Global Engineering & Construction, LLC

CourtArmed Services Board of Contract Appeals
DecidedApril 1, 2016
DocketASBCA No. 60072, 60073, 60074, 60075, 60076, 60077
StatusPublished

This text of Global Engineering & Construction, LLC (Global Engineering & Construction, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Global Engineering & Construction, LLC, (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Global Engineering & Construction, LLC ) ASBCA Nos. 60072, 60073, 60074 ) 60075,60076,60077 ) Under Contract No. W912DY-12-D-0013 )

APPEARANCES FOR THE APPELLANT: Johnathan M. Bailey, Esq. Kristin E. Zachman, Esq. Bailey & Bailey, P.C. San Antonio, TX

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Steven W. Feldman, Esq. Clay Weisenberger, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Huntsville

OPINION BY ADMINISTRATIVE JUDGE DELMAN ON THE GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

The U.S. Army Corps of Engineers (government) moves to dismiss these appeals for lack of jurisdiction. The contractor, Global Engineering & Construction, LLC (Global or appellant), opposes dismissal. 1 For reasons stated below, we dismiss the appeals for lack of jurisdiction.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 11July2012, appellant was awarded Contract No. W912DY-12-D-0013 under a Multiple Award Task Order Contract (MATOC) for design and construction services at various military medical facilities under the Army's Medical Repair and

1 The government's original motion sought dismissal of the appeals based upon, inter alia, the failure of Global to submit a properly filed claim to the contracting officer. In supplemental briefing, the government took a different tact, contending that appellant did file a proper claim but that it failed to timely appeal the contracting officer's decision denying the claim, and hence dismissal of the appeals is warranted on this basis. Renewal (MRR) Program (R4, tab 1). 2 The MRR Program, administered by the U.S. Army Corps of Engineer's Engineering and Support Center in Huntsville, Alabama, is a fast-track method for design and execution of all types of facility repairs, renovations, conversions, alterations, additions and construction projects. The actual work to be performed under the MATOC was to be competitively awarded to the MATOC awardees through issuance of task orders.

2. In September 2013, the government issued three task orders for construction services to appellant: Task Order (TO) 0002, Aviation Survival Training Center in Lemoore, California, for the firm-fixed-price of $7,805,355.06 (R4, tab 2); TO 0003, Aviation Survival Training Center in Oak Harbor (Whidbey Island), Washington, for the firm-fixed-price of$3,132,015.02 (ASBCA Nos. 60074, 60075 R4, tab 2); and TO 0004, Pain/Neuro/TBI Clinic in Fort Sill, Oklahoma, for the firm-fixed-price of$5,069,304.14 (ASBCA Nos. 60076, 60077 R4, tab 2).

3. During the performance of these TOs, the parties joined issue on certain staffing requirements for the projects. In brief, the government was of the view that appellant was required under the contract and each TO to provide two separate individuals to perform the three roles of site superintendent, on-site quality control manager, and site safety and health officer. Appellant was of the view that it was permitted to use one person on each project to perform all three functions.

4. The government issued three letters to appellant on or about 12 February 2015, directing appellant to provide an additional person as an on-site quality control manager for TOs 0002, 0003, and 0004. Appellant disputed the government's position by letter dated 18 February 2015, contending that it was providing what was required by the contract. (R4, tab 5 at 6)

5. By letter to appellant dated 26 March 2015, the contracting officer (CO) directed appellant to provide a second person for each project by 30 March 2015 (R4, tab 5 at 10). Appellant responded by email letter of the same date, stating, in part, that it would provide such a person under protest. It considered the government's direction a change to the contract for which it was entitled to an equitable adjustment. Appellant stated: "As soon as these costs are known, a CDA claim for such costs will be submitted." (Id. at 13)

6. Appellant failed to provide the second person for the project under TO 0004 by 30 March as directed by the government. On 31 March 2015, the CO suspended

2 References to the Rule 4 file will be to ASBCA Nos. 60072 and 60073 unless otherwise indicated.

2 the work under TO 0004 pending appellant's compliance (ASBCA Nos. 60076, 60077 R4, tab 5 at 15-17).

7. On 31 March 2015 appellant submitted invoices to the government for work performed on each TO. The government rejected the invoices. By email letter dated 31 March appellant objected, stating that the rejection was without basis and demanding that the government immediately rescind the rejection. Appellant did not demand a payment in a sum certain, nor did it seek an interpretation or adjustment of contract terms or any other relief with respect to the staffing issue. (R4, tab 5 at 17-18)

8. By email to appellant dated 2 April 2015, "Subject: Payment Retainage on Current and Future Invoices" the CO stated as follows:

Due to the non-conformance of providing the required second person on site for Ft. Sill, Lemoore, and Whidbey Island, the current rejected invoices and all future invoices will be short paid to cover the costs of additional person and potential damages (same cost as for the second person) due to non-conformance.

The CO stated that the government would withhold $185,597.76 ($30,932.96 to be spread over six invoices) under TO 0002; $214,428.48 ($42,885.70 to be spread over five invoices) under TO 0003; and $220,735.20 ($31,533.60 to be spread over seven invoices) under TO 0004. (R4, tab 5 at 29)

9. The 2 April 2015 email concluded as follows:

The current invoices that were recently rejected will be accepted, but will be reduced by the amount specified above for each task order. Once projects are completed and projects are deemed acceptable, we will release the extra retainage being held for damages. Also occurring at the end of each project, a modification will be issued for the reduction of the cost for the mandatory second person on sight [sic] on each task order.

(R4, tab 5 at 29) (Emphasis added) The email did not state it was a CO's decision and did not inform appellant of any rights of appeal. By email dated 3 April 2015, appellant acknowledged receipt of the government's email, and stated that it did "not agree that the Government's claim has any merit" (id. at 31).

3 10. By letter to the CO dated 28 May 2015, referencing all three TOs, appellant's counsel asserted that appellant should be reimbursed for the monies improperly withheld by the government and also for appellant's expenses to comply with the government's directive of 26 March 2015. The total amount sought by appellant was in excess of $100,000, but appellant did not provide a claim certification. (R4, tab 5 at 35-70) 3

11. By email and letter dated 19 June 2015, the CO replied to appellant's 28 May letter, disagreeing with appellant's contract interpretation. The CO ended the letter by stating: "Based on the foregoing, we consider your request for an equitable adjustment to be without merit. Should you have any questions regarding this matter, please do not hesitate to contact myself." This email also did not state it was a CO's decision and also did not inform appellant of any rights of appeal. (R4, tab 5 at 71-74)

12. On 13 July 2015, appellant filed six notices of appeal with this Board. Each notice of appeal (NOA) stated that the appeal was from the "April 2, 2015 decision of the Contracting Officer."4

13. Appellant filed two NOAs for each TO, one from the government's retainage for "potential damages," and one from the government's withholdings related to the staffing issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Global Engineering & Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/global-engineering-construction-llc-asbca-2016.