Global Energy Services, Inc v. US Applicators LLC

CourtDistrict Court, M.D. Louisiana
DecidedMarch 5, 2020
Docket3:18-cv-00512
StatusUnknown

This text of Global Energy Services, Inc v. US Applicators LLC (Global Energy Services, Inc v. US Applicators LLC) is published on Counsel Stack Legal Research, covering District Court, M.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Global Energy Services, Inc v. US Applicators LLC, (M.D. La. 2020).

Opinion

UNITED STATES DISTRICT COURT

MIDDLE DISTRICT OF LOUISIANA

GLOBAL ENERGY SERVICES, INC. CIVIL ACTION VERSUS NO. 18-512-JWD-EWD US APPLICATORS, LLC

RULING AND ORDER This matter comes before the Court on US Applicators LLC’s (“US Applicators” or “Defendant”) Motion for Partial Summary Judgment on Breach of Contract. (Doc. 38.) Plaintiff Global Energy Services, Inc. (“Global” or “Plaintiff”) opposes the motion (Doc. 48), and US Applicators has filed a reply (Doc. 51). Oral argument is not necessary. The Court has carefully considered the law, the facts in the record, and the arguments and submissions of the parties and is prepared to rule. I. Introduction Global entered into a Contract Order with Entergy Louisiana, LLC (“Entergy”) to perform vegetation management work along Entergy’s rights of way. Global then entered into a Subcontract with US Applicators under which US Applicators would perform some of Global’s work for Entergy (specifically, applying foliar herbicide). The central issue in this motion is whether all reasonable jurors would conclude that the Subcontract was unambiguous with respect to how US Applicators was to be paid. US Applicators argues that the Subcontract is unambiguous and that they should be paid “at the contracted rate for the number of line miles Global assigned to US Applicators.” This is because: (1) The Subcontract says that US Applicators shall be paid for the same quantities of work that Entergy pays to Global, and the prime contract between Entergy and Global requires payment by the line mile; and (2) US Applicators is obligated to guarantee that 100% of the line miles Global assigned to US Applicators met Entergy’s specifications, which require 100% herbicide coverage with 95% efficacy. Thus, if any line Global assigned US Applicators failed to meet these standards, Global could require US Applicators to retreat the lines at US Applicators’ expense.

Global responds that the Subcontract only required Global to pay US Applicators for the total miles in each circuit that US Applicators sprayed with herbicide. According to Global, if there was no spraying in a given mile, then there should be no billing. Global argues that the Subcontract is ambiguous, or, at the very least, unambiguous in a way that supports Global’s argument. Having carefully considered the matter, the Court finds that US Applicators has the better position. All reasonable jurors would find that the Subcontract was unambiguous and that, within the four corners of that document, US Applicators was to be paid at the contracted rate for the number of line miles Global assigned to US Applicators. Global’s position is wholly unsupported by the record (to which it provides few if any citations), contrary to the plain language of the agreement, leads to absurd consequences, and is at odds with the equities of the Subcontract. Accordingly, partial summary judgment is granted in US Applicators’ favor on this issue. II. Relevant Factual Background A. The Contract Order Effective December 15, 2016, Global entered into a Contract Order (the “Contract Order”) with Entergy whereby Global would perform Vegetation Management services on Entergy’s rights of way for 2017–18. (US Applicators’ Statement of Uncontested Material Facts (“SUMF”) ¶ 1, Doc 38-2; Global’s Concise Statement of Material Facts (“CSMF”), Doc. 48-1.)1 The Scope of

1 Global failed to rebut virtually all of the factual assertions in US Applicators’ SUMF. (See CSMF, Doc. 48-1.) The relevant local rule in effect at the time US Applicators filed its motion provided, “All material facts set forth in the statement required to be served by the moving party will be deemed admitted, for purposes of the motion, unless controverted as required by this Rule.” M.D. La. LR 56(b) (2019); see also AmeriHealth Caritas Louisiana, Inc. v. Work for the Contract Order included “network line mile trimming, reactive work, capital work, special projects, and small local storm work.” (SUMF ¶ 2.) The network line mile trimming generally is the tree trimming along the right of way, while reactive work, capital work, special projects, and small storm work are one-off projects that Global performs in addition to the line-

