GLF Construction Corporation v. Fedcon Joint Venture
This text of GLF Construction Corporation v. Fedcon Joint Venture (GLF Construction Corporation v. Fedcon Joint Venture) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF FLORIDA TAMPA DIVISION
UNITED STATES OF AMERICA for the use and benefit of GLF CONSTRUCTION CORPORATION, a Florida profit corporation,
Plaintiff,
v. Case No: 8:17-cv-01932-T-36AAS Consolidated with: Case No. 8:17-cv-02650-T-36TGW FEDCON JOINT VENTURE, a Florida joint venture, DAVID BOLAND, INC., a Florida profit corporation, JT CONSTRUCTION ENTERPRISE CORPORATION, and WESTERN SURETY COMPANY,
Defendants. ____________________________________
FEDCON JOINT VENTURE,
Counter-Plaintiff,
v.
GLF CONSTRUCTION CORPORATION and FIDELITY AND DEPOSIT COMPANY OF MARYLAND,
Counter-Defendants. ___________________________________/
O R D E R This cause comes before the Court upon the Amended Motion to Strike Defendants’ Proposed Findings of Fact and Conclusions of Law as Improper Argument Including Certification Pursuant to Local Rule 3.01(g) (the “Motion”), filed by GLF Construction Corporation (“GLF”) and Fidelity & Deposit Company of Maryland (“F&D”). Doc. 254. FEDCON Joint Venture, David Boland, Inc., JT Construction Enterprise Corporation, and Western Surety Company (collectively, “Defendants”) responded in opposition, Doc. 255, to which GLF and F&D replied, Doc. 258. Having considered the parties’ submissions and being fully advised in the premises, the Court will deny the Motion.
BACKGROUND The Court held a thirteen-day bench trial on these consolidated actions during October and December of 2019. The Court directed the parties to provide oral closing arguments, rather than written closing arguments. On the final day of trial, before closing arguments, Defendants advised the Court of “supplemental authority or additional research we’ve done upon the evidence as it’s come in at trial.” Doc. 244 at 8:6–11. The Court decided to address this matter after closing arguments. Id. at 8:12–13. Following closing arguments, the Court advised, “It may be that you can incorporate any updates in your conclusions of law . . . .” Id. at 94:18–20. Defendants’ counsel stated his belief that Defendants could “incorporate the additional authority that we’ve covered [which] we believe
is quite relevant” into proposed findings of fact and conclusions of law. Id. at 95:20–25. Defendants’ counsel wanted to ensure that Defendants “wouldn’t be bound by only what we cited in our initial brief.” Id. at 95:24–25, 96:1. The Court replied, “No. You can incorporate that into your proposed findings of fact and conclusions of law to the fact that they are supplemental cases or supplemental authority.” Id. at 96:2–5. Counsel for GLF and F&D then asked to receive “some notification” of any “supplemental authority” relied upon by Defendants prior to Defendants filing proposed findings of fact and conclusions of law, akin to when GLF and F&D filed a notice of supplemental authority for a then-recently decided case during trial. Id. at 96:9–21. According to counsel for GLF and F&D, “that would be helpful” in case “there’s anything else then that [he] might have to address from a legal standpoint . . . .” Id. at 96:14–17. Defendants’ counsel responded that he had no problem with providing counsel for GLF and F&D with any “additional authority” that Defendants relied upon in its proposed findings and conclusions. After the Court granted the parties an extension of time to file proposed findings of fact
and conclusions of law, Doc. 247, the parties did so on May 1, 2020, Docs. 249, 251. Prior to filing their Proposed Findings of Fact and Conclusions of Law, Defendants filed their Notice of Authority, in which they gave “notice of the following authority substantively cited in their proposed Findings of Fact and Conclusions of Law.” Doc. 248 at 2. Defendants advised that the cited cases did not constitute “new or supplemental authority, but, given the parties’ stipulation at the conclusion of trial, are submitted in an abundance of caution.” Id. GLF and F&D filed their Notice of New and Supplemental Authority after filing their Proposed Findings of Fact and Conclusions of Law. Doc. 250. Therein, GLF and F&D gave notice of “new and supplemental authority substantively cited in their Proposed Findings of Fact and Conclusions of Law.” Id. at 1–2. Now, through the Motion, GLF and F&D move the Court to strike the proposed conclusions
of law in Defendants’ Proposed Finding of Fact and Conclusions of Law. Doc. 254 at 9–10. GLF and F&D contend that they have been prejudiced by Defendants’ “complete disregard of the Court’s directions as to no written closing arguments and only supplemental cases and supplemental authority being included in a party’s proposed Conclusions of Law.” Id. at 9. ANALYSIS The Motion is due to be denied. At the outset, the Motion lacks a memorandum of law. Indeed, the Motion does not provide any legal authority for the requested relief. The Local Rules require a motion or other application for an order to include a memorandum of legal authority in support of the request. Local R. M.D. Fla. 3.01(a). This deficiency alone warrants denying the Motion. Next, GLF and F&D’s attack on Defendants’ provision of legal authority in their Proposed Findings of Fact and Conclusions of Law that was not included in their trial brief is undercut by the recognition that GLF and F&D’s Proposed Findings of Fact and Conclusions of Law also provides legal authority not included in their trial brief.
Further, even if the Court assumes that Defendants disregarded certain instructions, the Court is not persuaded that striking proposed conclusions of law is an appropriate form of relief. In the absence of any offered legal standard, the Court looks to Rule 12(f), which governs motions to strike. See ZSR Patlayici Sanayi A.S. v. Sarac Distribs. LLC, No. 2:19-cv-864-FtM-39MRM, 2020 WL 1065231, at *4 n.5 (M.D. Fla. Mar. 5, 2020) (“Federal Rule of Civil Procedure 12(f) governs motions to strike. [The movant] does not cite Rule 12(f) or argue entitlement under it, so the request [to strike exhibits attached to the complaint under Federal Rule of Evidence 408] could be denied on this basis alone.”). Rule 12(f) provides that a court may “strike from a pleading an insufficient defense or any redundant, immaterial, impertinent, or scandalous matter.” Fed. R. Civ. P. 12(f) (emphasis added). “Pleadings” consist of only: a complaint, an answer to a complaint, an
answer to a counterclaim designated as a counterclaim, an answer to a crossclaim, a third-party complaint, an answer to a third party complaint, and a reply to an answer (if the court orders such reply). Fed. R. Civ. P. 7(a). Numerous courts within the Eleventh Circuit have held that motions to strike filings that do not constitute pleadings, as defined by Rule 7(a), are improper. See, e.g., Jallali v. Am. Osteopathic Ass’n, No. 11-60604-CIV, 2011 WL 2039532, at *1 (S.D. Fla. May 25, 2001); Croom v. Balkwall, 672 F. Supp. 2d 1280, 1285 (M.D. Fla. 2009); Inter-Tel, Inc. v. W. Coast Aircraft Eng’g, Inc., No. 8:04-cv-2224-T-17MSS, 2005 WL 2431267, at *2 (M.D. Fla. Oct. 3, 2005). GLF and F&D concede in their reply that they could have labeled the Motion as a motion for contempt, motion for sanctions, or another type of motion. Doc. 258 at 3. Significantly, the purpose of proposed findings of fact and conclusions of law is to provide the Court with findings and conclusions to fashion its own findings and conclusions.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
GLF Construction Corporation v. Fedcon Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glf-construction-corporation-v-fedcon-joint-venture-flmd-2021.