GLOBAL COMPANIES LLC & Others v. HOP ENERGY, LLC, & Others.

Massachusetts Appeals Court·Decided June 16, 2025·No. 23-P-0935·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-935

GLOBAL COMPANIES LLC & others 1

vs.

HOP ENERGY, LLC, & others. 2

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

Defendant HOP Energy, LLC (HOP), appeals from a judgment

entered against it on the plaintiffs' breach of contract claim

following the parties' cross motions for summary judgment. 3 HOP

raises several arguments, and we address each in turn.

1. Service of process. HOP's first argument is that the

plaintiffs did not effectuate service on it within the ninety-

day period set out in Mass. R. Civ. P. 4 (j), as appearing in

402 Mass. 1401 (1988). The original complaint was served outside the ninety days, but a judge of the Superior Court (the first judge) allowed a motion to enlarge the time for service of process. An extension may be obtained upon a showing of "good cause." Id. See Commissioner of Revenue v. Carrigan, 45 Mass. App. Ct. 309, 311, 314 n.5 (1998).

The judge wrote that the extension was allowed "without prejudice to the defendants contesting service of process and its timeliness." This is a strange formulation, as it appears to indicate that the judge allowed the motion without determining whether there was "good cause" for allowing the extension. HOP argues that there was no such good cause. Even if that was what the judge meant, however, we need not determine, in this case, whether good cause was indeed shown. We conclude that even if the original complaint was late served, there was no prejudice to HOP.

To begin with, although we need not rely upon it, the fact is that at the time the motion was allowed, the statute of limitations had not expired. See G. L. c. 260, §§ 1, 2. 4 Thus, had the motion been denied or HOP's motion to dismiss allowed, the plaintiffs could simply have refiled the complaint and

served it -- which is in essence what they did. While still within the time period for filing suit, the plaintiffs in fact filed an amended complaint, which is the operative one, and served it within ninety days of its filing. In these circumstances, where there can, therefore, have been no prejudice to HOP, it would elevate form over substance to dismiss this case on the basis of late service of the original complaint.

2. The merits. Turning to the merits of the judgment, this case arises out of an injury suffered by John Trudel, an employee of HOP, on premises leased to HOP by plaintiff Chelsea Sandwich LLC. The lease agreement contained a provision pertaining to HOP's insurance obligations. It stated that HOP would:

"take out and maintain throughout the Term [of the lease] . . . : Comprehensive liability insurance insuring Landlord and Tenant against all claims and demands for any injury to persons or property which may be claimed to have occurred on the Premises or on the sidewalk or ways adjoining the Premises, in an amount equal to not less than One Million Dollars." HOP did have a commercial general liability policy issued by defendant First Mercury Insurance Company (First Mercury), which was effective at the time of the injury. The policy provided that First Mercury would "have the right and duty to defend the insured against any 'suit' seeking" damages "because

of 'bodily injury' or 'property damage' to which this insurance applies."

Trudel never brought a "suit" against the plaintiffs. He did make a claim against the plaintiffs, which First Mercury refused to defend. After First Mercury's refusal to become involved, the plaintiffs settled the claim for $365,000, which their own insurer, plaintiff Liberty International Underwriters (Liberty) paid.

A second judge, who heard the plaintiffs' and HOP's crossmotions for summary judgment, concluded that HOP had failed to obtain the insurance which it had agreed in the lease to obtain, i.e., insurance against all claims and demands, not only against all suits; that this failure was a breach of contract; and that, consequently, the plaintiffs were injured in the amount of the settlement and the costs of defending against the claim.

a. Construction of the lease and insurance contract. We review the judge's construction of the lease and the insurance policy de novo. See James B. Nutter & Co. v. Estate of Murphy, 478 Mass. 664, 667 (2018). We agree that the plain language of the lease required HOP to obtain insurance broader than that it obtained from First Mercury. There is no error in the second judge's construction of the lease or the insurance policy.

HOP argues that the second judge erred by ignoring the conclusions of the first judge, who ruled in favor of First

Mercury on its earlier motion for summary judgment. HOP argues that the first judge's conclusions are "the law of the case." Vittands v. Sudduth, 49 Mass. App. Ct. 401, 413 n.19 (2000) ("The 'law of the case' doctrine reflects the reluctance of a second judge to rule differently from the first judge on a case, issue, or question of fact or law once decided by final judgment or on appeal").

This argument is of no avail, as the basis of the first judge's entry of summary judgment in favor of First Mercury was precisely that it did not breach its obligation by failing to defend against what was only a claim and not a suit. This is precisely the reasoning of the second judge.

b. First Mercury's refusal to defend the claim. HOP also argues that the reason First Mercury did not defend the claim was that the plaintiffs failed to provide it with information it requested.

Pursuant to the lease, HOP provided the plaintiffs with certificates of insurance covering most of the Global entities except Chelsea Sandwich LLC, a wholly-owned subsidiary of Global Partners LP. Chelsea Sandwich LLC is, in fact, the only entity that is a signatory to the lease and that is named as the landlord in the lease. 5 It is true that in its final

communication with certain of the plaintiffs, 6 First Mercury asked for documentation showing that Global Companies LLC was a landlord listed in the lease or that the insurance provision covered affiliates of the landlord, given that, after reviewing the lease, First Mercury concluded that only Chelsea Sandwich LLC was listed as a landlord.

But, in an earlier communication, First Mercury also said that in the absence of any litigation, it was not obligated to defend. In its motion for summary judgment, First Mercury stated that it had no such obligation because of the terms of the insurance policy, and the first judge, who ruled on that motion, agreed. Likewise, in the order allowing the plaintiffs' motion for summary judgment against HOP, the second judge concluded that the claim by Trudel was not covered under the terms of the insurance policy. Again, we agree with that reading of the policy, and, consequently, the failure of some of the plaintiffs to respond to the questions posed in the e-mail message sent by First Mercury is ultimately irrelevant to this case. We note also that even if the plaintiffs had satisfied First Mercury that Chelsea Sandwich LLC was a named insured

under the policy, First Mercury still would have refused to defend, as the policy did not cover Trudel's claim, regardless of who the named insureds were.

Free access — add to your briefcase to read the full text and ask questions with AI

GLOBAL COMPANIES LLC & Others v. HOP ENERGY, LLC, & Others., (Mass. Ct. App. 2025).

GLOBAL COMPANIES LLC & Others v. HOP ENERGY, LLC, & Others. (GLOBAL COMPANIES LLC & Others v. HOP ENERGY, LLC, & Others.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Frost v. Porter Leasing Corp.
436 N.E.2d 387 (Massachusetts Supreme Judicial Court, 1982)
Correllas v. Viveiros
572 N.E.2d 7 (Massachusetts Supreme Judicial Court, 1991)
Fabre v. Walton
802 N.E.2d 1030 (Massachusetts Supreme Judicial Court, 2004)
Commissioner of Revenue v. Carrigan
698 N.E.2d 23 (Massachusetts Appeals Court, 1998)
Vittands v. Sudduth
730 N.E.2d 325 (Massachusetts Appeals Court, 2000)
Commonwealth v. Williams
827 N.E.2d 1281 (Massachusetts Appeals Court, 2005)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)