PO. Yerkes advised Ritter that NSTI needed much less ferrosilicon than anticipated due to business conditions and the recession.

By email, Ritter responded that the June PO was a contract for a set quantity of ferrosilicon, and he requested that NSTI purchase the remaining tons under the terms of the contract. In a follow-up email, Ritter wrote that NSTI was obligated to purchase an amount “reasonably proportionate” to the quantity given in the contract, which it had not done.

Although Yerkes believed NSTI had fulfilled its obligations under the June PO, on January 9, 2009, Yerkes contacted Ritter with the following offer: NSTI would extend the contract through the first half of 2009 and would take all of its purchase requirements from Global during that time. 2 Yerkes explained that there was no volume guarantee, and it offered to pay low market price plus $.39 per pound. 3 Ritter responded with two offers, each proposing that NSTI purchase the remaining amount of the original 600 tons by the first half of 2009, with an additional purchase at an agreed-upon price. By email, Yerkes informed Ritter that the counteroffers were unacceptable and that NSTI’s offer was nonnegotiable. Ritter responded that he was not happy to take the loss but would accept the offer in the hope that NSTI and Global could continue to work together.

After Ritter accepted NSTI’s terms, Yerkes issued a change order on January 15, 2009 (the January PO). This document was identical to the June PO and had the same order number, but the words “change order” were stamped diagonally across each page, the description specified “ADDENDUM 1/15/2009,” and the due date was marked as June 30, 2009. The January PO stated:

This change order is issued to extend the end date of this blanket order until June 30, 2009, based on a sincere request from Global Minerals to do so. Given the economic situation and that Nucor will help our supplier base, at time, this order is extended. NSTI continues to make no commitment or guarantee with regard to the actual quantity of product released under this purchase order. However, NSTI will take all of its purchase requirements during this period January through July 2009 from Global Minerals. The price shall be changed to a formula basis, as Ryan’s Notes Low for the month prior to the month of shipment plus $.39 per pound.... A price cap of $1.48 per pound ... shall also be in effect. This change is confirmed with Dan Ritter on January 13, 2009 and per email proposal from Jim Yerkes to Dan Ritter dated January 9, 2009. By Jim Yerkes-January 15, 2009.

After seeing the January PO, Ritter emailed Yerkes, “it looks like what we discussed on the phone and email so lets get it going.”

NSTI purchased only about 120 tons under the January PO. NSTI did not purchase ferrosilicon from any other distributor, but it did take delivery of some of its own stored inventory that had been purchased earlier from entities other than Global.

*242 In November 2009, Global’s president Michael Xu contacted Yerkes to request that NSTI extend the January PO to 2010 to purchase the remaining 400 tons of fer-rosilicon Global was warehousing. After NSTI declined, Global filed the instant breach-of-contract action naming as defendants NSTI and its parent company, NC. 4

Both parties moved for summary judgment. Global argued that each PO was a separate contract and that the January PO could not be a modification to the June PO because it was entered into after the time to perform under the June PO had passed. Global also argued that NC was liable under agency theory. NSTI argued that there was no breach because the January PO was an accord and satisfaction and a substitute agreement. NSTI also noted that the January PO was a requirements contract with no volume guarantee, and NSTI had adhered to the terms by purchasing only from Global during the relevant time period. Finally, NC argued that it was not liable because there was no agency relationship, it had no role in the contracts, and there was no basis to pierce the corporate veil.

The district court granted NSTI’s summary judgment motion, finding no breach of contract. Specifically, the court found that there was only one contract — the June PO — and the January PO was a change order to that contract. In reaching this conclusion, the court considered the emails between Yerkes and Ritter leading up to the January PO, but the court explained that it would reach the same result even if confined to the “four corners” of the January PO. The court then found that the January PO created a requirements contract, which contained neither an estimate nor a specific quantity, but only a maximum purchase amount of 600 tons. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Access Now, Inc. v. Southwest Airlines Co.
385 F.3d 1324 (Eleventh Circuit, 2004)
Shiver v. Chertoff
549 F.3d 1342 (Eleventh Circuit, 2008)
Robinson v. Tyson Foods, Inc.
595 F.3d 1269 (Eleventh Circuit, 2010)
Horowitch v. DIAMOND AIRCRAFT INDUSTRIES, INC.
645 F.3d 1254 (Eleventh Circuit, 2011)
Ex Parte Dan Tucker Auto Sales, Inc.
718 So. 2d 33 (Supreme Court of Alabama, 1998)
La Trace v. Webster
17 So. 3d 1210 (Court of Civil Appeals of Alabama, 2008)
Cook's Pest Control, Inc. v. Rebar
28 So. 3d 716 (Supreme Court of Alabama, 2009)
Simcala, Inc. v. American Coal Trade, Inc.
821 So. 2d 197 (Supreme Court of Alabama, 2001)
BOARD OF WATER & SEWER COM'RS v. Bill Harbert Const. Co.
870 So. 2d 699 (Supreme Court of Alabama, 2003)
Barnett v. Quinn
979 So. 2d 816 (Court of Civil Appeals of Alabama, 2007)
Cavalier Mfg., Inc. v. Clarke
862 So. 2d 634 (Supreme Court of Alabama, 2003)
Safeco Insurance Co. of America v. Graybar Electric Co.
59 So. 3d 649 (Supreme Court of Alabama, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
490 F. App'x 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/global-minerals-corporation-v-nucor-steel-tuscaloosa-inc-ca11-2012.