mile trimming. (SUMF ¶ 3.) Under the Contract Order, Global was awarded network line mile trimming on nine different Networks over the 2017–18 timeframe: Amite/Bogalusa; Bastrop; Denham Springs/Gonzales; Hammond; Lafayette; Lake Charles/Sulphur; Port Allen/Zachary; West Monroe; and Labadieville/Reserve. (SUMF ¶ 4.) Each Network is comprised of multiple “Circuits,” or “area[s] from a substation that feeds a certain amount of customers.” (SUMF ¶ 5.) B. The Subcontract - Generally On May 5, 2017, Global and US Applicators executed a Subcontract Agreement (“Subcontract”) whereby US Applicators would apply “herbicide/pesticide along Entergy right of way as identified by GES project personnel.” (SUMF ¶ 6.) The Subcontract provides that it is to

be construed in accordance with Maine law. (SUMF ¶ 7.) Mario Martinez was one of the “GES project personnel” who assigned work to US Applicators. (SUMF ¶ 8.) Martinez explained that he assigned circuits to US Applicators by providing a map of the circuit and, at US Applicators’ request, provided the total feeder miles.

Promise Hosp. of Ascension, Inc., No. 16-484, 2018 WL 1370599, at *1 n.1 (M.D. La. Mar. 16, 2018) (deGravelles, J.). As a result, the Court will deem almost all of the facts in US Applicators’ SUMF admitted for purposes of this motion. See AmeriHealth, 2018 WL 1370599, at *1 n.1. Further, the Court notes that Global failed to provide almost any record citations in its memorandum in support and its CSMF in violation of the Rule 56. See Fed. R. Civ. P. 56(c)(1) (“A party asserting that a fact cannot be or is genuinely disputed must support the assertion by: (A) citing to particular parts of materials in the record, . . .”); Ragas v. Tennessee Gas Pipeline Co., 136 F.3d 455, 458 (5th Cir. 1998) (citations and quotations omitted). Nevertheless, the Court has thoroughly reviewed the extrinsic evidence submitted by Global. (See Pl. Ex. B, Aff. of Kevin Pomerleau, Doc. 48-3; Dep. of Steven Hoover, Doc. 48-4.) However, the Court need not supplement its presentation of the facts with this evidence because, as will be explained below, (1) the Court finds that the Subcontract is unambiguous as a matter of law, and thus (2) no parole evidence is admissible to interpret this agreement. (SUMF 49.) At times Global only assigned partial circuits to US Applicators because a portion of the circuit had already been completed by Global and approved by Entergy. (SUMF ¥ 10.) Section 1.1 of the Subcontract provides, “The Contractor [Global] employs the Subcontractor [US Applicators] as an independent contractor to perform all work set forth in Exhibit A, .. . (hereinafter called Subcontractor’s Work), a part of the work that the Contractor has contracted with the Owner [Entergy] to provide on the Project.” (SUMF § 11; Def. Ex. D, USAPP000158, Doc. 34-5 at 1.) Specifically, US Applicators’ work was part of the network line mile trimming Global agreed to provide for Entergy under the Contract Order. (SUMF 4 12.) US Applicators’ work was unrelated to Global’s reactive, capital, special project, or small local storm work. (SUMF ¥ 13.) C. The Subcontract - Payment Exhibit B to the Subcontract provided that US Applicators will be paid by the mile for “‘the Work performed,” including “all operations required to complete the Work in conformance with the Contract Documents”:

EXHIBIT B PAYMENT SCHEDULE

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Liquid Air Corp.
37 F.3d 1069 (Fifth Circuit, 1994)
Ragas v. Tennessee Gas Pipeline Co.
136 F.3d 455 (Fifth Circuit, 1998)
Darryl W. Elliott v. S.D. Warren Company
134 F.3d 1 (First Circuit, 1998)
City of Augusta v. Quirion
436 A.2d 388 (Supreme Judicial Court of Maine, 1981)
Champagne v. Victory Homes, Inc.
2006 ME 58 (Supreme Judicial Court of Maine, 2006)
Acadia Insurance Co. v. Buck Construction Co.
2000 ME 154 (Supreme Judicial Court of Maine, 2000)
American Protection Insurance v. Acadia Insurance Co.
2003 ME 6 (Supreme Judicial Court of Maine, 2003)
Portland Valve, Inc. v. Rockwood Systems Corp.
460 A.2d 1383 (Supreme Judicial Court of Maine, 1983)
V.I.P., Inc. v. First Tree Development Ltd. Liability Co.
2001 ME 73 (Supreme Judicial Court of Maine, 2001)
Matthew Eastwick v. Cate Street Capital, Inc.
2017 ME 206 (Supreme Judicial Court of Maine, 2017)
Farrington's Owners' Ass'n v. Conway Lake Resorts, Inc.
2005 ME 93 (Supreme Judicial Court of Maine, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Global Energy Services, Inc v. US Applicators LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/global-energy-services-inc-v-us-applicators-llc-lamd-2020.