Glens of Ironduff Property Owners Ass'n v. Daly

735 S.E.2d 445, 224 N.C. App. 217, 2012 N.C. App. LEXIS 1359
CourtCourt of Appeals of North Carolina
DecidedDecember 4, 2012
DocketNo. COA12-52
StatusPublished
Cited by5 cases

This text of 735 S.E.2d 445 (Glens of Ironduff Property Owners Ass'n v. Daly) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glens of Ironduff Property Owners Ass'n v. Daly, 735 S.E.2d 445, 224 N.C. App. 217, 2012 N.C. App. LEXIS 1359 (N.C. Ct. App. 2012).

Opinion

GEER, Judge.

Plaintiff The Glens of Ironduff Property Owners Association, Inc. (“the Association”) appeals from an order granting summary judgment to defendants John E. Daly and Constance V. Daly (“the Dalys”). Based on our review of the record, we hold that the trial court properly determined that the Association’s claims were barred by the statute of repose, and we accordingly affirm the summary judgment order.

[218]*218Facts

The Dalys were the developers of The Glens of Ironduff (“The Glens”), a planned community in Haywood County, North Carolina. The Dalys purchased the lánd that became The Glens in September 2001. At that time, there was an existing unpaved farm road that ultimately became part of Coyote Hollow Road. The road ran approximately parallel to a stream that was about 10 feet below the road. The slope from the road down to the stream was at a 65 to 70 degree angle.

The farm road had been compacted with stones and rocks embedded in the ground. At some point before March 2004, the Dalys widened the farm road for use by lot owners in The Glens. During that process, the stones and rocks were removed by a bulldozer and replaced with packed dirt. Upon completion of the widening of the road, the Dalys began using the road for construction traffic to build two houses. The road continued to be used for construction and by individuals who purchased lots accessed by the road.

In 2005, the Dalys paved the road. Custom Paving placed six inches of stone and two inches of hotmix asphalt on the roadway. The paving did not, however, involve any change in the grade of the road, the width of the road, or the slope of the stream bank.

In the fall of 2009, a portion of the stream bank adjacent to the road eroded and slid down to the stream. At this point in the roadway, there ceased to be any shoulder to the road. The Association hired Alpha Environmental Sciences, Inc. to evaluate the roadway embankment. The consultant determined that “[b]oth the steepness of the slope and the undercutting from the creek appear to be causing the ongoing slope failure.”

On 15 January 2010, the Association, a homeowners association including all of the property owners within The Glens, wrote Mr. Daly regarding the erosion of the bank, which could eventually render the road impassable. The Association requested that Mr. Daly either fix the road or agree to reimburse the Association for the cost of eliminating the hazard.

On 30 March 2010, the Association filed suit against the Dalys asserting claims for breach of the warranty of workmanship, negligent construction, contribution and indemnification, and violation of the Sedimentation Pollution Control Act of 1973. The complaint alleged that the Dalys had negligently designed and constructed the road and that negligence was the proximate cause of the road slip[219]*219ping and falling into the adjacent creek. The complaint sought damages in the amount of $36,500.00.

Subsequently, the Association filed an amended complaint and a second amended complaint. The second amended complaint asserted only a claim for breach of implied warranty of workmanship and fitness for purpose and a claim for negligent construction. The second amended complaint sought damages in excess of $10,000.00. The Dalys denied the material allegations of the complaint and alleged that the Association’s claims were barred by the statute of limitations and statute of repose.

The Dalys subsequently filed a motion for summary judgment supported by an affidavit from John E. Daly and the Association’s discovery responses. The Association opposed the motion with the affidavits of William Allen, Secretary of the Association and a property owner whose only access to his home was over the eroded road, and Francis D. Brown, the person who sold the land to the Dalys. The Association also provided the trial court with the Dalys’ discovery responses, a report from a consultant who had evaluated the eroded bank, and the response to a subpoena served on an engineer retained by the Association to remedy the hazardous road condition.

At the hearing on the motion for summary judgment, defendants contended that the Association’s claims were barred by the three-year statute of limitations and the six-year statute of repose, that the Association lacked standing to assert a claim of implied warranty, that the Association was contributorily negligent, and that the damages in the case were not reasonably foreseeable. On 28 September 2011, the trial court entered an order concluding, based on its review of the evidence, that “there is no genuine issue as to any material fact and that Defendants are entitle[d] to judgment as a matter of law.” The court, therefore, entered summary judgment in favor of the Dalys and against the Association. The Association timely appealed to this Court.

Discussion

“Our standard of review of an appeal from summary judgment is de novo; such judgment is appropriate only when the record shows that ‘there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law.’ ” In re Will of Jones, 362 N.C. 569, 573, 669 S.E.2d 572, 576 (2008) (quoting Forbis v. Neal, 361 N.C. 519, 524, 649 S.E.2d 382, 385 (2007)).

[220]*220We first address whether summary judgment was appropriate based on the statute of repose set out in N.C. Gen. Stat. § l-50(a)(5) (2011). See Whittaker v. Todd, 176 N.C. App. 185, 187, 625 S.E.2d 860, 861 (2006) (holding that N.C. Gen. Stat. § l-50(a)(5) “is a statute of repose and provides an outside limit of six years for bringing an action coming within its terms”). N.C. Gen. Stat. § l-50(a)(5)(a) provides: “No action to recover damages based upon or arising out of the defective or unsafe condition of an improvement to real property shall be brought more than six years from the later of the specific last act or omission of the defendant giving rise to the cause of action or substantial completion of the improvement.”

“Whether a statute of repose has run is a question of law.” Mitchell v. Mitchell’s Formal Wear, Inc., 168 N.C. App. 212, 215, 606 S.E.2d 704, 706 (2005). "Summary judgment is proper if the pleadings or proof show without contradiction that the statute of repose has expired.” Bryant v. Don Galloway Homes, Inc., 147 N.C. App. 655, 657, 556 S.E.2d 597, 600 (2001).

Here, the Association points to the paving of the road in 2005 and argues that the road was not substantially completed until paved and, in any event, the paving was the last act or omission giving rise to its causes of action. Since this action was filed on 30 March 2010, under the Association’s analysis of the facts, the action would be timely for purposes of the statute of repose.

The statute defines “substantial completion” as “that degree of completion of a project, improvement or specified area or portion thereof (in accordance with the contract, as modified by any change orders agreed to by the parties) upon attainment of which the owner can use the same for the purpose for which it was intended.” N.C. Gen. Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Autry v. Bill Clark Homes
Court of Appeals of North Carolina, 2022
BDM Invs. v. Lenhil, Inc.
826 S.E.2d 746 (Court of Appeals of North Carolina, 2019)
Glover v. Charlotte-Mecklenburg Hosp. Auth.
817 S.E.2d 919 (Court of Appeals of North Carolina, 2018)
Glens of Ironduff Prop. Owners Ass'n, Inc. v. Daly
Supreme Court of North Carolina, 2014
Christie v. Hartley Construction, Inc.
745 S.E.2d 60 (Court of Appeals of North Carolina, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
735 S.E.2d 445, 224 N.C. App. 217, 2012 N.C. App. LEXIS 1359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glens-of-ironduff-property-owners-assn-v-daly-ncctapp-2012.